83 N.J.L. 728 | N.J. | 1912
The opinion of the court was delivered by
This writ of error, running to the Supreme Court, brings to test the judgment of that court in setting aside a resolution of the town council of the town of Bloomfield, adopted March 6th, 1911, and all proceedings thereunder. The resolution thus removed authorized and directed the mayor and clerk to enter into and execute on behalf of the municipality a supplementary agreement with the rail
d’he original contract, dated July 12th, 1910, had been sanctioned by an ordinance, and had for its purpose the abolition of grade crossings in the town.
The prosecutor, the defendant in error in this court, owned the land upon which its manufacturing plant is located, abutting on Mechanic street, which ran between the railroad and the prosecutor’s property, and enjoyed the use of a switch or industrial siding from the main line of the railroad across Mechanic street at grade, to the prosecutor’s lands. The scheme to elevate embodied the vacation of Mechanic street, and the substitution in lieu of the former industrial switch, of an elevated siding to leave the main line in its elevated position, and thence to he carried upon abutments to the prosecutor’s lands.
The vacation of Mechanic street was in fact accomplished before the date of the resolution under review, and the work under the original contract had progressed so far tha t the railroad tracks had been moved westerly within the limits of what was formerly Mechanic street. The work of replacing the industrial siding in its proposed elevated position had so far advanced that the abutments had been completed for it to pass from the main tracks. Possession of the land, lying within the hounds of Mechanic street (vacated), reverting to the prosecutor upon its vacation, had been permitted to the railroad company, and the industrial sidings formerly existing had been removed.
A petition had been presented to the council on January 3d, 1931, for the opening of. a new street, which, for convenience, may be called ISTew Mechanic street, to run practically parallel to old Mechanic street, close to, but westerly of its site, and
“The town shall indemnify and save harmless the railroad companies and their respective successors and assigns from and against all claims, demands, suits, actions, damages, costs and expenses ' which the railroad companies or either of them shall incur or be subjected to, by or on account of the American Malleables Company and Iledden Iron Construction Company and all persons whomever by reason of the omission or elimination or failure to reconstruct and maintain an industrial siding or switch leading from the main tracks of the railroad companies to the lands and property of the American Malleables Company.
It is argued in behalf of the town that, by the decision of the Supreme Court, there has been a denial of power, under the existing legislation, to enter into a contract such as the one under consideration is. "Undoubtedly, sufficient power has been given by the legislature, to enable the town to contract for changes in streets, their vacation or opening, for the purposes of securing safety to the public, by means of the elimination of grade crossings, and thereby promote the interest of the municipalities. Such contracts, when properly made, the municipalities have plenary power to carry into execution, by proper municipal proceedings, in the manner provided by their respective charters. Morris & Cummings Dredging Co. v. Jersey City, 35 Vroom 587, and, of course, incidentally, the structures to be erected may be made sightly, perhaps to the point of being ornamental. Morris and Essex Railroad Co. v. Newark, 47 Id. 559. Nor can the power to alter and amend such a contract be doubted, provided such alterations and amendments concern those matters which are included in the objects of the legislation in question, namely, the security of life and property, effected by change of grade in railroad tracks. But the abandonment of the proposed industrial sidings, at the time of the change in the original contract, did not .tend to this purpose. Their proposed reconstruction was to be upon private properties, and thus the agreement to do away with them did not tend to promote the public good, or to confer anjr advantage upon the public.
Moreover, the opening of New Mechanic street was no part of the pj'oposed work, as set forth in the original ordinance. It may be true that the subject had been mooted during the progress of the development of the elevation .scheme, and that certain independent steps may have been instituted, looking
If the contracting parties had, in their supplemental agreement, provided for the opening of the new street, as incidental to the work of the elevation, and for the abolition of the sidings, as obstructive to such new street, and dangerous to the public, a different question would have been presented for decision.
The present agreement deals only with structures upon private property, except that it provides for the expenditure of public money for the benefit of the railroad companies in their acquisition, for their own purposes, of the lands formerly constituting the site of the vacated street to the amount of the cost of such acquisition, in excess of $2,500, at which price the companies had theretofore secured an option to purchase, contingent upon the construction of the industrial sidings.
The town, under the terms of the former agreement, was free from liability for damage for vacation of Mechanic street, in excess of $2,500, and was not obliged to stand the cost of acquiring land in that street, after its vacation, for the benefit of the railroad company.
.In addition to the foregoing, the town agreed to indemnify the railroad companies for damages, which might accrue to them, by reason of the omission of the switches. The amendment to the contract, as matters stood at the time of its execution, in effect, compels the town to pay for the prosecutor’s
A municipal body has no power to indemnify one against his own act which may result in damage to the property of another, where public rights are not concerned. 2 Dill. Mun. Corp., § 814. There may be cases where the grade crossing legislation may give such authority, when the act resulting in damages is inseparably connected with, the agreed plan to carry out the object of such legislation, but that is not this case.
The point has been made, that an ordinance as distinguished from a resolution is required to authorize a contract on the part of the municipality for the opening or vacating highways, or altering the lines or grades of streets, inasmuch as these acts are required by the statute under which Bloomfield is incorporated, to be done by ordinance, and such contracts are not self-executing. Clark v. Elizabeth, 32 Vroom 565.
It is conceded that we have no authoritative decision in this state upon this point. It is not necessary to recount the arguments made for and against limiting the exercise of such power, by ordinance only, for the original contract had in fact sprung from an authorization in the form of an ordinance. The further insistence is that the supplemental resolution assuming to alter an ordinance and the contract cannot stand. That proposition must be sound, if the original contract needed municipal action, by way of ordinance to support it.
The plaintiff in error asserts authority in the original contract itself for its modification by mere resolution, in the following clause: “As it may be found necessary by both parties hereto, during the progress of said work, to make changes in plans or parts of plans, or in the construction of said work, it is hereby agreed that when such changes are approved by resolution of the town council of Bloomfield the work shall proceed in accordance therewith. A copy of such resolution shall be made a part of this agreement, and a certified copy thereof shall be furnished to the companies,” and, in another
The argument is not persuasive. The contrasting provisions indicate rather that the railroad and tire town, in carrying on the work, may find minor changes necessary, and when such changes have the approving resolution of the municijral body, it shall be sufficient authority, on the part of the town, for the company to proceed accordingly. These changes evidently refer to those not substantially altering the scheme, or in any way involving the rights of third parties. The later-quoted provision binds the contracting parties to adhere closely to the terms of the original contract, except where a duly executed supplemental agreement shall change it. We conclude that these provisions are not sufficient to warrant by resolution an alteration of the scope and magnitude of that here presented.
To return, then, to a consideration of the effect of a resolution working a modification of an ordinance. The latter is of a higher grade than the former. There is abundance of authority holding that an ordinance cannot be amended, repealed or suspended except by an act of equal dignity. 2 Dill. Mun. Corp. (5th ed.), § 572; 1 Sm. Mod. L. Corp., § 543; 28 Cyc. 380; 21 Am. & Eng. Encycl. L. 1003; City of
But, if we are in error in this regard, yet there is an insuperable obstacle to sustain the modified agreement in this case. It interfered with private rights, and, therefore, was judicial in its character'. Its express object was to abolish a private siding, existing at the time of its passage upon private property. It is settled by a long line of decisions that municipal action which affects or adjudicates regarding property rights, to be valid, can be taken only after notice, actual or constructive, has been given' to those whose rights are affected. Cape May v. Railroad Company, 31 Vroom 224; Camden v. Mulford, 2 Dutcher 49; Moore v. Haddonfield, 33 Vroom 386. Tn the last ease, it was held by this court that “if the original ordinance was a judicial act, it could not be abrogated even in part, save upon notice.”
The prosecutor was a property owner, and it does not appear that it, or any other property owner, had actual notice, or notice by construction, of the contemplated resolution, or of the execution of the contract which followed immediately upon its passage. Every intendment must be made against the fact that any notice was given'. This is sufficient to set aside the resolution.
The town, however, contends in opposition that the prosecutor has, in fact, no property rights to be affected, and that nowhere do any facts appear' supporting such right in the siding, and that the passage of the resolution and the making of the contract were in no sense judicial acts.
The argument is that the prosecutor has failed to show any contractual relation with the railroad companies either with regard to the original switch or the proposed switch to be substituted. It does appear that a switch existed there originally, and the agreement shows that a new one was to be substituted.
Whatever may have been the relation between these parties before the making of the agreement of July 12th, 1910, the railroad companies, by that contract, agreed to construct a substituted siding, and the city assented to it, and in the carrying out of the genera] scheme of elevation, it may be that sufficient authority was vested in the town, as' well as in the railroad companies to make a valid contract for the preservation of the .prosecutor’s access to the railroad tracks in this manner, and under the existing conditions. Moreover, by the terms of the agreement, a benefit was conferred upon the prosecutor in consideration for which the railroad companies had been enabled to acquire their option to purchase the lands of the prosecutor required for their improvement, at a lower price than they otherwise would. So that whatever may have been the status of the siding originally, it seems clear now that the prosecutor has a property right to its construction. In Styles v. Long Company, 41 Vroom 301, this court held that one, not a party to a contract, has no status to sue upon it, if he be a person with whom the.contracting parties never meant to come into contractual relations, and that a possible benefit'to such party by the performance of a contract is not enough to give him the right to maintain an action upon it. To have that effect, it must appear that the contract was made for his benefit. The agreement fairly shows, not only that the railroad companies and the town did contemplate contractual relations with the prosecutor, but that the former actually contracted £or its benefit by agreeing to the construction of the substituted sidings, as delineated upon tire plans accompanying that instrument. ' .
It seems to us to be plain that property rights flowed to the prosecutor from it, and that by the enforcement of the supplemental resolution, they will be swept away, without notice.
The judgment of the Supreme Court under review will be affirmed.
For affirmance — The Chancellor, Chief Justice, Yoorhees, Kaltsch, Bogert, Yredenburgh, Congdon, White, Treacy, JJ. 9.
For reversal — Garrison, Trenchard, JJ. 2.