OPINION
The plaintiff in this ease, American Insurance Company (American), served as the Miller Act surety on an Air Force construction contract. It seeks compensation from the United States alleging that the Air Force improperly released progress payments to the construction contractor, thereby impairing plaintiffs suretyship and increasing its costs when it was required to take over performance of the contract. Defendant has filed a motion for summary judgment, asserting that, in dispensing the funds in question, it breached no legally cognizable duty to plaintiff. Based on its review of the record and the parties’ assertions, and for the reasons that follow, the court finds the latter argument persuasive and GRANTS defendant summary judgment.
I. BACKGROUND
The relevant facts are relatively uncomplicated:
This case finds it origins in a February 14, 1994, Air Force contract with G & C Enterprises, Inc. (G & C) to construct an aircraft parking apron and a jet fuel storage facility at McGuire Air Force Base, New Jersey, for the firm fixed-price of $10,380,390. The contract had a completion date of June 15, 1996. It included the following standard FAR provision regarding progress payments:
The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer. The Contractor shall furnish a breakdown of the total contract price showing the amount included therein for each principal category of the work, which shall substantiate the payment amount requested in order to provide a basis for determining progress payments, in such detail as requested by the Contracting Officer.
It further provided that—
If the Contracting Officer finds that satisfactory performance was achieved during*153 any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.
Pursuant to the Miller Act, 40 U.S.C. §§ 270a-270d (1994), plaintiff issued payment and performance bonds on behalf of G & C in connection with this contract.
During performance of the contract, G & C periodically submitted requests for progress payments to the contracting officer together with progress reports reflecting the work it had completed. The contracting officer reviewed these documents and issued payments pursuant to the contract provisions quoted above.
Around June of 1996, G & C began experiencing difficulties in completing the contract. The parties have slightly different accounts of what happened next. American alleges that it learned that G & C was in a state of financial difficulty and that, when contacted, the Air Force confirmed that G & C was making unsatisfactory progress and technically in default. Defendant alleges that, on June 22, 1996, a windstorm damaged facilities being constructed by G & C on a separate unrelated contract with the government. It contends that, for approximately six months, G & C failed to complete work on this unrelated contract, as well as the contract for which American served as surety. Defendant avers that it informed G & C that it was considering terminating the contacts for default. Finally, it asseverates that American and the Air Force entered into negotiations, wherein American assured the Air Force that it would provide G & C with the necessary financial resources to complete the project and the Air Force, in turn, assured American that it would not terminate its contact with G & C for default.
Sometime after June of 1996 — and the record does not disclose exactly when — -American assumed defacto managerial control over the project in order to protect its financial interest. It entered into a subcontactor/takeover agreement with G & C and contracted with C & T Associates, Inc. (C & T) to complete the project for $2.7 million. G & C remained the contractor under the contact, but in name only, with American maintaining custody and control of the remaining contract funds, which were paid over to C & T. By letter dated May 23, 1997, American informed the Air Force of this arrangement.
On August 20,1999, plaintiff filed an action in this court asserting that defendant had overpaid G & C by $842,000, representing the difference between the 97 percent of the contract price paid to G & C and the 80 percent it alleges should have paid for the amount of work G & C had actually completed by the time American assumed perform-
II. DISCUSSION
Summary judgment is appropriate when there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. RCFC 56; Anderson v. Liberty Lobby, Inc.,
A surety arrangement typically involves three parties: an obligee who has recourse against a surety (the secondary obligor) with respect to the obligation of another person (the principal obligor) to that obligee. See Restatement (Third) of Suretyship and Guaranty (hereinafter “Restatement”) § l(l)(a) (1996). The central issue raised in this case is whether defendant — the obligee — owes plaintiff — the secondary obligor — the difference between the amount of money that it paid G & C — the principal obligor — and the value of the work G & C actually completed.
In its complaint, plaintiff raised four theories in support of this recovery, to wit, that: (i) defendant breached a “three-party contract of suretyship” through its alleged failure to administer properly the contract with G & C; (ii) American should be equitably subrogated to defendant in the amount of the completion costs; (iii) defendant breached its “fiduciary duty” to American by failing to protect the contract balance on behalf of American; and (iv) defendant breached “equitable duties” to American through its failure to protect the contract balance. However, in its brief in response to defendant’s motion, plaintiff did not discuss, in any detail, the first, third and fourth of these theories, giving rise to a reasonable argument that it had waived these theories. See Jay v. Sec’y of Dept. of H.H.S.,
First, the Federal Circuit has squarely rejected the notion that, in the absence of a takeover agreement, a suretyship arrangement creates a direct contractual relationship between the defendan/obligee and the surety. Here, there was neither such a takeover agreement nor any indication that American was viewed as a third-party beneficiary of the contract between defendant and G & C. The situation is essentially identical to that in Fireman’s Fund Ins. Co. v. United States,
With regards to plaintiffs equitable subrogation theory, it is axiomatic that “before any obligation arises to withhold or divert funds, the Government must be notified that the sureties believe the contractor is in default and cannot complete the contract.” Ransom v. United States,
Plaintiff correctly notes that a surety may, without providing the requisite notice, recover against an obligee that impairs its suretyship status. Thus, in National Surety v. United States,
By way of further explanation, the Federal Circuit observed that “[i]t is of course almost axiomatic that any change or modification of the construction contract which materially increases a compensated surety’s risk discharges the obligation” Id. at 1547. Recognizing that such a discharge was of little direct value to the surety because it already had performed before the breach, the court, nonetheless, concluded that the surety was entitled to an affirmative recovery against the government, reasoning—
Contract terms that provide security for the bonded performance can not be ignored, waived, or modified without consideration of the surety’s interests.... The government’s failure to retain the required sums during performance of the ... contract was a change in the terms from those on which the surety provided its bonds. When National Surety completed the contract in accordance with its performance bond, it was entitled to the benefit of the contractually-required retainage. The government’s improper release of this security does not avoid liability to the surety for losses thereby sustained.
Id. at 1547. In so holding, the Federal Circuit cited, with approval, section 37 of the Restatement,
In the case sub judice, there is no indication that the Air Force violated the terms of its contract with C & G. As to progress payments, that contract provided that “[t]he Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer.” Contrary to plaintiff’s im-portunings, this provision does not prohibit the contracting officer from making payments beyond those dictated by the progress of work — it merely affirmatively required such payments as progress was made. Any notion that this provision could be applied in the converse to govern unsatisfactory performance ignores the fact that the contract had a specific provision which provided that in the absence of satisfactory progress, “the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.” The use of the permissive terms “may” and “maximum” plainly allowed, but did not require, the contracting officer to retain up to 10 percent of the payment for a given period.
Of course, various cases suggest that if the Air Force abused its discretion in making progress payments that too could be viewed as an impairment of plaintiffs suretyship and give rise to damages. “During the performance of the contract,” the Court of Claims once stated, “the Government has a duty to exercise its discretion responsibly and to consider the surety’s interest in conjunction with other problems encountered in the administration of the contract.” Argonaut Ins. Co. v. United States,
The key question then becomes whether the Air Force’s contracting officer did, in fact, responsibly exercise the discretion given him. On this count, plaintiff has failed to establish any genuine issue of material fact as to whether the contracting officer abused his discretion in continuing to make, under the circumstances presented, full progress payments. Rather, apart from general allegations made by its counsel during oral argument, plaintiff never addressed this issue and instead chose to argue that those payments were not authorized by the contract — a proposition that this court has now rejected. See Pure Gold, Inc. v. Syntex,
Plaintiff ultimately is left to argue, sans decisional support, that the Air Force breached some undefined fiduciary or equitable duty. These assertions also miss the mark. For one thing, such general breaches of claimed fiduciary or equitable duties are ordinarily viewed as giving rise, if anything, to torts,
III. CONCLUSION
This court need go no further. Based on the foregoing, the court GRANTS defendant’s motion for summary judgment. The Clerk is directed to dismiss plaintiffs complaint.
IT IS SO ORDERED.
Notes
. American asserts that, in these discussions, representatives of the Air Force acknowledged that they had "overpaid” G & C, that is, provided G & C with payments that exceeded its progress; however, defendant contests this.
. For reasons that are unexplained, the letter is not in the record. However, in his affidavit, John W. Simms, the contracting officer here, describes the letter as follows:
By letter dated May 23, 1997, American Insurance wrote to me notifying me that G & C Enterprises Inc. was experiencing financial problems. American Insurance Company further notified me that they were soliciting bids from completion contractors to finish the project. It was agreed upon and understood by both parties that progress payments would be made to G & C Enterprises, Inc. and then in turn payments would be made to the completion contractor, with the approval of Cashin Associates, the project manager. American Insurance Company never requested stoppage of progress payments to G & C and never notified the Contracting Officer that defaulting [sic] G & C Enterprises Inc.
Plaintiff does not contest this characterization of the letter.
. To be sure, in Balboa Ins. Co. v. United States,
. Further explaining the role played by this notice requirement, the Federal Circuit, in Fireman's Fund, stated—
[o]nly when the surety may be called upon to perform, that is, only when it may become a party to the bonded contract, should the government owe it any duty. The surety knows best when this may occur; consequently, only notice by the surely triggers the government's equitable duty.
. See, e.g., Newark Ins. Co. v. United States,
The progress payment issue falls squarely under the controlling case law. Because [the surety] did not give notice to the Coast Guard of [the contractor’s] default on the surety bonds, and did not request that the last progress payments be withheld, it failed to 'trigger the government’s equitable duty to act with reasoned discretion toward it.’ Fireman’s Fund, supra,909 F.2d at 499 . It is not the Government’s responsibility, as the Federal Circuit made clear in Fireman’s Fund, to divine the surety’s thinking process, or to act as a nanny for the surety and ask it whether, under the circumstances of a given contract, it would like the Government to withhold progress payments to the contractor. [The surety]*156 was fully apprised of [the contractor’s] performance record and the danger of its default on the ... contract ... because it was copied on the Coast Guard's warning notices to [the contractor]. It was [the surety’s] responsibility to decide for itself what it wanted to do, if anything, with the information it received from the Coast Guard. It chose to do nothing, and it was not the Coast Guard’s prerogative or duty to substitute its judgment for the surety’s.
Id. at 579.
. Section 37(1) of the Restatement provides that ”[i]f the obligee acts to increase the secondary obligor’s risk of loss by increasing its potential cost of performance or decreasing its potential ability to cause the principal obligor to bear the cost of performance, ... the secondary obligor has a claim against the obligee as described in subsection (4).” Subsection (4) states—
(4) If the obligee impairs the secondary obli-gor’s suretyship status
(a) after the secondary obligor performs any portion of the secondary obligation; or
(b) before the secondary obligor performs a portion of the secondary obligation, if the secondary obligor then performs:
(i) without knowledge of such impairment;
(ii) for the benefit of an intended beneficiary who can enforce the secondary obligation notwithstanding such impairment; or
(iii) under business compulsion;
the secondary obligor has a claim against the obligee with respect to such performance to the extent that such impairment would have discharged the secondary obligor with respect to that performance.
Restatement, § 37(4); see also id. at cmt d ("Subsection (4) gives the secondary obligor a
. While the word "may” can, in some contexts, mean "must”, see Cortez Byrd Chips, Inc. v. Bill Herbert Constr. Co.,
. In various of its affidavits, plaintiff asserts that Air Force representatives admitted that the contracting officer had "overpaid” C & G in varying amounts. In the court's view, this "admission,” insofar as it goes, does not create a material question of fact on the discretion issue because there is no indication that the Air Force representatives ever admitted that the overpayments were erroneous, contrary to the terms of the contract or an abuse of discretion.
. In this regard, a letter dated December 31, 1997, from Cashin Associates (which had been retained by plaintiff to assist G & C) to the Air Force indicates that "Cashin has been advised by representatives of G & C and the Government that the overpayment situation developed based on the need to maintain cash flow on this project.” The same letter suggests that the progress payments may have corresponded to work actually performed by G & C, albeit relating to change orders, as opposed to the base contract, stating "G & C had commenced and in some cases completed work on a series of change orders, at the Government’s request, prior to the issuance of a formal modification related to the extra work.”
. See Regents of Univ. of N.M. v. Knight,
