123 Kan. 502 | Kan. | 1927
The opinion of the court was delivered by
The plaintiff as surety for the National Paving Company of Oklahoma City executed a maintenance bond guaranteeing certain paving. The bond was executed on the application of the defendants, who were the officers and chief stockholders of the
The plaintiff alleged, in substance, that it was a Texas corporation engaged in the general business of acting as surety for persons and corporations engaged in constructing paving and similar work; that the defendants were officers and principal stockholders of the National Paving Company, an Oklahoma corporation; Stingley, president, and Peak, vice president; that the paving company, under the active management of the defendants, became and was the successful bidder for certain paving in Oklahoma City, requiring a bond of $38,758, conditioned upon its paying for all work and materials used in the performance of its contract; that plaintiff at the especial instance and request of the paving company and as a result of the personal solicitation of the defendants became the surety upon such bond; that as a further condition pertaining to the letting of the paving contract, the paving company was required to execute a maintenance bond guaranteeing the maintenance of the paving for a'period of five years after completion and acceptance of the work; that defendants being fully conversant with all the requirements of the city, after extensive negotiations procured the plaintiff to execute a maintenance bond in the sum of $38,758, guaranteeing the maintenance of the paving for a period of five years; that such bond was eventually executed by plaintiff upon a formal written application by defendants; that the application for such maintenance bond was executed by the paving company and by the defendants as sureties; that thereafter, as additional security to plaintiff for the execution of the maintenance bond and other bonds, the plaintiff required the paving company to' deposit $3,000 in the American National Bank, and a certificate thereof to be assigned to the plaintiff. Provisions of the application and bond are set out in the petition in much detail. It is alleged that the paving company duly entered upon the work of constructing the paving, which was completed and accepted by the city August 21, 1917; that the paving company failed to pay for material and labor provided in its contract in accordance with the terms of the bond first mentioned, as a result of which plaintiff was compelled to pay a judgment for the paving company of $10,588; that thereafter, for the purpose of reimbursement, the plaintiff brought suit against the paving company and the
The defendants answered denying generally the allegations of the petition. They pleaded also the five-year statute of limitations, and the three-year statute of limitations. For a further defense, they alleged that plaintiff took possession of a plant used in the laying of hard-surface roads, of wagons, motors, etc., of a total .value of $19,500, which more than satisfied the claims, if any, of plaintiff against the defendants and the National Paving Company. They also alleged that plaintiff had recovered the sum of $4,050 on the certificate of deposit mentioned in plaintiff’s petition.
The plaintiff in reply denied the allegations of new matter set up in the answer of the defendants and further alleged that in a certain attachment action brought by the plaintiff against the National Paving Company, the paving plant and equipment referred to by the defendant in its answer had been seized, appraised and sold and that there was realized therefrom approximately the sum of only $250.
Trial was to the court; evidence to sustain the allegations of both parties; general judgment for defendants; no special findings.
The plaintiff contends that the judgment was contrary to the evidence. Defendants contend that the action is barred by the five- and three-year statutes of limitations; that there was a variation
In support of the contention that the action was barred by the statute of limitations, the defendants say that the paving was completed Thanksgiving day in November, 1916; that the city made no demands for repairs under the bond until December 8, 1921, more than five years after completion of the work. The petition alleged and there was evidence in support of the allegation that the paving began to crack within eighteen months after it was completed, and continued to grow worse until; with some exceptions, the entire pavement had become useless within five years after its completion. The city made due demand upon the plaintiff within time to compel compliance with the provisions of the bond. Plaintiff’s cause of action against the defendants accrued when it paid the judgment in favor of the city, April 21, 1924. Action was filed against defendants in August, 1924. Neither the five- nor the three-year statute of limitations had. run against plaintiff’s cause of action, and defendants’ contention in this regard, therefore, cannot be sustained.
With respect to variations between the application and the bond it is contended:
“That the application did not specify the amount of indemnity to be named in the bond and that when a bond of 100 per cent of the contract price was executed, it therefore was not'in accordance with the application; that the application called for a maintenance bond for five years from the completion of the paving while the bond itself called for five years from completion and acceptance; that the application in no way contemplated the provision in the bond itself, whereby the city engineer and commissioners possessed the power of determining the amount necessary to place the pavement in proper condition to stand up.”
It may be noted that the city, in its requirements expressed in the advertisement for bidders, required a maintenance bond for the full amount of the contract price for five years from the date of the completion and acceptance of the improvements. The specifications adopted by the city, and contemplated by proposal of the National Paving Company and the contract of that company with the city, provided the procedure in case of failure to make necessary repairs. It provided that the contractor guarantee the work for five years from completion and final acceptance of the paving, also for the giving of the maintenance bond for one hundred per cent of the contract price.
Respecting the contention of the defendants that plaintiff has received credits sufficient to relieve defendants of liability in this action, the record is not entirely clear. There was evidence that the plaintiff was compelled on its contractor’s bond to pay a judgment and attorney’s fees on behalf of the National Paving Company amounting to $11,149. As partial compensation for this outlay, plaintiff received $4,050 from the certificate of deposit in the American National Bank. This left a balance due plaintiff at that time of something over $7,000. The plaintiff filed an attachment action against the National Paving Company and attached the plant and equipment that had been used in the construction of the pavement. Various questions are raised by the defendants as to the validity of that action. It is claimed that the entire proceedings were void and that the action of Attorney A. J. Decker in entering appearance therein of the National Paving Company was without any authority.
The judgment is reversed and the cause remanded for further proceedings not inconsistent with the views herein expressed.