122 So. 837 | Ala. | 1929
Lead Opinion
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *597 This case was tried by the court without a jury, and there was a judgment for the plaintiff. The defendant appeals, and the assignments of error are predicated on two propositions only, first, that there was error in rendering a judgment for the plaintiff in any amount, and, second, if the plaintiff was entitled to recover at all, the amount was limited by the contract to $50.
The main question and the one first presented in argument calls for an interpretation of the following clause in the contract, to wit:
"It is agreed by and between the parties hereto that the Contractor is not an insurer, and that the rates hereinbefore named are based solely on the value of the service in the operation of the system described, and in case of failure to perform such service and a resulting loss its liability hereunder shall be limited to and fixed at the sum of $50.00 as liquidated damages, and not as a penalty, and this liability shall be exclusive."
As we view this clause, it is but a limitation of the amount recoverable in case of a breach of the contract. It is unlike those contracts or clauses construed by the courts as being invalid because providing a penalty though designated as liquidated damages.
The contract does not penalize the defendant for a failure to perform, and it only restricts the plaintiff as to its recovery in case of a breach by the defendant, and does not attempt to penalize or fix the damages against the plaintiff in case of a breach by it. It deals only with a breach by the defendant, and in no sense penalizes it for a breach; so we are at a loss to understand the necessity for the earnest and elaborate argument by both sides on the question of when such clauses should be construed as a penalty or liquidated damages. Conceding, however, that, by limiting the amount of recoverable damages, it operates as a burden or hardship on the plaintiff, still we are not at liberty, by analogous authorities, to make a new contract for the parties or to strike therefrom a clause well understood and evidently within the intention of the parties.
As brought out by Mr. Sutherland in his work on Damages, and by Mr. Williston in his work on Contracts, much confusion has heretofore arisen, and there is little harmony in the cases dealing with the question as to when certain clauses of contracts, fixing the amount of recovery for a breach, should be construed as liquidated damages or stricken because they provided a penalty, but the more recent cases show a tendency to uphold clauses of this character with the same degree of solemnity and importance as other parts of the contract.
As said by the United States Supreme Court in the case of Sun Printing Publishing Ass'n v. Wm. L. Moore,
Mr. Sutherland in his work on Damages, § 283, vol. 1, p. 842, after discussing the decisions on the subject, lays down the following rules or test: "First, that if by the terms of the contract, a greater sum is to be paid upon default in the payment of a lesser sum at a given time, the provision for the payment of the greater sum will be held a penalty; second, where, by the terms of a contract, the damages are not difficult of ascertainment according to such terms and the stipulated damages are unconscionable, the latter will be regarded as a penalty; third, within these two rules parties may agree upon any sum as compensation for the breach of a contract."
When the contract in question was entered into, the nature and amount of damages that might arise as the result of a breach were conjectural and uncertain, and the parties had the right to fix the same by the contract, and, having intended to do so, the court is not authorized to nullify this provision by declaring it a penalty, although the actual damage sustained may be in excess of the sum fixed by the contract. Stratton v. Fike, *599
Another question, however, arises as to those counts of the complaint in tort for the negligent breach of duty growing out of the contract and whether or not the clause can apply as to the limitation of a liability for the negligence of the defendant. This court is committed to the doctrine that, where parties enter into a relation carrying a legal duty, while one may limit the scope of his duties, he cannot stipulate for protection against negligence in the performance of the duties he does assume. Thompson v. Mobile Light R. Co.,
We do not understand the case of W. U. Tel. Co. v. Westmoreland,
The case of Wells Fargo Co. v. Taylor,
There was evidence from which the trial court, sitting as a jury, could reasonably infer that the signal apparatus failed to function as a result of a negligent maintenance of same, either in permitting the clot of oil to get upon same, or in failing to discover and remove same, and that the failure of the signal to function was the proximate cause of the damages sustained by the plaintiff. It is true, the contract made no express provision as to what the defendant was to do after receiving a signal at its central office, but it does provide for the installation of transmission boxes and the wire connection "necessary to transmit signals to the Contractor's Central Station," and there must have been an implied duty upon the defendant to take some action, after receiving the signal, to prevent damage to the plaintiff. Otherwise the transmission of the signal to the central station would be a piece of folly, and, in fact, the installation of the signal system could have served no useful purpose. It is evident that, had the signal been given, the defendant, as on occasions when the signal was received would have taken steps leading to an extinguishment of the fire and cutting off the water when the fire was extinguished.
The judgment of the circuit court is affirmed.
Affirmed.
SAYRE, THOMAS, and BROWN, JJ., concur.
Addendum
The defendant is not subject to the control of the Public Service Commission, and has the right to contract with whom it pleases, and is not legally bound to serve the public. Browne v. National District Tel. Co., P. U. R. 1921A, 113; Re American District Tel. Co., P. U. R. 1921E, 519; Wolff Packing Co. v. Court of Industrial Relations,
This being the case, the contract in question falls within the influence of our case of McKinney v. Mobile O. R. Co.,
The trial court erred in rendering judgment for the plaintiff for any sum in excess of $50, with interest thereon since the injury. The foregoing opinion is modified, and the judgment is corrected and affirmed for $50 and interest, and the application for rehearing is overruled. Appellee is taxed with the cost of this appeal.
SAYRE, THOMAS, and BROWN, JJ., concur.