Opinion by
Two questions are raised by this appeal. 1. Whether or not the notice of the intention, on the part of the plaintiff to file a lien, complied with section 7 of the Act of June 4, 1901, P. L. 481. 2. Whether or not the lien filed by the plaintiff in this case complied with section 11 of the same act.
As to the notice, section 8 provides that “ any sub-contractor intending to file a claim, must give to the owner written notice to that effect, together with a sworn statement setting forth the contract under which he claims, the kind of labor or materials furnished, and the date when the last work was done, or materials furnished. Such notice and statement must be served at least one month before the claim is filed, and within three months after the last of his work was done or materials furnished, if he has six months within which to file his claims.”
Clause 11, of section 11 of the act, requires that when the contract is with other than the owner, the claim shall set forth when and how notice was given to the owner of an intention to file the claim. We decided in Thirsk v. Evans,
Cbunsel for appellee object to the notice, and allege that the kind of material furnished is not shown with sufficient defi
As to the objection that the notice does not allege that the materials were furnished in accordance with the specifications of the contract, the act does not prescribe such an averment. But the sworn statement which is part of the notice does aver that the letters, copies of which were contained in it, showed “ the contract under which the said cast-iron water pipe and specials were furnished.” If an averment such as appellee contends were necessary, this would certainly answer.
The court below has not indicated in what particulars the notice does not, in its opinion, comply with the act of assembly. It is difficult to see how a notice more strictly complying with the act could be drawn, although substantial compliance is all that is necessary. “ The object of the notice,” it is said in Thirsk v. Evans,
Now as to the sufficiency of the claim. It would have been
The provisions of the act involved in this feature of the controversy are as follows : By section 11 of the Act of 1901, P. L. 431, the claimant is required to set forth, inter alia, “ (4) a copy of his contract or contracts, if in writing, or a statement of the terms and conditions thereof, if any of them are verbal; (5) the kind and character of the labor or materials furnished, or both. (6) When the contract is with other than the owner or not for an agreed sum, a detailed statement of the kind and character of the labor or materials furnished, or both, and the prices -charged for each thereof; (11) When the contract is with other than the owner, when and how, notice was given to the owner of an intention to file the claim.”
It is suggested in behalf of appellee that the claim is fatally defective in failing to state the kind and character of the materials furnished with the particularity required by the act. But the claim asserts, “ That under said contract with the said Wm. M. Powell & Company, contractor, the said American Car & Foundry Company sub-contractor, furnished the materials set forth in the bill of particulars attached hereto and marked Exhibit A, and which bill the said claimant prays, may be taken and made a part of this lien, said materials being furnished by the said claimant upon the credit of the said pipe line, water works plant and system, rights, franchises and privileges of said water company, at the times, in the quantities and at the prices set forth in said bill of particulars.”
This court has repeatedly held, under prior similar statutes, that the bill of particulars is to be taken as part of the lien. Thus in Wilvert v. Sunbury Boro., 81 * Pa. 57, it is said “ The bill of particulars annexed to the statement is as much a part of it, as if it had been incorporated in the statement itself.” To the same effect is School v. Gerhab,
It may be that the bill of particulars considered by itself, and as a detached paper, if it contains only dates, pounds, prices and amounts, does not designate “ the kind of materials furn
Appellee also objects to the claim because it does not contain any averment that the pipe was shipped in accordance with the specifications of the contract. But it is expressly alleged that “under said contract with Wm. M. Powell & Company, contractors, the said American Car & Foundry Company, subcontractor, furnished the materials set forth in the bill of particulars.” This is certainly a sufficient averment of this fact. There is no substance in the objection that the notice claims a lien for materials furnished between September 23 and November 27, 1903, while the lien filed contains items from September 17, to November 27, because it plainly appears that credits are allowed for payment of all matertial furnished prior to September 23. The notice and claim, therefore, correspond as to all items for which a lien is claimed.
Justice Bell gave utterance to a principle, in considering the act of 1836, which is equally appropriate to the statute now before us. In Knabb’s Appeal,
The court below has not stated any reasons for holding that the lien does not substantially comply with the requirements of the law, and our examination of the case, has satisfied us that it does.
The order of the court below striking off the lien, is therefore reversed, and the lien is reinstated.
