2 P.2d 1007 | Cal. Ct. App. | 1931
This is an appeal by plaintiff American Material Service Company, a corporation, from a judgment allowing priority of a deed of trust of defendant John R. McCoy and Title Guarantee and Trust Company over the mechanic's lien of plaintiff. The facts are briefly these:
Defendant L.O. Wallin, Fred W. Klein and Frances Klein owned a lot in the city of Los Angeles. During the early part of 1926 they commenced the erection of a brick garage thereon. There was no general contract for the erection of said garage. During the course of the construction of this garage, the owners purchased from plaintiff and appellant certain building materials, consisting principally of rough lumber to be used in the construction of said garage. After the work had begun on the garage, but before appellant had sold or delivered any material, said owners executed a deed of trust upon said real property in favor of defendant John R. McCoy to secure the payment of a promissory note in the sum of $15,750, naming the defendant Title Guarantee and Trust Company as trustee. Said deed of trust was also *529 recorded in the office of the county recorder before appellantdelivered any materials for said building. Failing to receive payment for said material, appellant filed a lien for the amount due and thereafter instituted this action for the foreclosure of such lien.
The court found that the building was commenced prior to the recordation of the deed of trust, but that no materials were furnished by appellant until after said deed of trust was recorded, and, therefore, the lien of said deed of trust on said real property was superior to the mechanic's lien of plaintiff and appellant, and rendered judgment accordingly.
The court found, however, that other persons, firms and corporations had furnished materials and performed labor upon said garage building prior to March 13, 1926, the date of the recordation of the deed of trust, and, also, found that there was no general contract for the erection of said garage building.
[1] Appellant contends that, under the court's findings, its lien would date back as of the date of the commencement of thework on said garage, and would, therefore, be prior and superiorto the lien of said trust deed. Consequently, only one question is presented for determination, which is: When did appellant's lien attach? Or, to state the question another way: Did appellant's lien attach when the building was first commenced or when appellant first delivered any lumber or other materialfor the construction of said building?
Section 1186 of the Code of Civil Procedure provides:
"The liens provided for in this chapter are preferred to any lien, mortgage, or other encumbrance which may have attached subsequently to the time when the building, improvement, or structure was commenced, work done, or materials were commenced to be furnished; also, to any lien, mortgage, or other encumbrance of which the lienholder had no notice, and which was unrecorded at the time the building, improvement, or structure was commenced, work done, or the materials were commenced to be furnished."
[2] It has been settled by a long line of decisions in this state that a deed of trust is a lien or other encumbrance withinthe meaning of said section 1186 (Fickling v. Jackman,
[3] In the case at bar, however, we have a different situation. Here the work on the building had commenced and others had already performed labor and furnished materials used in the construction of said building, when the deed of trust was executed and recorded, but appellant did not furnish anymaterial until after the recordation of the deed of trust, and nowritten contract for the construction of the building isinvolved. The owner built the structure and dealt directly with the laborers and materialmen.
In the case of McClain v. Hutton,
The court in that case further held that "under this provision (sec. 1186 Code Civ. Proc.) the cases must be divided into two categories, distinguished by the existence or nonexistence of a valid contract. In the former case (where there is a valid contract) the priority of the liens is to be determined by the date of the commencement of the buildings; in the latter, by the time the work was done, or the materials commenced to be furnished.
In Simons Brick Co. v. Hetzel,
It is true that since the decision in McClain v. Hutton,supra, and in 1911 (Stats. 1911, p. 1313) section
The division of mechanics' liens into two classes is based on section 1186 of the Code of Civil Procedure and this section has not been amended since its enactment in 1872.
Appellant seems to rely upon the case of Sax v. Clark,
From what we have said it follows that we are of the opinion that, as there was no general contract for the construction of the garage in question, appellant's lien did not attach until the materials were commenced to be delivered and said deed of trust, having been recorded prior to that time, is superior to the lien of appellant.
The judgment is affirmed.
Plummer, J., and Thompson (R.L.), J., concurred.