127 F. 671 | 6th Cir. | 1904
This suit was brought by Gibson county, Tenn., against Hugger & Winston, as contractors, and the American Bonding & Trust Company, as surety, upon a contract and bond for the erection of a courthouse. Recovery was sought for the expense incurred by the county over the contract price in completing the courthouse, and damages resulting in the delay, the employment of the contractors having been terminated under a stipulation of the contract Pleas, both
The contract price for the building was $30,485.00, payable in installments at times to be determined by the progress of the work. The work was done under the supervision of architects, and all payments made upon their written certificates. The contract was made April 1, 1899, and the building was to be completed on April 1, 1900, in default of which the contractors were to pay to the county $5 a day for each day the building should remain unfinished. Failure of the contractors to prosecute the work with promptness and diligence was covered by the following clause of the contract:
“Art. V. Should the contractors at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality; or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the owners shall be at liberty, after three days’ written notice to the contractors, to provide any such labor or material, and to deduct the cost thereof from any money then due or thereafter to become due to the contractors under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractors for the said work and to enter upon the premises and take possession, for the purpose of completing the work comprehended under this contract, of all materials, tools and appliances thereon and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractors he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractors, but if such expense sljall exceed such unpaid balance, the contractors shall pay the difference to the owner. The expense incurred .by the owner as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default shall be audited and certified by the architects, whose certificate thereof shall be conclusive upon the parties.”
Complaint of the slow and unsatisfactory character of the work was made in May and June, 1900, and on August 2, 1900, the architects (using the language of the > above clause) notified the building committee of the county that the contractors were refusing and neglecting to supply a sufficiency of workmen and material, and had failed to prosecute the work with promptness and diligence, and certified that this failure, refusal, and neglect was such as to warrant the termination of the employment of the contractors.; Accordingly, after proper notice, their employment was terminated, possession taken, and the building completed by the county. • .
The contract price of the building was to be paid in six installments of $3,484 each, and a final payment of $9,581. The contractors did all the work except that covered by the final payment. The plaintiff neither 'alleged nor proved that the architects had audited and certified the expense and damage incurred by the county through the default of the contractors, and for lack of this certificate, the defendants insisted
The distinction sought to be drawn by the plaintiff, that the suit is not one on the contract, but one for damages on account of the abandonment of the contract, does not appeal to us. This is not a case like the Fuller Company v. Doyle (C. C.) 87 Fed. 687, where the contractor, without doing any substantial work, abandoned the contract, but. a case where the contractor, having done all the work except that covered by the last payment, had his employment terminated under article 5, through a strict compliance with its provisions. The damages sought to be recovered here are not damages outside the contract, but damages under the contract, resulting from a violation of its provisions. Accordingly, the surety is also sued. Now, the surety guarantied the faithful performance of the cojitract, and the measure of the damages1 for which it can be held responsible must be found in the contract itself. If there be in the contract a provision for ascertaining the amount of damages incurred through a violation of any of its provisions, the surety has a right to insist on its observance before being held responsible. Under the contract, the county had a right to insist on a certificate from the architects before paying the contractors for work 'done (Kihlherg v. United States, 97 U. S. 398, 24 L. Ed. 1106; Sweeney v. United States, 109 U. S. 618, 3 Sup. Ct. 344, 27 L. Ed. 1053; Martinsburg & Potomac R. R. Co. v. Marsh, 114 U. S. 549, 5 Sup. Ct. 1035, 29 L. Ed. 255; Chicago, Santa Fé & C. R. Co. v. Price, 138 U. S. 185, 11 Sup. Ct. 290, 34 L. Ed. 917; and United States v. Gleason, 175 U. S. 588, 602, 20 Sup. Ct. 228, 44 L. Ed. 284), and, under the contract, the contractors and their surety had a right to insist on a certificate from the architects before paying the county for work done after it took over the job under the provisions of article 5. The first certificate was, perhaps, peculiarly for the benefit of the county, but the second was more particularly for the benefit of the contractors and their surety. If a certificate was required to guard the rights of the county when the work was being done by the contractors, a certificate was also required to protect the rights of the contractors and their surety when the work was being done by the county. The reason for requiring one certificate is the ground for demanding the other.
The judgment of the lower court is reversed, and the case remanded for a new trial.