208 P. 594 | Mont. | 1922
delivered the opinion of the court.
This action was brought to recover from the defendant the Farmers’ Elevator & Milling Company damages for its failure to deliver to the Globe Construction Company a certificate of deposit on the Montana State Bank of Geraldine in the sum of $3,000. One J. B. Hogg was a member • of what was known as the “building committee” of the elevator company. The contract between the two companies provided for payments on stated occasions, as the work progressed. Among other things, it was provided therein that, when the construction should reach the point “when the cribbing for the elevator was up” to where the roof was to begin, the construction company, in the place of cash, should accept interest-bearing certificates of deposit of the Montana State Bank of Geraldine in payment of the second installment of $3,000. On October 10 the cribbing was completed to the point mentioned in accordance with the terms of the contract. On October 6, 1917, Mr. Napper and Mr. Hosch, president and secretary of the construction company, respectively, applied to the plaintiff bank for a loan of $3,000. For the purpose of assisting the construction company to procure the loan, J. B. Hogg, who, besides being’ a “member of the building committee” of the elevator company, was also cashier of the Montana State Bank of Geraldine, represented to the plaintiff bank that he was authorized to speak for the elevator company and stated to Mr. Reckard, the president of the bank, that the construction company had theretofore agreed with the elevator company that it would accept interest-bearing certificates of deposit on the Montana State Bank of Geraldine, instead of cash; that the construction company agreed that it would assign and deliver to plaintiff, as security for the loan, the certificates of deposit that were to be delivered to it as a second payment on the building contract. Upon assurance of Mr. Hogg that the certificates of deposit would be delivered
On December 12, 1917, a petition was filed by certain creditors of the construction company alleging that it was insolvent. On March 8, 1918, it was adjudged a bankrupt. In an agreement entered into on September 1, 1917, between the elevator and the construction companies there was this provision: “The contractor shall furnish a good and sufficient bond to the amount of fifty per cent of the contract price.! Said bond to be in force until all lien rights on the buildings or equipment have expired and the building has been found to be of good workmanship and free from defects. Said bond to be furnished before the second payment has been made on the building to protect the owners from any loss.” This bond was not given, nor was its exaction ever waived by the elevator company.
Upon the issues thus made, the case was tried by the court without a jury, its findings being that the plaintiff agreed to accept as security for the loan the certificates of deposit upon the representations made by Mr. Hogg, but for which the loan would not have been made; that the construction company used the proceeds of the loan upon different of its jobs, including the building of the elevator and mill, but what amount the testimony does not disclose; that demand for the certificate was made and delivery refused; that the cribbing was completed on October 10, 1917; that Hogg in the transaction was acting without any authority from the elevator company, and that October 6, 1917, the date of the acceptance by him of the order, Hogg told the president and secretary-treasurer of the elevator company of its signing and ac
Counsel in their brief admit that plaintiff failed to prove that Hogg had authority to make the acceptance for the elevator company, but rely upon the ratification of Hogg’s acceptance by the board of directors at its meeting on November 12. Their argument is that the elevator company’s failure to pass a resolution disavowing acceptance at the meeting amounted to ratification by silence. They argue that, when the president and secretary, or one of them, at a board meeting stated in the presence of the other members of the board that they raised no question on the acceptance, stating “that it was all right and not to sue Hogg,” it amounted to an express ratification of Hogg’s action in accepting the order to deliver the certificate of deposit, and that it was not necessary for the plaintiff to make out a ease from which the elevator company would be estopped to deny the acceptance.
Ratification, being purely a voluntary act upon tbe part of tbe principal, ordinarily requires some positive act. No duty rests upon him to adopt it or to make inquiries concerning it. (Pew v. McLeish, 62 Mont. 437, 205 Pac. 235.) In order that acquiescence alone should become ratification, the delay must be so long continued that it can be accounted for only on the theory that there has been some affirmative act. (Evans v. Smallcombe, L. R. 3 H. L. 249; Town of Derby v. Alling, 40 Conn. 410.) The evidence does not preponderate against the findings.
Judgment and order affirmed.
'Affirmed.