OPINION
This is an accelerated appeal from the trial court’s interlocutory order denying the Amends’ request for a temporary injunction in their trespass suit against the Watsons. We affirm the trial court’s order.
BACKGROUND
In 1953, the owner of a 2.424-acre property near White Rock Lake, the William Herbert Hunt Trust, granted the City of Dallas an easement across the side of the property “for the purpose of constructing and maintaining a city sanitary sewer main.” The easement has not been used, and the property it encumbers is now vacant and belongs to the Amends.
The Watsons own the property behind the Amends’ property.
1
The Watsons want to discontinue use of the existing
The Amends filed a trespass suit against the Watsons claiming that the installation of the sewer main would constitute a trespass. The Amends sought a temporary restraining order, a temporary injunction, and a permanent injunction preventing the Watsons from installing the sewer main. The trial court granted a temporary restraining order and held a hearing on the application for temporary injunction. After the hearing, the trial court signed an order denying the application for temporary injunction.
TEMPORARY Injunctions and Standard of Review
The purpose of a temporary injunction is to preserve the status quo of the litigation’s subject matter pending a trial on the merits.
Butnaru v. Ford Motor Co.,
The decision to grant or deny a temporary injunction is within the trial court’s sound discretion, and that decision can be reversed on appeal only if we are convinced that it represents a clear abuse of discretion.
Id.; In re Marriage of Beach,
Analysis
The Amends argue that they were entitled to a temporary injunction because the easement and the City code do not allow the Watsons to use the City’s
In response, the Watsons disagree with the Amends’ interpretation of the language in the easement and in the City code. And because the Watsons contend that the easement and the City code permit them to contract and pay for installation of the sewer main, they argue that the trial court did not abuse its discretion in denying a temporary injunction because it could have reasonably concluded that the Amends did not meet their burden to demonstrate a probable right to recovery. Alternatively, the Watsons argue that the trial court did not abuse its discretion because it could have reasonably concluded that the Amends did not meet their burden to demonstrate a probable, imminent, and irreparable injury. In reply, the Amends argue that a temporary injunction is required to preserve the status quo in this case because there is “no question that the Wat-sons are seeking to permanently and irreversibly change the Amend Property by constructing a 422-foot long wastewater main under it.”
We address the parties’ competing arguments about irreparable injury first because we cannot reverse an order denying a temporary injunction if an applicant did not prove a probable, imminent, and irreparable injury.
See Matrix,
Cargill
is distinguishable from this case because Buie submitted uncontroverted evidence that his property (1) had already suffered actual injury, and (2) was facing imminent depletion of the subsurface mineral resources. Moreover,
Cargill
does not stand for the proposition that an applicant seeking a temporary injunction in a trespass suit is not required to submit evidence to demonstrate irreparable injury, nor does it stand for the proposition that every trespass on land constitutes irreparable injury as a matter of law. We also note that at least one of our sister courts has rejected the similar proposition “that the simple fact that real property is involved mandates injunctive relief’ without a showing of irreparable injury.
Parks v. U.S. Home Corp.,
Similarly, we decline to hold that every trespass constitutes irreparable injury as a matter of law. Instead, applying well-settled Texas law, we conclude that the Amends were required to submit evidence to demonstrate a probable, imminent, and irreparable injury.
Butnaru,
In this case, the Amends pleaded as follows in their petition and application for temporary restraining order and temporary and permanent injunc-tive relief:
Unless enjoined, [the Watsons] will be in a position to commence and will probably commence construction of the waste-water main, thereby causing permanent, irreparable harm to [the Amends’] land. If a temporary [injunction] is not immediately issued by the Court, [the Amends] will be without an adequate remedy at law and will suffer immediate and irreparable harm given the fact that [the Amends] are in immediate danger of having their realty altered in a manner that cannot be undone.
[[Image here]]
If such relief is not granted, [the Amends] will suffer irreparable harmbefore a trial on the merits of this case can be conducted.
Although the Amends generally argued to the trial court that trees could be killed or that the sewer main could leak, “fear and apprehension of injury are not sufficient to support a temporary injunction.”
Matrix,
We do not address the parties’ competing arguments concerning the proper interpretation of the easement and the City code because our conclusion about the merits of the underlying trespass claim would not affect the disposition of this appeal. Tex.R.App. P. 47.1;
see also See Davis v. Huey,
Conclusion
In summary, viewing the evidence in the light most favorable to the trial court’s order, we cannot conclude that the trial court abused its discretion in denying the Amends’ application for temporary injunction. Consequently, we affirm the trial court’s order denying the Amends’ application for temporary injunction. 5
Notes
. Kay Watson is the record title owner of the property. Jim Watson is her husband.
. The Amends cite numerous statements made by the trial court during the temporary injunction hearing and argue that the trial court misconstrued language in the easement and in the City code as a matter of law. However, a judge's statements during a hearing do not constitute written findings and conclusions, and do not limit the grounds upon which an order can be upheld on appeal.
See Larry F. Smith, Inc. v. Weber Co., 110
S.W.3d 611, 615 (Tex.App.-Dallas 2003, pet. denied). And when no findings of fact or conclusions of law have been requested or filed, as in this case, we must uphold an order granting or denying a temporary injunction on any legal theory supported by the record.
Tom James of Dallas, Inc. v. Cobb,
. During his testimony, Jim Watson testified that there are two trees within the City’s easement. He testified that to prevent any damage to the trees or surface of the Amends’ land, the Watsons agreed to pay a higher price for directional boring, as opposed to digging a trench through the surface of the easement. Directional boring will bore the hole for the sewer line seven or eight feet underground starting on the Watsons' property, so that the hole for the eight-inch sewer line can be installed in the City’s easement without affecting the root systems of the Amends' trees. Robert Edwin Farrow, the owner and president of Saber Development, the Watsons’ contractor, testified that the City has signed off on the installation plans, inspected the job site, and given its final written approval for the installation. He also testified that he has done fifty or sixty projects that involved boring for utilities, as opposed to trenching. He has bored under trees and has never had a complaint about injury to a tree.
. Moreover, in exercising its discretion, the trial court was required "to take into account other considerations evident on the face of the pleadings and in the evidence adduced at the temporary-injunction hearing — for example, the issue of comparative injury or a balancing of the ‘equities’ and hardships, including a consideration of the important factor of the public interest.”
Methodist Hosps. of Dallas v. Tex. Indus. Accident Bd.,
.The Amends also filed a separate, unopposed petition for writ of injunction, seeking to preserve this Court's jurisdiction over the subject matter of the dispute pending disposition of this interlocutory appeal. In response, we ordered the original proceeding, this
