delivered the opinion of the court:
This аppeal arises from a building contract entered into between Felix Ambrose, d/b/a F. J. Ambrose Construction Company, (Ambrose), and Aubrey and Beverly Biggs (Biggses), for the construction of a house on property owned by the Biggses. A dispute over the final payout on the contract caused Ambrose to file claims for a mechanic’s lien and breach of contract against, among others, the Biggses. The Biggses counterclaimed for damages. After a bench trial, the court found in favor of Ambrose on its contract claim, against Ambrose on its mechanic’s lien claim, and against the Biggses on their counterclaim. The Biggses appealed.
The contract was signed by the parties on September 1, 1983, and included the following pertinent provisions: (1) payment of the contract price was to be made in three installments — the first payout when construction was under roof, the second payout when the trades were roughed in, and the third and final payout upon substantial сompletion of the building; (2) Ambrose would comply with the Mechanics’ Liens Act (Ill. Rev. Stat. 1983, ch. 82, par. 1 et seq.); (3) the bpilding must be substantially completed in six months; and (4) any extras must be evidenced in writing and any adjustment to the contract price resulting from extras shall be determined by mutual agreement of the parties before starting the work involved.
Ambrose proceeded to build the house, and the Biggses made the first two payouts as the work progressed. The payouts were made despite Ambrose’s lack of compliance with the Mechanics’ Liens Act’s requirement that a sworn contractor’s statement be provided prior to any payouts by the owner. (Ill. Rev. Stat. 1983, ch. 82, par. 5.) During construction, the Biggses, one or both of whom were on the premises nearly every day, ordered several extras which Ambrose duly constructed. In August 1984, as the house neared completion, Ambrose requested the final payout. The Biggses refused to make the payment and Ambrose stopped work.
Ambrose initiаted suit against the Biggses seeking enforcement of a mechanic’s lien and recovery of damages on the contract. The Biggses responded by asserting that Ambrose’s failure to file a proper sworn contractor’s statement vitiated the mechanic’s lien and contract claims. Additionally, the Biggses contended that Ambrose’s failure to substantially complete the contract within the contractually required period entitled them to monetary damages and that Ambrose shоuld be denied payment for extras because there was neither written evidence of the extras nor any agreement concerning their price. The court found, inter alia, that Ambrose’s failure to file a proper sworn contraсtor’s statement precluded the mechanic’s lien claim; the Biggses’ failure to comply with the Mechanics’ Liens Act allowed Ambrose to recover on the contract claim; the Biggses could not recover damages for Ambrose’s delay in completing the house; and the Biggses had waived the procedural requirements of the contractual provision addressing extras.
Before proceeding to the arguments raised by the parties, we note that the trial court’s denial of Ambrose’s mechanic’s lien claim has not been contested on appeal. Therefore, we decline comment on that ruling and confine our decision to the contract claims raised.
The Biggses first contend that Ambrose’s failure to provide a proper sworn contractor’s statement precluded Ambrose from recovering damages on the contract and, therefore, the trial court erred in not dismissing both the mechanic’s lien claim and the contraсt claim. Ambrose, without citation to any supporting legal authority, responds that the trial court correctly found that the Biggses had waived compliance with the mechanic’s lien provision of the contract and Ambrose could therefore recover on the contract. We agree with the Biggses that the trial court should have also dismissed the contract claim.
At issue is whether a contractor can recover damages on a contract claim against an оwner, despite the contractor’s failure to provide a sworn contractor’s statement as provided in section 5 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1983, ch. 82, par. 5). Section 5, which is applicable to every construction cоntract between an owner and a contractor, unequivocally imposes a duty on the contractor to give and the owner to require “a statement in writing, under oath or verified by affidavit, of the names and addresses of the parties furnishing materials and labor, and of the amounts due or to become due each,” before the owner shall be required to pay moneys due to the contractor. (Ill. Rev. Stat. 1983, ch. 82, par. 5.) In an action involving solely a mechanic’s lien claim, the failure of both the owner and contractor to comply with section 5 has been held not to be a bar to a contractor’s mechanic’s lien claim. (Abbott Electrical Construction Co. v. Ladin (1986),
In the present case, however, we are concerned with a contract claim. Contrary to a mechanic’s lien claim, subcontractors are not necessary parties tо a contract claim between an owner and a contractor. As a result, in the context of a contract claim, an owner is not protected from potential subcontractors’ claims unless a proper contraсtor’s statement is provided. Consequently, an owner acts at the risk of valid subcontractors’ claims when making payment to a contractor without the benefit of a contractor’s statement. (Deerfield Electric Co. Inc. v. Herbert W. Jaeger & Associates, Inc. (1979),
The Biggses next contend that they should háve been awarded damages for Ambrose’s delay in completing the house. The contract provided that the house would be substantially completed in six months. Ambrose did not finish working on the house until approximately five months after the scheduled completion date. The Biggses argue that thе trial court erred in ruling that absent a liquidated damages clause, damages for delay are only recoverable in a commercial situation. Relying on Galbraith v. Chicago Architectural Iron Works (1893),
In Galbraith, the court awarded damages for delay in the construction of iron entrance arches to an office building. In awarding damages equal to the rental value of the building for the period of delay, the court stated that: “No inquiry as to what use the appellant had for the premises, is admissible, or whether he could or could not have rented them[;] *** [t]he rental value only is to be cоnsidered in estimating the damages.” (Galbraith v. Chicago Architectural Iron Works (1893),
The owner’s right to recover damages for delay in the construction of a residence is consistent with the remedies available in contract cases. The owner has been denied the use of the building for the period of delay and should be compensated for the loss of use of the premises. (Potter v. Anderson (1970),
The Biggses’ final contention is that the triаl court erred in entering judgment in favor of Ambrose for certain extras that were added to the house. The contract provided that any extras must be evidenced in writing and any adjustment in the contract price resulting from said extras shall be determined by mutual agreement of the parties before starting the work involved. The gist of the Biggses’ argument is that Ambrose’s failure to make timely demands for additional compensation and the absence of proof demonstrating that the Biggses agreеd to pay for the extras precluded Ambrose from recovering payment for the extras in dispute.
In Watson Lumber Co. v. Guennewig (1967),
As stated in Watson, an owner’s agreement to pay for extras can be evidenced by either words or conduct. At least one of the Biggses was on the house site nearly every day of construсtion. They ordered the extras and did not object when Ambrose added the extras to the house. Under these circumstances it has been recognized that an owner impliedly agrees to pay a reasonable price for the extras. (Wingler v. Niblack (1978),
In summary, the trial court erred in finding that Ambrose could recover on the contract and was entitled to compensation for the extras in dispute. The trial сourt erred in denying the Biggses damages for the delay in completion of the building. Because the trial court did not consider what period of delay was attributable to Ambrose, we remand for further consideration on this issue.
For the reasons stated herein, the judgment of the circuit court of Lake County is affirmed in part and reversed in part, and the cause is remanded for further proceedings consistent with this opinion.
Affirmed in part; reversed and remanded in part.
HOPF AND UNVERZAGT, JJ., concur.
