Opinion
— These appeals concern the constitutionality and application of a living wage ordinance enacted by the City of Hayward (City) and incorporated into its municipal contracts. Although Cintas 1 entered into such contracts with the City, it did not provide the minimum wages or benefits required by the ordinance to employees who worked in the company’s stockroom or laundry production facilities, which are located outside of the City. Plaintiffs, representing a class of such employees, sued Cintas for violations of the living wage ordinance, Labor Code section 200 et seq., Business and Professions Code section 17200 and breach of contract. The trial court rejected Cintas’s challenges to the constitutionality of the ordinance and, on cross-motions for summary judgment or summary adjudication, found that Cintas violated the ordinance, breached its contracts with the City, and violated several Labor Code provisions as well as Business and Professions Code section 17200. The court awarded back wages and unpaid benefits, imposed penalties for the Labor Code violations pursuant to the Labor Code Private Attorneys General Act of 2004 (Lab. Code, § 2698 et seq.), and awarded plaintiffs statutory attorney fees and costs. Cintas challenges nearly every aspect of these rulings on appeal. In separate cross-appeals, plaintiffs dispute the trial court’s finding that Cintas’s conduct was not “willful,” challenge the court’s calculation of penalties, and claim they are entitled to recover additional costs.
We conclude the trial court correctly decided all of the numerous legal issues presented. Accordingly, we affirm the judgment and postjudgment orders in their entirety.
During the period from July 1999 through the end of June 2003, the City contracted with Cintas for certain uniform and linen services. Cintas leased the City a variety of uniform garments as well as janitorial items such as shop towels and other towels, mops and industrial doormats. Cintas drivers collected soiled items from various City departments every week and delivered them to a Cintas facility for laundering. During the contract period, items from the City were processed at Cintas plants located in Union City and San Leandro. Cintas production workers would first unload items from the truck and sort them into bins by category (i.e., garments, towels and mats). The items were not separated by customer; instead, the garments and other items collected from the City were, mixed with items from multiple other Cintas customers. Next, the items would be laundered, steamed or pressed (as necessary), inspected for damage, sorted again, and loaded back onto trucks for delivery. Cintas also maintained a stockroom in San Leandro. Stockroom workers filled requests for replacement garments, repaired damaged garments, and either applied or removed customer-requested logos and labels for the garments. Like production workers, Cintas employees in the stockroom worked on items for many different customers each day.
In April 1999, the City adopted the Hayward Living Wage Ordinance (LWO). (Hayward Ord. No. 99-03, adding ch. 2, art. 14, § 2-14.010 et seq. to Hayward Mun. Code.) In connection with this ordinance, the Hayward City Council made the following findings: “a. The City awards many contracts to private firms which provide services and labor to City government and to the public. [¶] b. Experience indicates that many City contractors who provide services and labor pay their employees . . . wages at or slightly above the minimum required by federal and state minimum wage laws. [¶] c. Payment of inadequate compensation does not provide affected employees with resources sufficient to afford a decent standard of living in Hayward. [¶] d. The City intends to require contractors to provide a minimum level of compensation that will improve the level of services rendered to and for the City. [¶] e. Based upon public comment, testimony and studies, the City Council finds that the wage levels set by this ordinance are minimum compensation levels required to afford a decent standard of living in Hayward.” (Hayward Ord. No. 99-03, at § 1.)
The LWO, which applies to all service contracts entered with the City on or after July 1, 1999, requires covered contractors to pay their employees at least $8 per hour if health benefits are provided, or $9.25 per hour if no health benefits are provided. (Hayward Mun. Code, § 2-14.020, subds. (a),
Two months before the ordinance went into effect, the City’s purchasing manager Ralph Costa sent Cintas a complete copy of the newly adopted LWO. In the facsimile cover sheet for this transmission, Costa reminded Cintas that the City intended to “add language to the renewal PO [purchase order] indicating that the contract is subject to the requirements of the ordinance.” On June 9, 1999, the City followed up with a form letter stating that the City’s renewable purchase order with Cintas was subject to the LWO and explaining the LWO’s requirements. The letter asked vendors to indicate whether they would comply with the ordinance, warning that a refusal to comply would result in the vendor’s contract or purchase order being cancelled. Dion Doshier, the general manager of Cintas’s Union City plant, checked a box certifying that Cintas would comply with the LWO and returned the signed letter to the City. Doshier did not recall reading the LWO when he first certified that Cintas would comply with it. He did not discuss its requirements with a representative of the City or with anyone at Cintas; rather, Doshier assumed the contract was being renewed under the same terms and conditions as had previously applied.
The following year, on June 2, 2000, the City sent a letter informing Cintas of the new hourly minimum wages required under the LWO (based on cost of living adjustments). Once again, a representative of Cintas signed and returned the letter, certifying that Cintas would comply with the LWO.
4
In addition, purchase orders from the City covering the period from July 1, 1999, through June 30, 2003, were stamped with the statement, “CINTAS agrees to comply with The City of Hayward Living Wage Ordinance . . . .”
5
In late May 2003, the City contacted Cintas about renewing its purchase order. When Matthew Ketchem, the general manager of Cintas’s San Leandro plant, reviewed the paperwork forwarded by the City, he noticed statements requiring compliance with the Hayward Living Wage Ordinance. Ketchem asked around throughout the service department, but no one knew what the LWO was and no one had contacted the City to find out. Ketchem contacted his supervisor, a regional vice-president based in Seattle, Washington, and was told to terminate the contract. By letter of July 3, 2003, Cintas terminated its contract with the City. Throughout the period from 1999 to 2003, revenue from the City of Hayward contract constituted less than 1 percent of the total revenue Cintas received from all customers serviced at the Union City and San Leandro facilities.
On June 23, 2003, plaintiffs filed a class action complaint against Cintas based on the company’s failure to compensate its Union City and San Leandro employees at hourly rates required by the LWO. The complaint alleged Cintas violated the LWO and associated Labor Code provisions (Lab. Code, §§ 204, 227.3), engaged in an unfair and unlawful business practice (Bus. & Prof. Code, § 17200), and breached its contract with the City of Hayward. After the Legislature enacted the Labor Code Private Attorneys General Act of 2004 (Lab. Code, § 2698 et seq.), which permits aggrieved employees to recover Labor Code penalties that previously could be pursued only by the Labor Commissioner, plaintiffs amended their complaint to seek additional penalties. The trial court certified a class consisting of all production and stockroom workers employed by Cintas at its facilities in Union City and San Leandro between July 1, 1999, and June 30, 2003. The court also permitted the City of Hayward to intervene as a plaintiff.
Early in the proceedings, Cintas moved for summary judgment on the ground that the City lacked authority to regulate wages for work performed outside of Hayward’s territorial boundaries. (Cal. Const., art. XI, § 7.) The trial court denied the motion, concluding application of the LWO was a proper exercise of the City’s contracting power. After the case proceeded through discovery, on September 23, 2005, the court ruled on cross-motions for summary judgment or summary adjudication filed by Cintas, the City and plaintiffs. Specifically, the court determined the LWO was not unconstitutional on its face or as applied to Cintas and was not so ambiguous as to render the contract between Cintas and the City unenforceable. The court
After the parties entered a stipulation to resolve certain matters for purposes of facilitating an appeal (see
Norgart
v.
Upjohn Co.
(1999)
Plaintiffs moved to recover their costs and attorney fees, based on Code of Civil Procedure section 1021.5 and fee-shifting provisions of the LWO and Labor Code. This motion was granted in part and denied in part. The trial court awarded fees of $1,199,550, calculated using a lodestar amount of $727,000 and a multiplier of 1.65, plus fees of $60,611 for work on the fee motion itself. The court also awarded $498 in nonstatutory costs but denied plaintiffs’ attempt to recover additional litigation expenses. As before, Cintas filed a notice of appeal from the order granting attorney fees, and plaintiffs cross-appealed. We consolidated all of the appeals and cross-appeals for briefing, oral argument and decision.
DISCUSSION
Most of the issues were summarily adjudicated below based on undisputed facts; accordingly, they are subject to de novo review on appeal.
(Guz v. Bechtel National, Inc.
(2000)
I. Constitutionality of the LWO
A. Extraterritoriality
Cintas’s first constitutional challenge to the LWO rests on article XI, section 7 of the California Constitution, a provision which Cintas contends
Article 11, section 7 states that a “county or city may make and enforce within its limits all local, police, sanitary, and other ordinances and regulations not in conflict with general laws.” (Cal. Const., art. XI, § 7.) The Supreme Court summarized this provision as meaning: “A municipal corporation has generally no extraterritorial powers of
regulation.
It may not exercise its
governmental functions
beyond its corporate boundaries. [Citations.]”
(City of Oakland
v.
Brock
(1937)
It is beyond dispute that City, as a charter city, has the power to enter contracts to carry out its necessary functions and may place conditions or specifications on the bidding for such contracts.
(Carruth v. City of Madera
(1965)
Although the issue of extraterritorial effects did not arise in
Alioto’s,
a more recent decision confirms that such effects do not invalidate an otherwise appropriate exercise of a local government’s contracting authority. In
Burns, supra,
In sustaining the county’s demurrer, the trial court in
Bums
concluded the Los Angeles County ordinance was valid “even if interpreted to require contracting parties to provide at least five days of paid jury duty leave to all of its employees who reside in California regardless of whether the employees would be providing service under any County contract.”
(Burns, supra,
The same is true here. The LWO does not purport to regulate conduct outside of Hayward’s boundaries; rather, it specifies certain conduct the City wants its contracting partners to follow. It does not matter, for constitutional purposes, whether contractors may have to perform this required conduct outside the City’s boundaries. The point is that the City’s only action is proprietary: It is the decision to enter a contract, or not, depending on whether the contractor agrees to pay its employees a living wage. Although the LWO may have extraterritorial effects when contractors must pay a living wage to employees who live or perform work outside of the City, these effects do not render the City’s exercise of its contracting power unconstitutional. (See Air
Transport
v.
City and County of San Francisco, supra,
Cintas also argues the regulatory nature of the LWO is belied by the fact that it prescribes more than just contractual remedies in the event of a violation. It is true that, unlike the ordinances at issue in Bums and Alioto ’s, the LWO purports to give employees a private right of action against their employer for violation of the LWO. (Hayward Mun. Code, § 2-14.040, subd. (a).) However, it does so by requiring each service contractor to agree to submit to a civil action by aggrieved employees. (Id., § 2-14.040, subd. (b).) The requirements of the LWO, and the enforcement mechanisms it provides, reach beyond the City’s boundaries only to the extent that outside parties choose to contract with the City. The fact that some enforcement measures, such as employee lawsuits or fines (id., § 2-14.040, subd. (e)), go beyond traditional contract remedies does not convert the City’s exercise of contracting power into an extraterritorial regulation. Companies that wish to avoid the LWO’s enforcement measures can do so simply by choosing not to bid on service contracts with the City.
B. Vagueness
Cintas also argues the LWO is so vague that it violates due process under the federal and state Constitutions. “[D]ue process of law is violated by ‘a statute which either forbids or requires the doing of an act in terms so vague that men of common intelligence must necessarily guess at its meaning and differ as to its application.’ [Citations.]”
(Britt v. City of Pomona
(1990)
In the trial court, Cintas attempted to support its arguments on the vagueness of the LWO and on the interpretation of the LWO, should it be applied, with statements made by City employees. In particular, Cintas relied on statements from acting assistant city manager, Perry Carter, whom the City had designated as its person most knowledgeable for deposition (Code Civ. Proc., § 2025.230) about the interpretation, application and enforcement of the LWO. Among other things, Carter stated in deposition that he could “certainly see” why contractors might find certain aspects of the LWO’s application ambiguous. The trial court excluded this evidence on the ground that the statements were inadmissible opinion testimony on a legal issue. Nevertheless, Cintas continues to rely heavily on such testimony and statements made by City officials to support its argument that the LWO is unconstitutionally vague.
The trial court’s ruling was correct. Opinion evidence about the meaning of a statute, whether from a lay person or a purported expert, has long been held inadmissible.
(People v. Torres
(1995)
2. LWO Not Unconstitutionally Vague
We turn now to Cintas’s claim that the LWO is impermissibly vague.
The Supreme Court has articulated two guiding principles for evaluating vagueness claims. “The first principle is derived from the concrete necessity that abstract legal commands must be applied in a specific
context. A
contextual application of otherwise unqualified legal language may supply the clue to a law’s meaning, giving facially standardless language a constitutionally sufficient concreteness. Indeed, in evaluating challenges based on claims of vagueness, the [United States Supreme Court] has said ‘[t]he particular context is all important.’ [Citation.]”
(Acuna, supra,
“The second guiding principle is the notion of
‘reasonable
specificity’ [citation] or ‘ “
‘[reasonable
certainty.’ ” ’ [Citations.] . . . ‘[F]ew words possess the precision of mathematical symbols, most statutes must deal with untold and unforeseen variations in factual situations, and the practical necessities of discharging the business of government inevitably limit the specificity with which legislators can spell out prohibitions. Consequently, no' more than a reasonable degree of certainty can be demanded. Nor is it unfair to require that one who deliberately goes perilously close to an area of proscribed conduct shall take the risk that he may cross the line.’ [Citation.]”
(Acuna, supra,
Cintas complains of three specific areas of ambiguity in the LWO: (1) whether a service contractor must pay employees the LWO rate for all hours worked, or only for time spent working on a Hayward contract; (2) whether the LWO applies to work performed outside of the City; and (3) whether the LWO applies to employees who do not work “directly” on Hayward projects. These three areas all boil down to questions about how the LWO should be interpreted to apply to the somewhat unusual situation of a service contractor that performed work in geographical locations outside the City and comingled work employees performed on the City’s contract with work performed for all other customers. The ordinance itself does not mention where work covered by the LWO is to be performed or which of an employee’s hours may or may not be subject to the LWO. It simply states that service contractors such as Cintas
11
must pay their employees certain minimum wages, where “employee” is defined as a person “employed ... on or under the authority of’ a service contract with the City. (Hayward Mun.
In passing the LWO, “[t]he City intended] to require contractors to provide a minimum level of compensation that will improve the level of services rendered to and for the City.” (Hayward Ord. No. 99-03, § 1(d), adding ch. 2, art. 14, § 2-14.010 et seq. to Hayward Mun. Code.) In other words, the City wanted employees who provide services to the City under service contracts to be paid a living wage because it believed payment of this wage would improve the quality of services such employees render. The City Council’s statement of intent, along with a provision in the LWO stating that the ordinance should be applied to the City’s service contracts “[t]o the maximum extent permitted by law” (Hayward Mun. Code, § 2-14.020, subd. (b)), indicates the LWO applies — -just as its language states — to all employees who work on or under a service contract with the City. There is no inherent vagueness in the statutory language, and adopting the plain meaning of this language serves the broad remedial purpose the City Council evidently intended.
It is true that the terms of the LWO do not spell out precisely how the ordinance will apply in situations where contractors perform work outside of the City or commingle an employee’s contract-related work with work for other customers. However, due process “does not . . . require that statutes must be drafted with the precision of a laser.”
(Personal Watercraft Coalition
v.
Marin County Bd. of Supervisors, supra,
Considering the purpose for which the LWO was enacted, it is “ ‘ “reasonable and practical” ’ ” to construe its language as requiring payment of a living wage to all employees who perform work for the City under a service contract.
(Personal Watercraft Coalition v. Marin County Bd. of Supervisors, supra,
II. Interpretation of LWO for Class Members’ Claims
Having rejected Cintas’s challenges to the constitutionality of the LWO, we now consider whether the trial court properly interpreted the requirements of the ordinance. Because Cintas’s claims in this regard raise issues of law, they are subject to de novo review.
(People ex rel Kennedy v. Beaumont Investment, Ltd.
(2003)
“We interpret ordinances by the same rules applicable to statutes. [Citation.]”
(Carson Harbor Village, Ltd. v. City of Carson Mobilehome Park Rental Review Bd.
(1999)
A. LWO Applies to the Cintas Contracts with Hayward
The City repeatedly advised Cintas, by letter and by statements stamped on the purchase orders, that its contracts with the company were subject to Cintas’s compliance with the LWO, and Cintas twice certified that it would comply with the ordinance. Nevertheless, despite its previous promise to comply, Cintas now argues the LWO does not apply to these contracts.
First, Cintas contends the plaintiff class members do not fit the LWO’s definition of employees because they rendered a service to Cintas, not to the City. According to Cintas, to be employed “on or under the authority” of a service contract “requires some agreement between the contracting parties as to the employment of individuals.” This argument is waived because it was not presented to the trial court. 12 (9 Witlcin, Cal. Procedure (4th ed. 1997) Appeal, § 394, pp. 444-445.) It is also nonsensical. The LWO defines a covered employee as “any individual employed by a service contractor on or under the authority of any contract for services with the City . . . .” (Hayward Mun. Code, § 2-14.010, subd. (c).) Plaintiffs were employed by Cintas, a “service contractor.” When they laundered and maintained uniforms used by the City, plaintiffs were carrying out Cintas’s obligations under service contracts with the City. Accordingly, these employees were working “on or under the authority of” a service contract. It makes no difference that the uniforms themselves were owned by Cintas and not the City; the point is that plaintiffs’ work for Cintas provided a service to the City that the City had contracted with Cintas to receive. Since it can be argued that many employees provide services to their employers, not their employers’ customers, Cintas’s interpretation would render the LWO inapplicable to many, if not all, contractors due to circumstances outside the City’s control. Such a result would undermine the broad remedial purpose of the ordinance.
B. LWO Covers All Hours of Employees Who Worked on the Contracts
Cintas next contends plaintiff class members have no claim under the LWO because the ordinance dictates a minimum level of pay only with respect to the time an employee spends working on a service contract. According to Cintas, the time any plaintiff spent working on items for the City was de minimis.
We start with the language of the ordinance. “If the statutory language is clear and unambiguous our inquiry ends.”
(Murphy v. Kenneth Cole Productions, Inc., supra,
The definition of a covered employee as someone working “on or under the authority of’ a service contract limits the scope of a contractor’s obligation in one respect, because it means the contractor need not pay all of its employees the required wage, but only those employees who do work for the City. However, no provision of the LWO limits the contractor’s obligation further, as Cintas suggests, by mandating a living wage
only
for the time an employee spends performing tasks related to the service contract with Hayward. If the City had intended to restrict the application of the LWO in this manner, it could have easily inserted the phrase “for hours worked on the contract” in the subdivision describing the ordinance’s “Living Wage Requirements” (Hayward Mun. Code, § 2-14.020, subd. (c)). (Cf.
Aguiar v. Cintas Corp. No.
2,
supra,
It might also have been possible to infer an intent to restrict the wage requirements to actual hours worked on a service contract if the LWO included any recordkeeping requirements. Because the ordinance does not require contractors to keep track of the amount of time any employee has spent on work related to a service contract with the City, it is reasonable to infer the City intended to require LWO compensation for all hours worked by those employees a contractor assigns to work on a City contract. Without such records, it would be impossible for the City to audit a contractor’s compliance with the LWO, as Cintas construes it. (See Hayward Mun. Codej § 2-14.040, subd. (d) [giving City authority to “investigate and address’,]!, alleged violations].) Cintas’s construction would also render the computatioii of compensated days off (Hayward Mun. Code, § 2-14.020, subd. (d)|_ confusing or, in the absence of detailed time records, impossible.
Finally, Cintas again points to statements by City officials as evidence supporting a contrary interpretation of the ordinance. “Only when the statute’s language is ambiguous or susceptible of more than one reasonable interpretation, may the court turn to extrinsic aids to assist in interpretation. [Citation.]”
(Murphy
v.
Kenneth Cole Productions, Inc., supra,
C. All Class Members Are “Employees” Under the LWO
In a related point, Cintas complains the trial court erred in shifting the burden to require Cintas to prove which of its employees worked on the City contracts. Cintas asserts there was no showing that any class
Undisputed evidence establishes that Cintas did not separate work related to the City contracts from work performed for other customers. No employees were specifically assigned to process City items, and, since these items were not tagged or identified in any distinct way in the production process, it is impossible to tell in retrospect which Cintas employees performed work on the City contracts. Because work on the City contracts was distributed among all Cintas employees, the general manager of Cintas’s San Leandro plant observed that “[a]lmost any production worker might [have] work[ed] on Hayward’s laundry or linens.” Based on this evidence, the trial court found: “the most likely state of affairs is that every employee in the class worked for some amount of time on the City contract and .. . there is no way of knowing whether the amount of work — in terms of time, revenue generated, pounds of laundry, or any other measurement — was large, small, or non-existent for any given class member.” (Fn. omitted.)
Cintas does not dispute the factual basis of this finding. Indeed, the company admitted in response to plaintiffs’ summary judgment motion that it has “no records or other data establishing which Union City or San Leandro Class Members worked on Contract Items during the Class Period.” Instead, Cintas claims the trial court committed legal error by shifting the burden of proof to it to prove which class members did no work on the City contracts and thus were not entitled to be compensated under the LWO.
In general, “[ejxcept as otherwise provided by law, a party has the burden of proof as to each fact the existence or nonexistence of which is essential to the claim for relief or defense that he is asserting.” (Evid. Code, § 500.) On occasion, however, courts may alter the normal allocation of the burden of proof.
(National Council Against Health Fraud, Inc. v. King Bio Pharmaceuticals, Inc.
(2003)
Relying on
Anderson,
California courts have shifted the burden of proof to employers when inadequate records prevent employees from proving their claims for unpaid overtime hours
(Hernandez v. Mendoza
(1988)
In addition, California has long approved of burden shifting outside the wage and hour context when the parties have unequal access to evidence necessary to prove a disputed issue. “ ‘Where the evidence necessary to establish a fact essential to a claim lies peculiarly within the knowledge and competence of one of the parties, that party has the burden of going forward with the evidence on the issue although it is not the party asserting the claim.’ [Citations.]”
(Sanchez v. Unemployment Ins. Appeals Bd.
(1977)
It makes sense to apply burden shifting in this case because, as plaintiffs’ employer, Cintas is in the best position to know which class members worked on the City contracts and at which times. Although the LWO imposes no recordkeeping requirements as such, 13 the entire aim of the ordinance is to require contractors to pay a living wage to employees who work on service contracts with the City. Thus, if a contractor does not wish to compensate all its employees in accordance with the LWO, the onus is on the contractor to segregate work on City contracts and assign it to specific employees, or at least to keep records of which employees perform contract-related work. Given Cintas’s control over workflow and its greater knowledge about the obligations imposed by the LWO, it would be unrealistic and unfair to expect individual class members to prove they performed work related to the City contracts.
Cintas attempts to distinguish the numerous precedents in favor of burden shifting by arguing that in all of these cases the employer had a duty to maintain records, whereas the LWO does not explicitly impose such a duty. However, the underlying rationale for burden shifting is not the employer’s duty of recordkeeping but the “fundamental principle of American jurisprudence that for every wrong there is a remedy, and that, unless countered by public policy, an injured party should be compensated for all damage proximately caused by the wrongdoer. [Citations.]”
(Hernandez v. Mendoza, supra,
In addressing the exact same facts regarding Cintas’s failure to segregate work to comply with a living wage ordinance, Division Seven of the Second District Court of Appeal relied on the precedents we have discussed and concluded burden shifting was appropriate. (Aguiar v. Cintas Corp. No. 2, supra, 144 Cal.App.4th at pp. 134-135.) The Los Angeles ordinance in question applied only to employees who had worked at least 20 hours per month on a covered contract, and Cintas argued this 20-hour rule created a distinction between the plaintiffs sufficient to defeat treatment of their claims in a class action. (Id. at pp. 133-134.) The appellate court concluded this difference could be remedied by use of subclasses, and it went on to note that the problem of identifying which employees are covered by the ordinance would rightly fall on Cintas: “To the extent questions arise later in the litigation about how to determine which putative class members worked at least 20 hours per month on the DWP [Department of Water and Power] contracts, or whether their schedules varied from month to month, that burden falls on Cintas. It was Cintas’s business decision to commingle DWP items with those of other customers and to allow all employees to work on the items at each substation (for example, sorting, hanging, folding) as they were processed through the plant.” (Id. at p. 134, italics added.) Because Cintas’s business decision likewise created the difficulty of determining which class members worked on the City contracts in this case, we too conclude Cintas must bear the burden of proof on the issue. In other words, Cintas has the burden of negating the inference plaintiffs established that they worked on the City contracts and were thus covered by the LWO.
Finally, we reject Cintas’s assertion that the LWO does not apply at all because the evidence suggests no individual class member worked more than a de minimis amount on items related to the City contracts. The LWO contains no exception to its requirements when the amount of an employee’s work on a contract is arguably very small or de minimis. Because it would contradict both the language and the purpose of the LWO, we decline to read such an exception into the ordinance.
III. Enforceability of the Contracts
Cintas next contends the trial court erred in granting summary judgment on plaintiffs’ breach of contract claims. In entering purchase contracts with the
A. Uncertainty of Contract Terms
Cintas’s challenge to the enforceability of the contracts rests on its claim that the terms of the LWO are unconstitutionally vague. We have rejected this constitutional claim, however, because the meaning of the LWO can be ascertained with reasonable certainty. (See
Acuna, supra,
“Where a contract is so uncertain and indefinite that the intention of the parties in material particulars cannot be ascertained, the contract is void and unenforceable. [Citations.]”
(Cal. Lettuce Growers
v.
Union Sugar Co.
(1955)
Cintas repeatedly agreed to comply with the LWO when it entered into the purchase contracts and sent two separate certifications to the City. As we explained in relation to Cintas’s constitutional challenge, the terms of this ordinance were not so vague or uncertain that Cintas could not have understood what its obligations were. The LWO simply requires a contractor
B. Intended Beneficiaries
Cintas next complains plaintiffs cannot sue to enforce the contractual promise to comply with the LWO because plaintiffs were not intended third party beneficiaries of the contracts with the City. A person who is not a party to a contract may nevertheless enforce it if the contract was made expressly for his benefit. (Civ. Code, § 1559.) For a third party to qualify as a beneficiary of a contract, the contracting parties must have intended to benefit that third party and their intent must be evident in the terms of the contract.
(Jones
v.
Aetna Casualty & Surety Co.
(1994)
This issue has been addressed by Courts of Appeal in the analogous context of California’s prevailing wage law. (Lab. Code, §§ 90.5, 1720-1861.) This law requires that all contractors and subcontractors working on a public works contract must pay their employees the prevailing wage rate for work performed on the contract. (Lab. Code, §§ 1771, 1774.) Although the Labor Code imposes a statutory duty to pay prevailing wages and the prevailing wage law is incorporated into public works contracts, our Supreme Court has not yet decided whether employees have a right to enforce the prevailing wage law absent a specific provision in their employment contracts.
(Department of Industrial Relations v. Fidelity Roof Co.
(1997)
In
Tippett v. Terich
(1995)
The same reasoning persuades us that plaintiffs are third party beneficiaries of the contract in which Cintas agreed to comply with the LWO. Like the prevailing wage law, the LWO is clearly intended to benefit employees by requiring the payment of higher wages. (See Hayward Ord. No. 99-03, § 1(c), (e) [finding the payment of a living wage is necessary to allow employees “to afford a decent standard of living in Hayward”].) Because employees who work on City contracts are intended third party beneficiaries of the provision requiring compliance with the LWO, these employees may sue for their employer’s breach of contract in failing to pay a living wage. (Cf.
Fidelity Roof, supra,
IV. California Labor Code Violations
In addition to alleging violations of the LWO itself, plaintiffs sought to recover penalties for various Labor Code violations. Specifically, plaintiffs alleged Cintas violated Labor Code sections 201, 202 and 204
16
by failing to
When proven, Labor Code violations give rise to civil penalties. Some statutory penalties are imposed only if an employers’ violation was “willful” or “knowing.” Relevant to the claims here, section 203 penalizes an employer that “willfully” fails to pay wages due under sections 201 or 202, and section 226, subdivision (e) penalizes an employer’s “knowing and intentional” failure to provide itemized wage statements under section 226, subdivision (a) (see also § 226.3 [providing civil penalties for violation of § 226, subd. (a) but directing Labor Commissioner to consider whether violation was inadvertent]). Two other penalty statutes impose penalties regardless of the employer’s mental state but provide for higher penalties if the violation is “willful or intentional.” (Former §§ 210, as amended by Stats. 1983, ch. 1096, § 1, p. 4103 [penalties for violation of § 204], 225.5, as amended by Stats. 1983, ch. 1096, § 2, p. 4103 [penalties for violation of § 223].) Plaintiffs argued they were entitled to the maximum penalties under these statutes, however the trial court disagreed. Because the court concluded Cintas’s conduct was not “willful,” it declined to impose or increase penalties under all provisions that include a “willfulness” component. In their cross-appeal from the judgment, plaintiffs challenge the court’s finding on willfulness. They also complain the court underassessed applicable penalties, even assuming the finding on willfulness was correct.
Plaintiffs’ right to pursue most of these Labor Code penalties came about with the passage of the Private Attorneys General Act (PAGA). (§ 2698 et seq.) Their original complaint, filed on June 23, 2003, sought waiting time penalties under section 203 but no other Labor Code penalties. However, on September 16, 2004, plaintiffs filed a second amended complaint to seek additional penalties under PAGA, which went into effect on January 1, 2004. In addition to establishing new civil penalties for Labor Code violations that did not previously carry a penalty (§ 2699, subd. (f)), PAGA allows aggrieved employees to recover Labor Code penalties directly from their employers. (§ 2699, subd. (g).) Previously, only the Labor Commissioner was authorized to pursue such remedies. (See, e.g., former §§ 210, subd. (b), 225.5, subd. (b) [stating penalty is to be recovered by the Labor Commissioner].) If an employee successfully recovers an award of civil penalties, PAGA requires that 75 percent of the recovery be paid to the Labor and Workforce Development Agency, with the remaining 25 percent going to the employee. (§ 2699, subd. (i).) Because PAGA did not become effective until after plaintiffs filed their lawsuit, Cintas argued its provisions could not be applied
We address first whether plaintiffs were entitled to rely on PAGA to penalize conduct that occurred before the statute went into effect. We next address the court’s threshold finding that Cintas’s conduct was not “willful” for purposes of the penalty provisions. Finally, we consider each side’s arguments pertaining to the calculation of penalties.
A. Application of PAGA to Preenactment Conduct
1. Retroactivity
Before the enactment of PAGA, divisions of the Labor and Workforce Development Agency — in particular, the Labor Commissioner — had the sole statutory authority to assess and collect civil penalties for many Labor Code violations. However, in 2003 the Legislature determined that shortages in funding and staffing in these agencies were preventing vigorous pursuit of civil penalties and thus hampering their intended deterrent effect.
17
(Stats. 2003, ch. 906, § 1;
Caliber Bodyworks, Inc. v. Superior Court
(2005)
Plaintiffs amended their complaint to seek penalties under the newly enacted PAGA for Cintas’s violations of various Labor Code provisions. Thus, the question arises whether PAGA may be applied in pending cases such as the present one, or whether doing so would have an impermissible retroactive effect. The trial court ruled that the expanded standing granted to private parties under PAGA could be applied immediately; however, the court determined that plaintiffs were precluded from pursuing any new penalties created by PAGA for claims that accrued before the statute went into effect.
18
“New statutes are presumed to operate only prospectively absent some clear indication that the Legislature intended otherwise. [Citations.]”
(Elsner
v.
Uveges
(2004)
“[A] retroactive or retrospective law ‘ “is one which affects rights, obligations, acts, transactions and conditions which are performed or exist prior to the adoption of the statute.” ’
(Aetna Cas. & Surety Co.
v.
Ind. Acc. Com.
(1947)
The enactment of PAGA expanded the universe of parties who can collect penalties from employers for Labor Code violations. In this case, the only effect of the new statute was to allow private parties — class members who are present or former employees of Cintas — to recover penalties that previously could have been recovered only by the state Labor Commissioner. This change did not increase Cintas’s liability in any way, because the Labor Commissioner could have recovered the
same
penalties for Cintas’s violations before the passage of PAGA.
19
It does not matter that Cintas’s wrongful conduct occurred before PAGA was enacted because the legal consequences
In addition, although neither party discussed the case in its briefing, we find support for our conclusion in the Supreme Court’s analysis in
Californians for Disability Rights
v.
Mervyn’s, LLC
(2006)
Our case is the procedural opposite of
Mervyn’s,
because PAGA granted private parties standing whereas Proposition 64 took their standing away absent a showing of injury. But the high court’s analysis of retroactivity is directly on point. Like Proposition 64, PAGA did not impose new or different liabilities on defendants based on their past conduct. (See
Mervyn’s, supra,
Having concluded the statute is not retroactive in effect, we need not address the parties’ attempts to divine legislative intent about the application of PAGA to past conduct.
2. PAGA Claims Relate Back to Original Complaint
In a related argument, Cintas contends the trial court erred in concluding plaintiffs’ claim for PAGA-based penalties relates back to their original complaint. This conclusion was important for the calculation of penalties, since the trial court determined that PAGA penalties are subject to a one-year statute of limitations. (Code Civ. Proc., § 340.)
“The prevailing rule with respect to actions involving parties designated by their true names in the original complaint is that, if an amendment is sought after the statute of limitations has run, the amended complaint will be deemed filed as of the date of the original complaint provided recovery is sought in both pleadings on the same general set of facts.
(Austin
v.
Massachusetts Bonding & Insurance Co.
(1961)
Plaintiffs’ request for PAGA penalties in the second amended complaint was based on the exact same facts alleged in their original complaint regarding Cintas’s failure to comply with the LWO. The factual basis of Cintas’s liability is the same, and the resulting injury plaintiffs allege is the same. It is true that plaintiffs could not have included a claim for PAGA penalties in their original complaint, because it was filed before PAGA was enacted, but this fact does not change the analysis. As the trial court observed, PAGA was at most a new theory of recovery that became available to plaintiffs during the pendency of their lawsuit, and claims based on new legal theories may relate back so long as they address the same set of facts. (Grudt v. City of Los Angeles, supra, 2 Cal.3d at pp. 583-584; see also Lamont v. Wolfe, supra, 142 Cal.App.3d at pp. 381-382 [even though wrongful death claim could not have existed when original complaint was filed, because decedent was alive, relation back doctrine applied because plaintiff was seeking recovery for what was essentially the same loss].)
Cintas does not directly dispute these conclusions. Rather, Cintas suggests it was improper for the court to allow plaintiffs to recover any PAGA penalties if the statute of limitations would have barred the Labor Commissioner from pursuing such claims when plaintiffs filed their second amended complaint on September 16, 2004. This argument is a red herring. Assuming it is appropriate to compare plaintiffs’ claims with claims the Labor Commissioner could have filed, the proper question would be whether the commissioner could have added penalties in September 2004 to an action initiated in June 2003. In light of the relation-back precedents we have discussed, the commissioner could indeed have added such penalty claims, so long as they concerned the same underlying conduct previously complained of, and the claims would not be time-barred.
We turn next to plaintiffs’ argument in the cross-appeal that Cintas’s Labor Code violations were willful, such that plaintiffs were entitled to recover “waiting time” penalties under section 203 and other penalties.
The settled meaning of “willful,” as used in section 203, is that an employer has intentionally failed or refused to perform an act which was required to be done.
(Barnhill v. Robert Saunders & Co.
(1981)
In
Barnhill,
this court considered whether an employer’s failure to pay wages is “willful” if its legal duty to pay them is unclear at the time of the violation. When the employee in
Barnhill
was discharged, she owed her employer a balance on a promissory note, which was intended to be repaid in installments by payroll deductions.
(Barnhill, supra,
Barnhill’s holding was memorialized in California Code of Regulations, title 8, section 13520. This regulation states: “A willful failure to pay wages within the meaning of Labor Code Section 203 occurs when an employer intentionally fails to pay wages to an employee when those wages are due. However, a good faith dispute that any wages are due will preclude imposition of waiting time penalties under Section 203. [¶] (a) Good Faith Dispute. A ‘good faith dispute’ that any wages are due occurs when an employer presents a defense, based in law or fact which, if successful, would preclude any recover on the part of the employee. The fact that a defense is ultimately unsuccessful will not preclude a finding that a good faith dispute did exist. Defenses presented which, under all the circumstances, are unsupported by any evidence, are unreasonable, or are presented in bad faith, will preclude a finding of a ‘good faith dispute.’ ” (Cal. Code Regs., tit. 8, § 13520.)
Plaintiffs argue the lack of case law setting forth an employer’s obligations is not dispositive on the issue of willfulness, relying on
Armenta v. Osmose, Inc.
(2005)
Armenia
and
Road Sprinkler Fitters
do not support plaintiffs’ position. Here, there is no evidence showing Cintas ever knew it was required to compensate its production workers at the rates prescribed in the LWO, or showing the company acted in bad faith when it failed to pay such rates. On the contrary, the trial court expressly distinguished
Road Sprinkler Fitters
Plaintiffs have directed us to no evidence that contradicts this finding of good faith. Instead, they complain the trial court focused on the wrong timeframe. Rather than asking whether an employer currently offers a good faith defense to the payment of wages, plaintiffs insist nonpayment of wages must be considered willful unless the employer relies upon a good faith defense
at the time the wages are due.
Because evidence from Cintas’s general managers indicates the company did not pay attention to the LWO’s requirements, or attempt to comply with them, plaintiffs argue Cintas cannot have relied on its current legal defenses when it failed to pay class members LWO wages during the contract period. However, despite plaintiffs’ creative interpretations of language in certain cases and the applicable regulation, there is no legal support for the requirement plaintiffs would impose. Nothing in California Code of Regulations, title 8, section 13520 requires that a “good faith dispute” must exist at the time wages are due. On the contrary, the regulation simply states that a good faith dispute “occurs when an employer presents a defense, based in law or fact which, if successful, would preclude any recover on the part of the employee.” (Cal. Code Regs., tit. 8, § 13520, subd. (a).) Compared with the broader word “dispute,” also used in the regulation, a “defense” is something typically asserted in the context of litigation. In contrast with the general notion of a dispute, a defense in
This court’s decision in
Barnhill
did not hold otherwise.
Barnhill
includes no factual finding or discussion regarding when the employer believed it had a legal right to set off the balance of a promissory note against her wages. We noted that the state of the law was unclear when the trial court determined the employer had no right to make such a setoff, but we did not attempt to divine the employer’s subjective belief about the law or when this belief was formulated. (Barnhill,
supra,
C. Amount of Labor Code Penalties
Cintas raises two types of challenges in regard to the amount of penalties awarded. First, Cintas argues it is not liable for penalties that were imposed pursuant to specific penalty provisions. Next, Cintas claims the trial court abused its discretion in awarding full penalties under PAGA because it failed to follow the guidelines of the Department of Labor Standards and Enforcement (DLSE) and set the penalties in an unjust, arbitrary and oppressive amount. We examine whether penalties could be imposed against Cintas under the specific statutes and then consider whether the trial court abused its discretion in declining to reduce the penalty award.
1. Challenges to Specific Penalties
a. Section 223: Secret Underpayments
Cintas claims the trial court erred in awarding penalties for a violation of section 223, which provides: “Where any statute or contract requires an employer to maintain the designated wage scale, it shall be unlawful to secretly pay a lower wage while purporting to pay the wage designated by statute or by contract.” The evidence below showed that although Cintas was on notice of its obligations under the LWO and certified to the City its intention to comply with the LWO, Cintas failed to pay class members at the LWO rate. The trial court concluded these facts established a violation of section 223.
On appeal, Cintas claims the trial court misinterpreted section 223. According to Cintas, this statute only applies when an employer has kept secret
from
Cintas correctly observes that section 223 was enacted to address the problem of employers taking secret deductions or “kickbacks” from their employees.
(Kerr’s Catering Service v. Department of Industrial Relations
(1962)
Moreover, Cintas’s construction is inconsistent with the plain language of the statute. Section 223 deems it unlawful “to secretly pay a lower wage while purporting to pay” the higher wage required by law or contract. Accordingly, the statute punishes secret underpayment. Under Cintas’s interpretation, it could only have violated section 223 if it kept secret from its employees that they were entitled to be paid a higher wage than they received. But, in such case, the secret is not the making of an “underpayment” but rather the existence of the employer’s obligation to pay more. If the Legislature wished to penalize employers for failing to advise employees of their right to receive a higher wage, one would expect it to say so directly.
Cintas does not dispute the factual basis of the trial court’s ruling. Cintas represented to the City that it would pay its employees in accordance with the LWO, and it certified its compliance with the ordinance even though it was in fact paying its production workers lower wages. These facts are sufficient to establish a violation of section 223. (See
Shalz v. Union School Dist., supra,
Next, Cintas contends the trial court erred in awarding PAGA penalties of $500 for a violation of section 227.3. 22 Section 227.3 states, in relevant part: “Unless otherwise provided by a collective-bargaining agreement, whenever a contract of employment or employer policy provides for paid vacations, and an employee is terminated without having taken off his vested vacation time, all vested vacation shall be paid to him as wages at his final rate in accordance with such contract of employment or employer policy respecting eligibility or time served; provided, however, that an employment contract or employer policy shall not provide for forfeiture of vested vacation time upon termination.”
Cintas argues penalties are not appropriate here because section 227.3 requires an employer to compensate employees for their accrued vacation time in accordance with “a contract of employment or employer policy,” and the LWO is neither of these things. Plaintiffs counter that the LWO’s provisions were “effectively incorporated” into their employment contracts. The trial court reached a similar conclusion, noting the LWO entitled plaintiffs to additional vacation time and thus, as to those class members who were terminated and not paid for this time, section 227.3 was violated.
Without regard to whether the LWO was somehow incorporated into plaintiffs’ employment contracts, we agree with plaintiffs’ observation that “the LWO . . . applies of its own force as a governing legal entitlement and therefore allows plaintiff class members to recover their accrued vacation pay.” However, the question here is not whether plaintiffs may recover their accrued vacation pay but whether Cintas may be subjected to Labor Code penalties. The answer turns upon whether Cintas violated section 227.3 when it failed to pay terminated plaintiffs for the additional vacation time they accrued pursuant to the LWO. We think it did.
Section 227.3 merely provides that if an employer promises — by contract or policy — to give its employees paid vacations, the employer must pay an employee wages for all “vested vacation time” he has accrued but not taken at the time of his termination. The statute does not specify the manner in which the employee must have accrued this time. We do not read it to say,
Accordingly, because Cintas does not dispute that plaintiffs’ employment contracts provided for paid vacations, and does not dispute that it failed to pay terminated class members for vacation time they accrued under the LWO, a violation of section 227.3 was established and the $500 penalty was properly imposed.
c. Former Sections 210/225.5: “Initial” Violations
Having found that Cintas violated sections 204 and 223, the trial court assessed penalties under their corresponding penalty statutes, former sections 210 and 225.5 These statutes, which are substantially identical, provide that every person who fails to pay the wages of an employee (pursuant to § 204) or withholds wages due an employee (pursuant to § 223) “shall be subject to a civil penalty as follows: [¶] (a) For any initial violation, [fifty dollars ($50)] for each failure to pay each employee. [¶] (b) For each subsequent violation, or any willful or intentional violation, [one hundred dollars ($100)] for each failure to pay each employee, plus 25 percent of the amount unlawfully withheld.” (Former §§ 210, 225.5.) 23
The parties disagree with each other and with the trial court about the proper interpretation of this language. Plaintiffs contend the provision means a violation occurs every pay period that an employee’s wages are underpaid. The first underpayment of wages constitutes an “initial” violation, but,
The trial court adopted neither party’s position in its entirety. Instead, the court agreed with the interpretation used by the DLSE, as set forth in a February 22, 1984 memorandum. Before PAGA was enacted, the Labor Commissioner had sole authority to enforce former sections 210 and 225.5. In the 1984 memorandum to implement these statutes, of which we take judicial notice, the commissioner advised his staff that an “initial” violation is “[a]ny violation occurring on or after January 1, 1984, regardless of whether penalties were assessed,” whereas a “subsequent” violation is “[a]ny violation which occurs after notice of a previous violation, regardless of whether penalties were assessed.” In describing how an investigating deputy should calculate penalties, the memorandum states: “If the violation is an initial violation, the citing officer will assess a penalty of $50 per each employee per each pay period. [¶] If the violation is a subsequent violation, the citing officer will assess a penalty of $100 per each employee per each pay period.”
The parties cite competing case law, as it suits their purposes, for the deference to be accorded to the DLSE memorandum. The most thorough guidance, however, may be found by the Supreme Court’s explanation in
Yamaha Corp. of America
v.
State Bd. of Equalization
(1998)
Accordingly, we conclude the trial court properly assessed penalties against Cintas under former sections 210 and 225.5 at the rate of $50 per pay period per class member.
2. Trial Court’s Exercise of Discretion for PAGA Penalties
a. Standards Guiding Discretion
Former sections 210 and 225.5 state that “every person who” fails to pay wages (former § 210) or unlawfully withholds wages due (former § 225.5) “shall be subject to a civil penalty” as described in the statute. The
Focusing on the word “shall,” plaintiffs argue the statutes describe mandatory penalties. (See, e.g., § 15 [as used in the Labor Code, “ ‘[sjhall’ is mandatory and ‘may’ is permissive”].) The repeated use of “shall” later in the statutes supports this view: “The penalty shall be recovered by the Labor Commissioner as part of a hearing held to recover unpaid wages and penalties pursuant to this chapter or in an independent civil action. The action shall be brought in the name of the people of the State of California and the Labor Commissioner and the attorneys thereof may proceed and act for and on behalf of the people in bringing these actions. All money recovered therein shall be paid into the State Treasury to the verdict of the General Fund.” (Former §§ 210, 225.5, italics added.) 24 Plaintiffs’ interpretation also finds support in legislative history. The Legislative Counsel’s Digest of Assembly Bill No. 1682 (1983-1984 Reg. Sess.), which gave rise to the version of the statutes that are at issue in this case, explains that prior law “permit[ted] the Labor Commissioner to recover the [$10] penalty as part of a hearing to recover unpaid wages and penalties or in a . . . civil action.” (Legis. Counsel’s Dig., Assem. Bill No. 1682 (1983-1984 Reg. Sess.) 4 Stats. 1983, Summary Dig., p. 389.) In addition to increasing the amount of penalties, the Legislative Counsel stated that the bill “would require, rather than permit, the Labor Commissioner to recover the penalties.” (Id. at p. 390, italics added.)
In contrast, Cintas focuses on the words “subject to” in the phrase “shall be subject to a civil penalty,” arguing these words indicate the commissioner — or the court, in assessing penalties through PAGA — has discretion to choose not to impose any penalty at all. This was the interpretation reached by the Labor Commissioner in the 1984 DLSE memorandum previously discussed. Stressing that violations would only “be subject to” a penalty, the commissioner concluded the amended language permitted the DLSE “to exercise judgment as to whether the penalties should be assessed.” The commissioner then expressed guidelines for his staff in exercising such judgment: “Penalties should not be assessed when there is evidence of a good faith dispute, when the wages are paid as the result of a voluntary settlement conference, or if there is other substantial evidence of an absence of intentional violation.”
Based on dictionary definitions of the phrase “subject to” and DLSE’s interpretation, Cintas argues the trial court had discretion to award
no
In any event, we think plaintiffs have the better of the argument concerning the mandatory nature of the penalties. This construction is most consistent with the statutory language and the legislative history. The DLSE memorandum’s opinion that penalties should not be assessed “when there is evidence of a good faith dispute” has no basis in the statutes, legislative history or case law. Moreover, as the trial court pointed out, this interpretation conflates the standards for a “willful” violation with the statutes’ directive that a penalty be imposed for nonwillful initial or subsequent violations. By refusing to assess penalties for any violation that occurred in the context of a good faith dispute, the DLSE’s interpretation renders nugatory the statutory directive that an initial, nonwillful violation “shall be subject to a civil penalty.” (Former §§ 210, 225.5.) Where an agency’s interpretation contradicts or alters the terms of a statute, it is entitled to no deference.
(Traverso
v.
People ex rel. Dept. of Transportation
(1996)
This leads us to a related argument advanced by Cintas. Cintas objects to penalties that could be recovered only by the Labor Commissioner before PAGA was enacted. In describing the trial court’s discretion to assess penalties made available by PAGA, section 2699, subdivision (e)(1) states: “For purposes of this part, whenever the Labor and Workforce Development
First, “authorized” does not mean “required.” That a court has authority to exercise discretion in the same manner as the DLSE does not necessarily mean it is required to do so. Without further support for this interpretation— and none has been offered — we are disinclined to believe the Legislature intended to so circumscribe the court’s discretion. Second, as we have explained, the DLSE’s policy of forgiving penalties when the employer has a good faith defense is entitled to no deference because it contradicts the express language of former sections 210 and 225.5. Third, Cintas’s argument contravenes Supreme Court authority holding that DLSE internal policies interpreting statutes are not entitled to judicial deference because they were not promulgated in accordance with the Administrative Procedures Act (APA).
(Tidewater Marine Western, Inc. v. Bradshaw
(1996)
b. Amount of Award
Section 2699, subdivision (e)(2) provides that in an action by an aggrieved employee to recover PAGA penalties, the court “may award a lesser amount than the maximum civil penalty amount specified by this part if, based on the facts and circumstances of the particular case, to do otherwise would result in an award that is unjust, arbitrary and oppressive, or confiscatory.” The trial court declined to do so in this case, stating: “Taking into account the facts in this matter, and the purposes of the penalty provisions at issue, the Court does not find reason to exercise its discretion to reduce the amount of penalties.” Cintas argues the court committed legal error by considering the purpose of the statutes and abused its discretion by “imposing penalties that are unjust, arbitrary and oppressive and confiscatory” in amount.
No authority brought to our attention supports Cintas’s claim of legal error. Cintas argues that a trial court imposing PAGA penalties can exercise its discretion based
only
on the considerations mentioned in section 2699, subdivision (e)(2). This argument rests on a misunderstanding of the nature of PAGA penalties: As we have explained, they are mandatory, not discretionary. Accordingly, section 2699, subdivision (e)(2) describes the conditions under which a trial court may exercise its discretion to
reduce
penalties. It does not specify guidelines for exercising discretion in general with regard to the amount of penalties, because the amount is fixed by statute. Cintas correctly points out that judicial discretion must be exercised within the confines of the statute that grants the discretion
(Horsford
v.
Board of Trustees of California State University
(2005)
Finally, the $258,900 penalty assessment is not confiscatory. The court received evidence that Cintas’s parent company had $2.81 billion in sales and $272 million in profits during fiscal year 2004. The penalty award is certainly not “astronomical” in comparison. (See, e.g.,
City and County of San Francisco
v.
Sainez
(2000)
In sum, the trial court did not abuse its discretion in declining to reduce the PAGA penalties pursuant to section 2699, subdivision (e)(2).
Cintas argues the trial court erred in awarding prejudgment interest of 10 percent on plaintiffs’ successful claim for restitution under the unfair competition law (Bus. & Prof. Code, § 17203 (UCL)). The court awarded prejudgment interest pursuant to Civil Code section 3287, subdivision (a), which provides for interest on an award of “damages certain, or capable of being made certain by calculation.” Cintas claims this ruling was erroneous because recovery for unpaid wages under the UCL is considered restitution, not damages. (Cortez v. Purolator Air Filtration Products Co., supra, 23 Cal.4th at pp. 177-178.)
We need not reach this issue because our decision can have no practical effect on the judgment. The trial court awarded precisely the same prejudgment interest ($372,546 plus $216.57 per day from April 29, 2006, through entry of judgment) on both the breach of contract claim and the UCL claim. The judgment specifically states that the prejudgment interest award for the UCL claim is “included in, and not in addition to, the prejudgment interest awarded on the Fifth Cause of Action” for breach of contract. Cintas challenged plaintiffs’ right to recover on their contract claim, but it did not dispute the award of prejudgment interest on the contract claim. Accordingly, because we are affirming the judgment in plaintiffs’ favor on the breach of contract claim, Cintas is now obligated to pay prejudgment interest on the contract damages. Cintas will not be required to pay any additional amount for prejudgment interest on plaintiffs’ UCL claim because the judgment directs that this award is subsumed in the award of interest on the contract claim.
“ ‘It is this court’s duty “ ‘to decide actual controversies by a judgment which can be carried into effect, and not to give opinions upon moot questions or abstract propositions, or to declare principles or rules of law which cannot affect the matter in issue in the case before it. . . .’ ” [Citations.]’ [Citations.] ‘ “When no effective relief can be granted, an appeal is moot and will be dismissed.” [Citations.]’ [Citation.]”
(Vernon v. State of California
(2004)
Both sides have appealed from the trial court’s postjudgment orders awarding attorney fees and costs. Cintas complains the court used an excessive multiplier in calculating attorney fees, and plaintiffs complain the court erred in refusing to allow recovery for certain litigation costs. We reject both arguments.
A. Attorney Fee Multiplier
In calculating the attorney fees to be awarded to plaintiff class, the trial court reviewed detailed billing records and arrived at a “lodestar” figure of $727,000, representing the total attorney hours expended multiplied by a reasonable hourly rate. Cintas has not disputed this amount.
A trial court has discretion to adjust the lodestar amount to take account of unique circumstances in the case.
(Ketchum
v.
Moses
(2001)
Plaintiffs’ motion for attorney fees asked the court to apply a multiplier of 2.0 based primarily on the novelty and difficulty of the issues presented and the successful results counsel achieved for the class, without the time and expense of a trial, on nearly every one of these issues. The trial court agreed with this assessment, though it determined a smaller multiplier of 1.65 was appropriate. The court explained its reasoning as follows: “The instant case presented a number [of] important issues of Constitutional interpretation, as well as interpretation of the Labor Code Private Attorney[s] General Act (Labor Code, § 2699 et seq.), and the Hayward Living Wage Ordinance itself.
We review an award of attorney fees for abuse of discretion.
(Serrano v. Priest, supra,
Cintas complains the court improperly based the multiplier on “contingent risk” without evidence of “comparative billing data (such as hours billed annually by the firm or amount of income deferred)” or without evidence that plaintiffs’ attorneys “sacrificed opportunities for other work” to represent the class. However, Cintas takes an unduly narrow view of the concept of “contingent risk.” It is not simply that counsel turned away paid work for a time in order to represent the class, but that counsel risked never receiving compensation
at all.
The claims and defenses in this case raised a significant number of complex legal issues of first impression, and class counsel took a substantial risk that it would not prevail on these issues and thus would not recover a full fee. (See
Horsford v. Board of Trustees of California State University, supra,
B. Cost Award
Plaintiffs were awarded all of the costs ($8,174.44) set forth in their memorandum of costs. In addition to these statutory costs, however, plaintiffs sought an award of $65,641.28 for litigation expenses not otherwise available under Code of Civil Procedure section 1033.5. This figure included over $40,000 in expert witness fees. Plaintiffs argued they were entitled to recover such expenses under
Beasley
v.
Wells Fargo Bank
(1991)
In a cross-appeal from the cost award, plaintiffs renew their arguments, again relying solely on the
Beasley v. Wells Fargo Bank
case. However, this holding from
Beasley
was expressly disapproved by the Supreme Court in the recent decision
Olson v. Automobile Club of Southern California
(2008)
The judgment and postjudgment orders on appeal are affirmed in their entirety. Plaintiffs shall recover their costs on appeal.
A petition for a rehearing was denied July 2, 2008, and the petition of defendants and appellants for review by the Supreme Court was denied September 10, 2008, S165293.
Notes
Cintas is used as a collective reference to defendants, Cintas Corporation No. 2 and Cintas Corporation No. 3.
These hourly rates would be adjusted annually to reflect changes in the Bay Area Consumer Price Index. (Hayward Mun. Code, § 2-14.020, subd. (c).)
Amici curiae League of California Cities and California State Association of Counties request that we take judicial notice of the provisions of nine different living wage ordinances adopted by other California cities and counties. Because the terms of other local laws are not relevant to the issues on appeal, the request is denied.
This time the certification was made by the service manager of Cintas’s San Leandro facility. Cintas closed its Union City facility in January 2000; thereafter, the City’s contract was serviced out of San Leandro.
The record includes copies of three of these purchase orders, for the fiscal years 1999-2000, 2000-2001 and 2002-2003. Although the purchase order covering the period from
The court later corrected the judgment, nunc pro tunc, to place it in the form required by the parties’ stipulation.
As a charter city, the City also has the constitutional authority to regulate matters that are deemed municipal affairs despite the existence of state laws governing the same subject matter.
(First Street Plaza Partners
v.
City of Los Angeles, supra,
65 Cal.App.4th at pp. 660-661; see also
Baron v. City of Los Angeles
(1970)
In
S.D. Myers
v.
City and County of San Francisco
(9th Cir. 2001)
Although Cintas complains the City Council did not compile evidence to support this finding, “a legislative choice . . . may be based on rational speculation unsupported by evidence or empirical data.”
(FCC
v.
Beach Communications, Inc.
(1993)
Enforcement measures for the LWO include a private right of action for aggrieved employees and penalties under Government Code section 36900; however, the ordinance specifically states that a violation may not be prosecuted as a misdemeanor. (Hayward Mun. Code, § 2-14.040, subd. (e).)
Although Cintas argued below that it was not a service contractor because it did not provide laundry services, or because the LWO’s definition of “laundry services” was unconstitutionally vague, it appears to have conceded this point on appeal.
Although Cintas claims this point was made in opposition to plaintiffs’ motion fq! summary judgment, the argument it directs us to concerns only whether Cintas provides “laundry services” to the City. Cintas did not attempt to distinguish plaintiffs’ service to Cinta] from service on or under the contracts with the City. b
The ordinance contemplates the future development of such requirements, however. One provision gives the city manager authority to “monitor compliance, which may include ... the periodic review of appropriate records maintained by service contractors to verify compliance . . . .” (Hayward Mun. Code, § 2-14.050, subd. (a).)
Tippett
v.
Terich, supra,
Cintas misconstrues our holding in
Fidelity Roof.
Our discussion of employees’ contractual rights was not premised on the absence of a private right of action for employees to enforce the prevailing wage law.
(Fidelity Roof, supra,
60 Cal.App.4th at pp. 425-426.) As another court has pointed out, these are two separate inquiries: “[T]he right to recover prevailing wages under the statutory scheme is separate from the right to recover under the public works contract. At the risk of stating the obvious, the right to recover under the statute arises from the statutory scheme [citations], while the right to recover on a contract theory arises from the common law right to sue for breach of the express terms of the contract as a third party beneficiary of the public works contract. [Citations.]”
(Road Sprinkler Fitters Local Union No. 669
v.
G & G Fire Sprinklers, Inc.
(2002)
Unless otherwise specified, all further statutory references are to the Labor Code.
At Cintas’s request, we take judicial notice of legislative history materials surrounding the enactment of Senate Bill No. 796 (2003-2004 Reg. Sess.) and its later amendments.
Specifically, the court observed section 227.3 (requiring payment of vested vacation wages upon termination) carried no civil penalty before the passage of PAGA. Because the penalty for this violation was new, the court concluded its application with respect to class members terminated before PAGA went into effect would impermissibly increase Cintas’s liability for past conduct. Violations occurring after PAGA’s effective date did not pose a retroactivity problem, however. Therefore, the section 227.3 penalty claims of class members who were terminated after January 1, 2004, remained viable. Neither side appears to contest this aspect of the court’s ruling (i.e., with respect to penalties available under § 227.3).
Although PAGA also increased the penalties available for some violations, plaintiffs did not seek these higher rates.
In
RUI One Corp. v. City of Berkeley
(9th Cir. 2004)
Plaintiffs rely on cases from other contexts to argue that gross negligence or recklessness may constitute willfulness. (See, e.g.,
Safeco Ins. Co. of America v. Burr
(2007)
Although section 227.3 itself does not provide for penalties, plaintiffs sought to recover them under the provision of PAGA that makes penalties available where they are not otherwise provided. (§ 2699, subd. (f).) Because the penalty did not exist before the enactment of PAGA, its imposition would have been impermissibly retroactive if based on violations of section 227.3 that occurred before January 1, 2004. (See
Myers
v.
Philip Morris Companies, Inc., supra,
Penalties are set at $100 for initial violations and $200 for subsequent, willful or intentional violations under the current versions of sections 210 and 225.5; however, plaintiffs sought only the penalties at the lower level that applied before these statutes were amended. Accordingly, all references to sections 210 and 225.5 in our discussion are to the former versions of these statutes before they were amended in 2003. (See Stats. 1983, ch. 1096, §§ 1, 2, p. 4106.)
Current versions of the statutes provide for a slightly different allocation of the money recovered in penalties, but they continue to use the word “shall” in directing where funds are to be paid.
Cintas counters that an initial violation “has meaning” even if no penalties are assessed because, after an initial violation, later violations will be considered “subsequent” and penalized at a higher rate. This observation (which is based on analysis set forth elsewhere in the same DLSE memorandum) is beside the point. The statutes direct penalties to be imposed for all violations, but DLSE’s enforcement policy excuses penalties when the employer’s conduct is not willful.
Cintas also asserts, without argument or citation to authority, that the imposition of penalties violates equal protection and the constitutional prohibition on ex post facto laws. These belated throwaway arguments have been waived.
(San Mateo County Coastal Landowners’ Assn. v. County of San Mateo, supra,
The court’s order did award plaintiffs an additional $498 in transcript and translation expenses, which it found reasonable under Code of Civil Procedure section 1033.5, subdivision (c)(4). Cintas does not dispute this award. All other litigation expenses were denied.
