ALUMINUM COMPANY OF AMERICA ET AL. v. CENTRAL LINCOLN PEOPLES’ UTILITY DISTRICT ET AL.
No. 82-1071
Supreme Court of the United States
Argued January 9, 1984—Decided June 5, 1984
467 U.S. 380
Jerrold J. Ganzfried argued the cause for the federal respondents under this Court‘s Rule 19.6, urging reversal. With him on the briefs were Solicitor General Lee, Assistant Attorney General McGrath, Deputy Solicitor General Claiborne, and Bruce G. Forrest.
Jay T. Waldron argued the cause for respondents Central Lincoln Peoples’ Utility District et al. With him on the brief was Donald A. Haagensen. James W. Durham, Alvin Alexanderson, and Robert T. O‘Leary filed a brief for respondents Portland General Electric Co. et al. Robert M. Greening, Jr., filed a brief for respondent Public Power Council.*
JUSTICE BLACKMUN delivered the opinion of the Court.
Since enactment of the Bonneville Project Act of 1937, 50 Stat. 731,
I
Before discussing the Regional Act‘s provisions that give rise to the dispute, certain aspects of hydroelectric power generation and the Project Act‘s allocation scheme must be explained.
Because the amount of power generated by BPA depends on streamflow in the Columbia River system, BPA cannot predict with accuracy the amount of power that it can generate. Accordingly, BPA historically has sold two types of power. “Firm power” is energy that BPA expects to produce under predictable streamflow conditions. “Nonfirm” power is energy in excess of firm power, and is provided only when such excess exists.
In the early years of the Project Act, BPA‘s contract with each of its customers obligated BPA to supply the customer‘s full contractual requirements on a “firm,” noninterruptible basis. In 1948, the increasing demand for power in the Northwest caused BPA to modify its industrial sales policy so as to require that, where feasible, a new contract signed with a DSI provide that some power be supplied on a nonfirm basis. This condition meant that a portion of DSI power could be interrupted when necessary to supply BPA‘s prefer-
The increased demand for power in the 1970‘s required that BPA alter its sales policies even more drastically. Projections at that time showed that because of increased power demand, preference customers soon would require all of BPA‘s power. See H. R. Rep. No. 96-976, pt. 1, pp. 23-27 (1980). Accordingly, BPA announced in 1973 that new contracts for firm power sales to IOUs would not be offered. In addition, when BPA signed contracts with DSIs in 1975, it specified that 25% of their power would be subject to interruption “at any time,” and it advised the DSIs that as their new contracts expired during the 1981-1991 period, they were not likely to be renewed.
The increase in demand soon threatened even the ability of BPA‘s preference customers to obtain federal power to meet their full power needs. In 1976, BPA informed its preference customers that BPA would not be able to satisfy preference customer load growth after July 1, 1983, and BPA began to consider how to divide the available federal power among its preference customers.
The high cost of alternative sources of power caused BPA‘s nonpreference customers vigorously to pursue ways to regain access to cheap federal power. Most important, many areas that were served by IOUs moved to establish public entities designed to qualify as preference customers and be eligible for administrative allocations of power.4 Because the
To avoid the prospect of unproductive and endless litigation, Congress enacted the Regional Act. The Act provided for future cooperation in the region by establishing a mechanism for comprehensive federal/state power planning. §§4 and 6,
Section 5(d)(1)(B) of the Act,
Pursuant to this statutory directive, the Administrator offered new, 20-year contracts to its DSI customers. The contracts were for the same amount of power specified by the existing 1975 contracts. Based upon his interpretation of the statute and the legislative history of the Act, however, the Administrator concluded that the terms of the power sales were not to be the same as they had been under the 1975 contracts. The 1975 contracts provided that a portion (the “top quartile“) of the power supplied to DSIs could be interrupted “at any time.” This provision made the top quartile of DSI power subject to the preference provisions of the Project Act, and enabled preference utilities to interrupt it whenever they wanted nonfirm power. The Administrator concluded that such a provision in the new contracts would conflict with §5(d)(1)(A)‘s directive that sales to DSIs should “provide a portion of the Administrator‘s reserves for firm power loads” (emphasis added). Accordingly, the Administrator offered DSI customers contracts that allowed interruption only to protect BPA‘s firm loads, and not to make sales of nonfirm energy. 46 Fed. Reg. 44340 (1981).
This aspect of the new DSI contracts is at the center of the present dispute. Under the Project Act, nonfirm power was allocated hourly on an “if available basis,” and was subject to the preference provisions of that Act. Although nonfirm power is too unreliable for preference utilities to use to satisfy the demands of their consumers on a general basis, it nevertheless is attractive to many preference utilities be-
Shortly after the Administrator‘s decision and the execution of new DSI agreements, respondents challenged the contracts by petition for review in the Court of Appeals. The core of their challenge was that the proposed contracts violated the preference to nonfirm power accorded under the 1975 contracts. That preference, it was said, was reserved by §5(a) of the Regional Act,
The Court of Appeals agreed with respondents and found the Administrator‘s interpretation of the Act to be unreasonable. Central Lincoln Peoples’ Utility District v. Johnson, 686 F. 2d 708 (CA9 1982). The court relied heavily on §§ 5(a) and 10(c) of the Regional Act to conclude that the Act preserved the longstanding practice of allocating nonfirm power under the 1975 contracts. Because of the importance of the issue, we granted certiorari. 460 U. S. 1050 (1983).
II
A
Under established administrative law principles, it is clear that the Administrator‘s interpretation of the Regional Act is to be given great weight. “We have often noted that the interpretation of an agency charged with the administration of a statute is entitled to substantial deference.” Blum v. Bacon, 457 U. S. 132, 141 (1982). “To uphold [the agency‘s interpretation] ‘we need not find that [its] construction is the only reasonable one, or even that it is the result we would have reached had the question arisen in the first instance in judicial proceedings.’ . . . We need only conclude that it is a reasonable interpretation of the relevant provisions.” American Paper Institute, Inc. v. American Electric Power Service Corp., 461 U. S. 402, 422-423 (1983), quoting Unemployment Compensation Comm‘n v. Aragon, 329 U. S. 143, 153 (1946).
Giving the Administrator‘s interpretation the deference that it is due, we are convinced that his interpretation is a fully reasonable one. Section 5(d)(1)(B) of the Regional Act,
First, respondents claim that the new contracts violate the statutory directive that the contracts be for the same “amount of power” as the 1975 contracts. Because the proposed contracts curtail the situations in which power can be interrupted, respondents argue that they effectively provide DSIs with a greater amount of power than they would have received under the 1975 contracts. Petitioners and the Administrator contend, on the other hand, that the term “amount of power” refers only to the quantity of power to be sold to the DSIs as measured in kilowatts. They claim that the phrase does not determine the interruptibility or “quality” of the power that is sold under the required contracts.
Sections 5(d)(1)(A) and 3(17) of the Regional Act lend support to this interpretation. The former expressly requires that power sales to the DSIs “shall provide a portion of the Administrator‘s reserves for firm power loads.” The latter defines reserves as the power needed to protect BPA‘s “firm power customers” from shortages. It is clear from these provisions that at least some portion of DSI power is interruptible to protect the firm needs of other customers. In addition, however, these provisions support the Administrator‘s inference that the Regional Act does not require DSI power to be interruptible to meet the nonfirm power desires of preference customers, and the legislative history confirms this view. The Report of the Senate Committee on Energy and Natural Resources clearly explains: “[T]he term ‘firm power customers of the Administrator’ is intended to mean the firm power loads of such customers. It is not intended that the Administrator‘s reserves will be used to protect other than firm loads” (emphasis supplied). S. Rep. No. 96-272, p. 23 (1979). Because it is clear that the top quartile of DSI power is a part of BPA‘s reserves, that power is not to be used to serve nonfirm power loads.
Respondents’ claim that the top quartile of power must be interruptible “at any time” in order to provide the DSIs with the same “amount of power” is incorrect even under respond-
The dissent apparently concedes that the second quartile interruptibility provisions of the new contracts differ from those in the 1975 contracts, post, at 403-405, and the dissent is presumably aware of the legislative history specifically endorsing the new provisions. Thus, the dissent acknowledges that its interpretation of the phrase “same amount of power” leads to an inconsistency, but claims that Congress was not ”aware that it was altering the interruptibility provisions” (emphasis supplied), apparently assuming that Congress simply forgot what was in the 1975 contracts. It seems improvident to assume such ignorance on the part of Congress, not to mention the Administrator of BPA, when Congress clearly had to focus on the terms of the 1975 contracts in drafting several aspects of the statute.
Respondents’ second argument is that the terms of the new contracts conflict with §5(a) of the Regional Act. It is true, as respondents assert, that that section preserves the priority and preference provisions that existed under the Project Act. But the preference system merely determines the priority of different customers when the Administrator receives “conflicting or competing” applications for power that the Administrator is authorized to allocate administratively. §4(b) of the Project Act,
It appears, therefore, that respondents’ view of the Regional Act would render meaningless the initial contracts contemplated by §5(d)(1)(B). Respondents’ argument is essentially that the allocation of power under the mandated contracts should be the same as it would be if the preference rules applied. But Congress presumably included §5(d)(1)(B) precisely because it wanted to achieve an allocation of power that differs from what allocation by preference
The Administrator‘s interpretation of the Regional Act also is supported by §5(g)(7) of that Act,
B
The legislative history of the Regional Act confirms the interpretation put forward by BPA and petitioners. That history shows that Congress paid specific attention to power sales to DSIs, and consulted BPA on the relationship between those sales and the broader purposes of the Act. The record gives no indication that Congress intended the new DSI contracts to have provisions governing interruptibility that were the same as in the 1975 contracts.
The Committee Reports of both Houses made particular reference to the DSI contracts and the manner in which those sales would provide the reserves for the Administrator‘s other obligations. The Senate Report contains the following explanation of the section dealing with DSI sales.
“The power quality provided the direct-service industries is determined by the reserve obligations set forth in their contracts in order to protect service to firm loads of the Administrator. It is intended that these contracts at least provide peaking power reserves similar to those provided in the present contracts, and that the energy reserves shall include a reserve approximately equal to 25 percent of the direct service industrial load to protect firm loads for any reason, including low or critical streamflow conditions . . .” (emphasis supplied). S. Rep. No. 96-272, p. 28 (1979).
This passage flatly contradicts respondents’ argument. The first sentence makes clear that the “quality” of the power provided to the DSIs is determined by the need to provide reserves to protect “the firm loads of the Administrator.” The sentence is noticeably devoid of any suggestion that the quality of power is to be the same as it was under the 1975 contracts. The rest of the passage reinforces the view that the purpose of the interruptibility provisions is “to protect firm loads.”
“Approximately 25 percent of the DSI load is to be treated as a firm load for purposes of resource operation and will provide an operating reserve that may be restricted by the BPA at any time in order to protect the Administrator‘s firm loads within the region and for any reason, including low or critical streamflow conditions and unanticipated growth of regional firm loads.” H. R. Rep. No. 96-976, pt. 2, p. 48 (1980).
This passage confirms that DSI sales were to be interruptible “to protect the Administrator‘s firm loads.” Such a requirement would have little meaning if, as respondents would have it, the statute also requires DSI power to be interruptible at any time for any reason.
The source of this language in the House Report is significant. While the bill was still under consideration, BPA conferred with the Committee‘s staff and furnished the Committee with its understanding of how sales to DSIs would operate. The passage from the Report quoted above is an almost verbatim incorporation of BPA‘s understanding of the provision. See Appendix III to Letter dated Aug. 19, 1980, from BPA Administrator to Rep. Kazen, Chairman, House Subcommittee on Water and Power Resources, App. to Pet. for Cert. I-23 (discussing the DSI service under the Regional Act). The legislative history therefore indicates that BPA consulted with Congress during the consideration of the Regional Act, and that BPA and Congress shared an understanding of the terms on which the Administrator would sell power to DSIs under the Act.
Respondents rely on the legislative history to establish two points, neither of which is controverted. First, respondents use the legislative history to demonstrate what §5(a) already makes clear—that the Regional Act does not alter the priority provisions of the Project Act. See Brief for Respondents
Respondents’ second use of the legislative history is to show that, under the 1975 contracts, the top quartile of DSI was subject to preference because it was interruptible “at any time.” Id., at 21-23. This point also is uncontroverted. The issue in this case, however, is whether the new contracts mandated by the Regional Act must provide that a portion of DSI power be subject to interruption “at any time.” If so, there is no dispute over whether preference would apply to that power. But respondents have not pointed to anything in the Regional Act that requires that the interruptibility terms of the 1975 contracts be incorporated into the new contracts.
C
Because the Regional Act does not comprehensively establish the terms on which power is to be supplied to DSIs under the new contracts, it is our view that the Administrator has broad discretion to negotiate them. Such discretion is especially appropriate in this situation, because DSI sales are merely one part of a complicated statutory allocation plan designed to achieve several goals. Most important, sales to DSIs under the Regional Act are intricately related to the “exchange” program established by the Regional Act on behalf of nonpreference utilities. §5(c),
The exchange program is designed to provide rate relief for consumers served by IOUs. As noted supra, the operation of preference under the Project Act produced an allocation of cheap federal power that heavily favored public
Because this exchange program essentially requires BPA to trade its cheap power for more expensive power, it is obviously a money-losing program for BPA. The Act expressly contemplates that much of the cost of this program is to be covered by power sales to DSIs, which pay a considerably higher price for power than other users. Section 7(c)(1),
“[The DSIs] will also pay significantly higher rates under the new contracts. These higher rates permit the Administrator to enter into contracts with the region‘s investor-owned utilities for an exchange of power equal to the utilities’ residential load. This exchange will permit residential customers of investor-owned utilities to share in the benefits of the lower-cost Federal resources. The power sold to BPA will be sold at the utilities’ average system cost and purchased back at the rate paid by the preference customers’ utilization [sic] their general requirements. The loss in revenue to the Administrator is in effect returned by the higher direct service industry rates. By providing these residential customers whole-
sale rate parity with residential customers of preference utilities, the amendment serves in a substantial way to cure a major part of the allocation problem.” H. R. Rep. No. 96-976, pt. 1, p. 29 (1980).
This passage makes clear that the DSI sales and the power exchange program are integrally related. BPA‘s ability to finance the exchange program is related to the amount of power that BPAs sell to DSIs, which in turn is determined by the interruptibility terms of the new DSI contracts. It is the responsibility of the Administrator to manage the complex relationship among these various aspects of the statute, and, absent an express statutory statement requiring particular terms in the contracts, it is appropriate that we give him broad discretion to determine them.11
III
For the foregoing reasons, the judgment of the Court of Appeals is reversed, and the case is remanded for further proceedings consistent with this opinion.12
It is so ordered.
JUSTICE STEVENS, dissenting.
Section 5(d)(1)(B) of the Pacific Northwest Electric Power Planning and Conservation Act of 1980, 94 Stat. 2697, provides:
“[T]he Administrator shall offer in accordance with subsection (g) of this section to each existing direct service
industrial customer an initial long term contract that provides such customer an amount of power equivalent to that to which such customer is entitled under its contract dated January or April 1975 providing for the sale of ‘industrial firm power.‘”
16 U. S. C. § 839c(d)(1)(B) .
The critical question in this case is whether the contracts offered by the Administrator of the Bonneville Power Administration (BPA) pursuant to the 1980 Act are for “an amount of power equivalent to” the amount to which the direct service industrial customers (DSIs) were entitled under their 1975 contracts.
Under the 1975 contracts, 75 percent of the specified amount of power was virtually guaranteed; the “top quartile,” however, was subject to interruption at any time to meet the demands of preference customers. Thus, the actual amount of power delivered under the 1975 contracts was an amount somewhere between 75 percent and 100 percent of the amount stated in the contracts.1
Under the 1980 contracts, 100 percent of the specified amounts is virtually guaranteed. No longer is the first quartile subject to interruption at any time. The result of changing the “quality” of first quartile power is to provide the DSIs with a larger amount of power than they would have received under the 1975 contracts. That is plainly inconsistent with §5(d)(1)(B), which indicates that the DSIs’
“contracts will provide power in amounts equal to, but not greater than, that which these companies are now entitled under existing contracts with BPA, and the terms of these contracts will require that these compa-
nies continue to supply reserves for the region.” H. R. Rep. No. 96-976, pt. 2, p. 29 (1980) (emphasis supplied).2
Thus, the new contracts do not comply with the plain language of the 1980 Act.3
“The power quality provided the direct-service industries is determined by the reserve obligations set forth in their contracts in order to protect service to firm loads of the Administrator. It is intended that these contracts at least provide peaking power reserves similar to those provided in the present contracts, and that the energy reserves shall include a reserve approximately equal to 25 percent of the direct service industrial load to protect firm loads for any reason, including low or critical streamflow conditions, and an additional energy reserve of approxiamtely [sic] the same amount to protect firm loads against the delayed completition [sic] or unexpectedly poor performance of reginal [sic] generating resources or conservation measures, and against the unanticipated growth of regional firm loads. One intended result of these procedures is that there will be no increase in firm power commitments to the direct service industrial customs [sic], except for technological improvements purposes.” S. Rep. No. 96-272, p. 28 (1980).
When read in light of its last sentence, this paragraph makes it clear that Congress intended that DSIs have no greater assurance against interruption than they did under their 1975 contracts. Moreover, in a rate analysis submitted to Congress by the BPA, it estimated its projected revenues under the proposed legislation by assuming that it would continue to interrupt the top quartile of DSIs’ power at the same rate that it had done so in the past, n. 1, supra, supplying from 86 to 96 percent of the DSIs’ loads, and also anticipated interruptions in the top quartile in excess of those necessary to protect firm loads. See S. Rep. No. 96-272, at 59.
In the 1981 contracts the DSIs agreed that the second quartile of power would be subject to interruption on two contingencies that were not applicable to the second quartile
the outset is whether the Court of Appeals correctly construed the Act.” FEC v. Democratic Senatorial Campaign Comm., 454 U. S. 27, 31-32 (1981) (citations omitted).
It is also worth noting that the Adminstrator‘s interpretation of this Act has not been a model of consistency. In the BPA‘s final Environmental Impact Statement, issued in December 1980, it stated that top quartile DSI power can be interrupted “[a]t any time for any period for any reason.” App. 31. Similarly, in its summary of its original draft contracts under the 1980 Act, it stated: “BPA may interrupt a portion of the DSI load, not to exceed 25 percent of the Operating Demand plus the Auxiliary Power, at any time, for any reason, and for any duration.” Id., at 74. See also n. 2, supra. In light of the lack of clarity that has characterized BPA‘s position both before and after the passage of the 1980 Act, its position surely is not entitled to so much deference as to override the plain import of the words Congress enacted. See General Electric Co. v. Gilbert, 429 U. S. 125, 143 (1976).
Moreover, it is questionable whether the second quartile interruptibility provisions of the 1980 Act constitute a real difference from the interruptibility provisions of the 1975 contracts with respect to that quartile. As the majority explains, ante, at 392, n. 8, the 1980 Act anticipated interruption of the second quartile only because of delayed completion or unexpectedly poor performance of generating resources or conservation measures. Prior to the 1980 Act, BPA had no authority to acquire or expand its resources; its function was merely to market power generated at dams constructed by the Army Corps of Engineers. See ante, at 386, and n. 5. Hence, the 1980 Act permits second quartile interruption only on a basis that would not have arisen under the 1975 contracts.4 Surely this relatively insignificant and some-
The language of §5(d)(1)(A) should be of little comfort to the majority. All it says is:
“The Administrator is authorized to sell in accordance with this subsection electric power to existing direct service industrial customers. Such sales shall provide a portion of the Administrator‘s reserves for firm power loads within the region.”
16 U. S. C. § 839c(d)(1)(A) .5
This subsection makes no reference at all to the “quality” of power to which DSIs are entitled. If this language was designed to entitle DSIs to higher “quality” power than they received under their 1975 contracts, then Congress picked a rather obtuse way of expressing the idea.
I read the subsection to mean what it says. The sales that the Administrator makes to the DSIs are part of the reserve for firm power loads.6 In the event of a shortfall, the Administrator is obligated to use top quartile DSI power to meet his firm power obligations even when there is a prefer-
in the circumstances in which interruption is permitted under the 1980 Act; those circumstances most likely would have given rise to a commercial frustration defense permitting BPA to interrupt second quartile power to the DSIs.
Because I find nothing in the statute or in its legislative history to indicate that Congress intended to allocate a greater amount of power to the DSIs than they were entitled to receive under their 1975 contracts, I cannot square the Court‘s holding with the plain language of the statute. I therefore respectfully dissent.
