62 Ind. App. 219 | Ind. Ct. App. | 1914
Lead Opinion
Fielding A. Conway and others filed their complaint in the court below in behalf of themselves and a large number of other land and lot owners, who with said Conway and others are designated in this opinion as plaintiffs, ashing as relief that the acceptance of the Pleasant Run interceptor sewer by the board of public works of the city of Indianapolis, and the primary assessment roll adopted thereon be set aside as fraudulent and void, and that certain defendants be enjoined from collecting any assessments on account of the construction of said sewer, and from taking any further steps in the matter of said improvement.
Stated generally, the basis of grievance, as set out in the complaint, is to the effect that, while the specifications required that a large portion of said sewer be constructed of monolithic concrete eight inches in thickness, most of such portion, as actually constructed, consists of reinforced concrete pipes in sections of three feet in length and about three and one-half inches thick; and that said sewer was defectively constructed, and that material of poor grade was used.
The board of public works of said city, the treasurer of Marion county, as eoo officio treasurer of said city, the city comptroller and Morris M. Defrees, as contractor, were made defendants. Said Defrees having assigned his interest in said assessment roll to August M. Kuhn, and having thereafter died, his administrator, Hugh J. Defrees, and said assignee are made appellees in this court.
Morris M. Defrees’ demurrer to the complaint for insufficiency of facts was overruled, and exception reserved. Each defendant filed a general denial. Said defendant contractor filed also a special answer in three paragraphs, Nos. 2, 3 and
The court, at the request of the parties, found the facts specially, and stated conclusions of law thereon. Except as stated in other connections, the material part of the finding of facts is in substance as follows: On June 22, 1906, the board of public works of the city of Indianapolis adopted a resolution under the provisions of the act of 1905 for the construction of the Pleasant Run interceptor sewer, to begin on the east bank of White river at a designated point, and thence in a northeasterly direction, approximately a distance of 20,665 feet to the center of Keystone avenue.
This suit was instituted October 2, 1909, by and in behalf of plaintiffs, all of whom the court finds had learned by rumor or otherwise, at or prior to the time of signing said remonstrances, that the sewer was not being constructed according to contract. The court then sets out the names of said persons, the description of their said real estate and respective amounts -of their assessments, and the length of time prior to the signing of the remonstrance that they knew by rumor or otherwise that said sewer was being constructed of reinforced concrete pipes rather than of monolithic concrete.
The decree follows the conclusions of law. Each appellant excepted to conclusion No. 10, and has properly assigned error on the same. Said 171 property owners, in whose favor judgment was rendered, and also said board of public works and the officers of said city, who were defendants below, have appeared to this appeal, and as appellees have filed a confession of error, to the effect that the court - erred in the conclusion No. 10 stated on the findings. Said Hugh J. Defrees as such administrator, and said August M. Kuhn, as such assignee, have each assigned cross-errors, challenging the court’s ruling on the demurrer to the complaint, and challenging also the first,
We first determine the sufficiency of the complaint, which question we hold to be -properly presented. Its allegations are in part to the effect that the contractor, after having completed about 4,000 feet of the sewer according to the specifications, used, in constructing the balance of the concrete portion of it, reinforced concrete pipes three and one-half inches thick, instead of following the prescribed plan of continuous monolithic concrete work eight inches thick; that no person in authority consented to such change, and that the engineer in charge, on being solicited by the contractor, refused to consent to such change; that the contractor departed from the specified plan of work, as alleged, over the protest of the property owners, who were . plaintiffs below; that the sand and gravel used in building said pipes contained soil and other foreign substances; and that, in constructing such sewer, the contractor used cracked and broken pipes, and did not properly cement' the joints, and that as a consequence, large quantities of water passed into the sewer from the surrounding earth, and that the noxious substances designed to be carried by the sewer would escape therefrom if it should be used. Facts are alleged to the effect that the city engineer repeatedly assured plaintiffs that the sewer would not be recommended for acceptance, and that plaintiffs, as property owners affected, relied on such assurance, and as a consequence were deceived into a failure to be present and protest when such sewer was recommended for acceptance and actually accepted by the board; that the sewer as constructed by the use of such pipe, cost $10,000 less than would have been its cost if constructed accord
We proceed to consider the conclusions of law. Conclusion No. 1 is to the effect that the action of the board of public works in accepting said sewer was void because the sewer constructed was radically different from that specified. Said conclusion, as we construe it, is based on the fact that the plan of construction was changed, as indicated, rather than on the fact that the sewer was defective by reason of unskillful work and the use of faulty material. Briefly summed up, the facts from which the court drew said conclusion, in addition to those hereinbefore set out, are as follows: At the lower end, 4,210 feet of the sewer was constructed according to the specifications, whereupon water difficulties were encountered to the extent that the contractor was able to make progress for a period of more than twenty days at the rate of less than two and one-half feet per day. The contractor was chargeable with knowledge that he would probably have to contend with water, but the quantity and velocity of such water could not be and was not definitely ascertained by either him or the city engineer until a substantial part of said work had been done as aforesaid. Both the contractor and the subcontractor were reasonably experienced in sewer building, and they believed that it was impracticable and impossible to continue said monolithic, process of construction, whereupon they called the city engineer and his assistant into conference and, after examining into the situation, it was determined by such conference that it was impracticable to continue such process of construction, under the special circumstances pre
Under the finding, the three necessary elements of such a sewer as is contemplated here are capacity, imperviousness to water infiltration and strength. The sewer as constructed has the same capacity as that specified, and the court expressly finds that a sewer built of such reiñforced concrete pipes in a skillful and workmanlike manner would be as impervious to water and as strong as a sewer constructed in accordance with said monolithic process and as specified.
The argument carried out leads to the conclusion ■that if any substantial part of such an improvement should prove to be impossible of performance by reason of unforeseen obstacles encountered in the progress of the work, the board would have no authority to arrange with the contractor for the completion of the contract by the use of some process other than that specified, even though the results from the substitution would be eminently satisfactory. Thus, applying the argument, should the water difficulties be such as to interfere with the construction of but 100 feet or ten feet of the sewer by such monolithic process, the board would not be warranted in authorizing such 100 feet or ten feet to be built by some other process just as good, but would be required to stop the work and adopt new specifications, etc., for such portion of the sewer. It can not be said that the board has authority of a certain nature and scope when the affected part of the sewer is of a certain length and an absence of authority, or authority of a different nature or scope when the affected part is of a different length. Hence, carrying the argument to its legitimate conclusion, although the unforeseen difficulties should interfere with the specified construction of but a comparatively inconsiderable portion of the sewer, the board would be required to readvertise, etc., rather than authorize the completion of the work by some other satisfactory process.' The argument advanced does not appeal to us as sound.
It is evident that the property owners here were in need of a sanitary sewer and desired that it be constructed. Viewed in the light as it then existed, a monolithic sewer commenced could not be
In Meyers v. Wood (1913), 173 Mo. App. 564, 158 S. W. 909, a public improvement contract provided that the sewer contemplated should be built along the center of Main street. While the work was in progress, the contractor encountered extensive deposits of limestone and high pressure water and gas mains. For the work to proceed further along such street would have necessitated blasting to such an extent as to be very expensive, and there would have been danger of bursting said water and gas mains, for the consequent damage to which the contractor would have been required to pay. In consideration of the situation, the city council authorized the contractor to detour the sewer around through an alley a distance of 1,100 feet. In a direct proceeding, brought by the property owners to cancel the tax bill issued on account of said improvement, arguments were advanced in support of the proceeding, substantially the same as here, to the effect that the acceptance of the sewer was void, because the city council exceeded its power in authorizing the change in the route; that there should have been a new ordinance, a readvertisement, and a reletting; that had
“The strongest ease to which appellants have directed our attention is that of City of Maryville ex rel. Bank v. Lippman, 151 Mo. App. 447, 132 S. W. 47, where the tax bills were adjudged invalid. On reading the opinion, however, it will be noted that the size of the brick was materially changed by the amended ordinance, and the iron dowel pins to connect the curbing were permitted to be left out. The opinion discusses the question, cites authorities, and holds that this change could not be made without a readvertisement. We thoroughly approve the doctrine therein announced. In that case it was properly held that the changes which were allowed were material changes, and they differ from the changing of or deviating from a line of sewer in this that the requiring of dowel pins and the specification of the size of the brick are matters that can be definitely determined at the time the ordinance contracting the work is passed, whereas it is impossible for the contractor or the engineer or the city officials to know exactly what substance will be encountered in digging a ditch for a sewer. One is a matter of definite ascertainment and the other largely a matter of estimate only. One is known to the city officials and all contractors and the other not
“Afterall,itmustbeborne in mind that contractors and city authorities are only human; and they should be held to no. higher duty in the use of good sense or good judgment than the ordinary run of men. The opinions holding that a strict compliance with the law is necessary in order to bind the tax-payer on a special tax bill, as we read them, mean a substantial, sensible, businesslike compliance — a prae-tieal rather than a theoretical compliance — and courts should view these relations as practical men rather than as theorists.”
In Stover v. City, supra, the sewer was shortened, laterals added and the grade changed. See, also, Hastings v. Columbus (1885), 42 Ohio St. 585, where, in a street improvement proceeding, the street was widened and a drain added; and Board v. Gibson (1901), 158 Ind. 471, 63 N. E. 982, where, in performing a contract to build a courthouse, the contractor having excavated to the specified depth, came to quicksand rather than solid ground, whereupon the board, without additional specifications or advertising for bids, arranged with the contractor to excavate deeper and to build a subbasement; and Smith v. Board (1893), 6 Ind. App. 153, 33 N. E. 243, where in executing a contract for the building of bridge 'piers unforeseen difficulties were encountered. See also Edwards v. Cooper (1906), 168 Ind. 54, 64, 79 N. E. 1047; Bass Foundry, etc., Works v. Board (1888), 115 Ind. 234, 242, 17 N. E. 593; Board v. Cincinnati, etc., Co. (1891), 128 Ind. 240, 27 N. E. 612, 12 L. R. A. 502; Board v. Newlin (1892), 132 Ind. 27, 31 N. E. 465; Sims v. Hines (1890), 121 Ind. 534, 542, 23 N. E. 515; Board v. Silvers (1864), 22 Ind.
The engineer and contractor, after having examined actual conditions as they then existed, agreed that it was impracticable to continue said monolithic process of construction, and that, should the sewer be so constructed, it would not be serviceable. The board at first passively acquiesced in the conclusion of the engineer and contractor, and later placed the stamp of approval on it by accepting the sewer. There is nothing to indicate that there was any wider departure from the specifications than was honestly believed to be rendered necessary in order that the unforeseen difficulties and obstacles might be met and overcome. Under such cir
We proceed, however, to consider the effect of the finding that said sewer is defective by reason of unskillful work and the use of improper material. The finding in its bearing on this question may be summarized as follows: The specifications provided that all materials should be of the best quality of their respective kinds; that the sewer should be so constructed as to prevent the seepage of surface water through its walls and joints; that sand and gravel used in manufacturing the pipes should be free from loam, earth, and other foreign substance. The further finding is in substance as follows: Said sewer was constructed as a part of the general sanitary sewer system of said city, and to that end a number of laterals were to be connected into it; that thereby noxious and other impure substances from vaults, cesspools, and like sources might be carried off from the entire territory drained. As designed, it had sufficient capacity to do said work, and also to carry an amount of surface water reasonably in excess of the normal and usual amount. Sewers built by either such monolithic or by such reinforced concrete process are in theory supposed to be water tight, but in actual experience it is found to be impossible to make them so, and as a consequence, under ordinary conditions an amount of seepage bearing some relation to the extent of the territory drained is permissible, which in said Pleasant Run sewer would amount to a total depth in the sewer of approximately two and one-half inches. In the construction of such a sewer, it is of the highest
When the contractor reported the sewer as completed, said reinforced concrete portion of it contained a number of leaky joints, and a number of pipes were permitting seepage through the walls and joints thereof, by reason of which the city engineer declined to approve the sewer, and reported to the property owners that he would not approve it unless about 3,000 feet thereof was removed and properly constructed or the joints thereof caulked with lead and unless and until said seepage was reduced to not more than two and one-half inches. , Thereafter the, contractor made an ineffectual effort to stop the openings in the walls and joints of said sewer, but, notwithstanding such effort, water continued to flow in said sewer varying from four inches deep at the upper end to ten inches deep at the lower end of said
In Lux, etc., Stone Co. v. Donaldson, supra, it seems to be held that such an acceptance can be impeached only on account of the fraud of the accepting body in the act of acceptance, and that the prior or contemporaneous fraudulent conduct of others by which such acceptance is induced is not sufficient to that end, the reason assigned being that the complaining parties have a right to present to such accepting body every legal reason why the improvement should not be accepted, including all accusations of fraudulent conduct on the part of the engineer, contractor, etc. At least on first view, a later case (Gorman v. Johnson, supra), seems to be in conflict with Lux, etc., Stone Co. v. Donaldson. In the former it is said: “It has also
In Zorn v. Warren-Scharf Co. (1908), 42 Ind. App. 213, 84 N. E. 509, an explanation of Lux, etc., Stone Co. v. Donaldson, supra, is suggested to the effect that the attack there was collateral. The attack in Gorman v. Johnson, supra, was direct, and such is the nature of the attack here. Perhaps it is well also to call attention to the scope of the hearing afforded by the statute under which Lux, etc., Stone Co. v. Donaldson, supra, was decided, as cited and construed therein. While doubtless, independent of statute, the board would have authority to grant a more comprehensive hearing, the statute involved here, 'and also in Gorman v. Johnson, supra, provides for a hearing at the stage of the proceedings under consideration only on the question of the amounts of the assessments and of special benefits. There is no provision for an appeal, but a landowner feeling aggrieved may obtain a review of his assessment on petition to the circuit court. §8725 Burns 1908, §8725 Burns 1914, Acts 1907 p. 563.
The trial court finds that said sewer can be properly completed by cementing the joints, etc., and that it will then be serviceable. The board
It may be said that the argument supporting our conclusion that on account of said unskillful work, and the use of the improper material, the contract has not been performed, applies with equal or- greater force to the fact that such reinforced concrete pipes were substituted for such monolithic work. Ordinarily this would be true, but the facts found by the court are sufficient to justify said change in the method of construction, especially since the court found in substance that the substituted form of construction is as good as the specified, where the work is properly done.
The tenth conclusion of law is to the effect that Lizzetta Alsmeier and said sixty other appellants are estopped from contesting said assessment roll. Such estoppel is based on facts found by the court respecting each appellant, and deemed by the trial court sufficient to establish that each appellant respectively had knowledge of said change in method of construction, and neglected seasonably to protest against such change. Under our holding that the special existing circumstances justified the use of such reinforced concrete construction, the facts found as constituting such estoppel become unimportant. There is no answer presenting the issue of estoppel as directed against the fact of unskillful work and the use of poor material, resulting in a defective
The facts are fully found by the court, and as a consequence it is not necessary that there be a new trial on reversal. If said acceptance be set aside, an opportunity will thereby be afforded the repre-sentatives of the contractor to complete the sewer as indicated by the finding. Thereafter, in any proceeding to procure the acceptance of the sewer' as completed, the matter of any saving to the contractor, if any, by reason of the cost of said substituted method of construction, as compared with the cost of thespecified construction, under ordinary conditions, can beadjusted. Criswell v. Board,etc., supra.
For error in the first and tenth conclusions of law, and consequent error in the ninth, the cause is reversed, with instructions to restate the conclusions to the effect that, under the circumstances presented by the finding, the board of public works must be held by its subsequent conduct to have ratified the substitution of such reinforced concrete construction for such monolithic construction, and, having so done, it acted within its authority under the special circumstances presented by the finding; that for unskillful work and the use of poor material, resulting in a defective sewer, as shown by the finding, the acceptance of said sewer and the making of said primary assessment roll and all subsequent proceedings thereon should be set aside as against plaintiffs and others for whom this action is brought as aforesaid-, being said Lizzetta Alsmeier and said sixty other appellants and Margaret E. Adams and said 170 other appellees; that the costs should be taxed one-half thereof against said Margaret E. Adams
Rehearing
On Petition for Rehearing.
Margaret E. Adams and the 170 other appellee.property owners, hereinafter designated as appellees, in whose favor judgment was rendered by the trial court, appearing specially to that end, have petitioned for a rehearing and moved for a modification of the mandate entered on this appeal. The basis of the combined petition and motion by which such relief is sought, stated generally, is as follows: That the sole foundation of this appeal as prosecuted by appellants is the alleged error of the trial court in stating its tenth conclusion of law; that appellees filed in this court a confession of error as to said conclusion, whereby this court acquired jurisdiction over the persons of appellees only for the purpose of adjudicating respecting the correctness of such conclusion; that cross-errors were subsequently assigned by appellees Kuhn and Defrees, administrators, hereinafter designated cross-appellants, but that appellees were not served with notice of the same, and they did not appear thereto, and consequently that this court did not acquire jurisdiction over appellees in their relation to such cross-errors. Appellees ask as relief that on a rehearing being granted, the court modify the mandate by striking therefrom all that relates to appellees. In aid of the petition and motion the following facts sustained by the record, except as otherwise indicated by us, are brought to oür attention: The judgment of the trial court consists of three paragraphs or specifications: By the first specification, which is based on the ninth conclusion of law, the city of Indianapolis, its officers .and agents, the contractor, and all persons claiming under or through
Further facts brought to our attention respecting steps taken in 1913 are as follows: On June 11, appellants served appellees with notice of appeal. On June 14, appellants filed the transcript and proofs of notice and assigned error, and at the same time appellees confessed error. As we have said, the sole error assigned by appellants challenged the tenth conclusion of law. The confession of error as filed was several in form, and'was to the effect that each appellee confessed that as far as he was informed or knew, appellants’ assignment of error was true, and that the court did err in said conclusion. Wherefore, each appellee declined to defend this cause on appeal, and asked that no costs be taxed against him. Appellants’ assignment of error is signed by one of the attorneys who afterwards filed briefs in behalf of appellants. The confession of error is signed by other attorneys. On July 22, appellants’ briefs were filed. On September 5, the eross
If there has been such an appearance by appellees, it consists in the nature and contents of the brief filed September 30, 1913, and denominated “Reply Brief of Appellants.” This brief is in reply to the answer brief filed in behalf of the cross-appellants on appellants’ assignment of error, and also in answer to the argument contained in that brief in support of the
The fact of the first result justified counsel as representatives of appellants alone in defending against said assignments, and they could not thereby be held as representing appellees, even though the nature of such defense was such as appellees might well make in their own behalf as against such assignments. But said brief is broader than as indicated. It contains a complete argument in support of the ninth conclusion of law challenged by the fifth assignment of cross-error, and in which appellees alone are interested. Thus, on page 4 of such brief counsel declare their purpose to champion the cause not only of appellants, but also of appellees, using the following language: “Bo far as questions relating to the reversal of the judgment in favor of cross-appellants are concerned, the interests of the 171 appellees who recovered judgment pursuant to the ninth conclusion of law, and the 63 appellants who were denied relief, pursuant to the tenth conclusion of law, are identical, and the argument in favor of appellants on the cross-errors is also in favor of the 171 coparties in the trial court who are appellees here.” Under the head of “Propositions Relied On”, counsel by proposition No. 8 on page 7 declare their purpose to uphold the ninth conclusion of law by upholding the first conclusion. As stated, peti
The brief being on the merits of the cause, and filed pursuant to such presumed authority, constituted an appearance. It follows that the petition for a rehearing should be denied, and the motion to modify overruled.
Petition for a rehearing denied, and motion to modify the mandate is overruled.
Note.- — -Reported in 105 N. E. 1033, 109 N. E. 58. Authority of attorney to bind client, 76 Am. Dec. 256; 30 Am. Rep. 358; 6 C. J. 631; 4 Cyc 928.