Case Information
*1 Bеfore WILKINS, Chief Judge, and MICHAEL and TRAXLER, Circuit Judges.
Petition for review denied by unpublished per curiam opinion. *2 COUNSEL ARGUED: Bruce J. Terris, TERRIS, PRAVLIK & MILLIAN, L.L.P., Washington, D.C., for Petitioners. M. Alice Thurston, Envi- ronment and Natural Resources Division, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Respondents. Michael Goodman Schneiderman, FOLEY & LARDNER, Chicago, Illinois, for Intervenor. ON BRIEF: Demian A. Schane, TERRIS, PRAVLIK & MILLIAN, L.L.P., Washington, D.C., for Petitioners. Thomas L. Sansonetti, Assistant Attorney General, Andrew Mergen, Ellen Durkee, Environment and Natural Resources Division, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C.; Daphne A. Fuller, Rаndy Ellen Hyman, Office of Chief Coun- sel, FEDERAL AVIATION ADMINISTRATION, Washington, D.C., for Respondents. Michael M. Conway, FOLEY & LARDNER, Chi- cago, Illinois; William O. Cooke, Jr., COOKE & COOKE, Greens- boro, North Carolina, for Intervenor.
Unpublished opinions are not binding precedent in this circuit. See Local Rule 36(c).
OPINION
PER CURIAM:
This case concerns the Federal Aviation Administration’s decision to approve plans to expand the Piedmont Triad International Airport (PTIA or the Airport) in North Carolina, which is operated by the Piedmont Triad Airport Authority (the Airport Authority). The FAA based its approval on an Environmental Impact Statement prepared in accordance with the National Environmental Policy Act, 42 U.S.C. § 4321 et seq. A non-profit group, Alliance for Legal Action, and seven individuals petitioned this court for review of the FAA’s deci- sion, challenging the adequacy of the EIS and requesting that we vacate the FAA’s decision and require the agency to prepare a new EIS. Although the EIS was not perfect, we hold that it was sufficient. We therefore deny the petition for review.
*3 I.
PTIA serves the area around Greensboro, High Point, and Winston- Salem, North Carolina. About 17,200 single-family homes and over 2,500 multi-family homes are within a five-mile radius of the Airport. It currently has two perpendicular runways, and various expansion plans have been considered over the years. In 1997 FedEx Corp., the overnight delivery company, solicited expansion proposals from air- ports in the Carolinas that were interested in accommodating a new FedEx mid-Atlantic cargo hub. FedEx selected PTIA over five other competing airports. After PTIA wаs selected, the Airport Authority applied to the FAA for approval to expand the Airport to meet FedEx’s needs. The expansion proposal calls for the building of a new 9,000-foot runway parallel to the existing 10,001-foot runway and the construction of a 300-acre sorting facility between the two runways. FAA approval is necessary to expand the Airport and to make the project eligible for federal funding. The FAA, as part of its consider- ation of the application, prepared an environmental impact statement in accordance with the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq.
One of the primary purposes of an EIS is to consider alternatives to the proposed project. In fulfilling this purpоse, the FAA developed a list of alternative sites for the cargo hub. The agency also developed alternative configurations for the runways and sorting facility at the PTIA site. In the first stage of its alternatives analysis, the agency eliminated most of the alternative sites and configurations because they did not meet the requirements that the hub be located at PTIA and that the airport have two parallel, 9,000-foot runways with space in between for a sorting facility. The five off-site alternatives were eliminated at this first stage mainly because they were not at the PTIA location; nevertheless, the FAA offered additional reasons for reject- ing each of the alternative locations. Five of the ten on-site alternative configurations were also eliminated. The next stage of the analysis compared the five remaining on-site configurations and the alternative of leaving PTIA as is (known as the "no-action alternative"). These six alternatives were the subject of extensive environmental analysis documented in the EIS issued in November 2001. On the basis of the EIS, the FAA selected a proposal cаlled W1-A1, a slight modification of the original proposal, and approved the expansion in a Record of *4 Decision (ROD) issued December 31, 2001. Under the decision the Airport is required to mitigate the problem of increased noise by offering to buy some properties near the Airport and providing insula- tion for others.
Alliance for Legal Action, a non-profit group representing about 900 persons living near the Airport, and seven individuals (together, ALA) have petitioned this court for review of the FAA’s decision approving the Airport expansion project on the ground that it was based on a faulty EIS. The Airport Authority has intervened as a respondent.
II.
We first consider whether we have subject matter jurisdiction.
Mitchell v. Maurer
, 293 U.S. 237, 244 (1934);
Betty B Coal Co. v.
Dir., Office of Workеrs’ Comp. Programs
,
The first question is whether a petition for review of the FAA’s
order is within the exclusive jurisdiction given to the courts of appeals
by § 46110(a). Specifically, we must decide whether an order includ-
ing determinations under multiple sections and statutes, with Part A
among them, may be considered an order issued under Part A. When
a statutory provision makes it "unclear whether review jurisdiction is
in the district court or the court of appeals the ambiguity is resolved
in favor of the latter."
Gen. Elec. Uranium Mgmt. Corp. v. United
States Dep’t of Energy
,
We must next clarify whether a petitioner may challenge all parts
of the order or just the Part A determinations that got the order into
this court in the first place. The statute allows review in the court of
appeals of an "order issued . . . under" Part A. 49 U.S.C. § 46110(a).
The ROD is a single order containing multiple determinations and
findings; it is not a collection of several different orders. By its plаin
language, the statute does not limit review to claims based on Part A.
Therefore, once the order is before an appellate court under
§ 46110(a), the court may consider a challenge to any part of it.
Cf.
Sutton
, 38 F.3d at 624-26 (construing predecessor statute);
City of
*6
Rochester v. Bond
,
III.
ALA cites both NEPA and the AAIA in stating its case, but its challenge to the EIS is really based on NEPA standards. NEPA’s requirement for an EIS is triggered by any "major federal action" that may have a significant effect on the environment, such as the FAA’s approval of the PTIA expansion project. See 42 U.S.C. § 4332(C). The EIS is the vehicle through which the agency contemplating an action (1) must examine and disclose the action’s environmental impact and (2) consider alternatives. 42 U.S.C. § 4332(2)(C)(iii). Here, ALA claims that the FAA’s Record of Decision approving the Airport expansion project cannot stand because it was based upon a faulty EIS. ALA challenges the EIS on the grounds that (1) the FAA’s statement of purpose and need in the EIS was too narrow, which led the agency to consider an inadequate range of alternatives to the proj- ect as proposed by its sponsors, and (2) the FAA fell short in its study of the environmental impacts of the project that it approved.
A.
An EIS must begin with a statement of the purpose and need for
the proposed federal action, 40 C.F.R. § 1502.13; and, as we said
above, it must include an evaluation of alternatives to the action, 42
U.S.C. § 4332(2)(C)(iii). The agency need not consider all of the pos-
sible alternative actions in the EIS; it is only required to look at those
that are reasonable in light of the project’s stated purpose.
See Friends
of Southeast’s Future v. Morrison
,
The statement of a projeсt’s purpose and need is left to the agen-
cy’s expertise and discretion, and we defer to the agency if the state-
ment is reasonable.
Friends of Southeast’s Future
.
Here, of course, the goals of the project sponsors (the Airport
Authority and FedEx) are to expand PTIA in a configuration that
meets FedEx’s preferences. ALA argues that the FAA gave those
preferences too much weight. The agency, however, is under a con-
gressional mandate to encourage and facilitate the construction of
cargo hubs. 49 U.S.C. §§ 47101(a)(4), (7). It is reasonable for the
agency to advance this goal by facilitating the construction of effi-
cient cargo hubs. The FAA does not, however, have any expertise in
operating hubs. It was therefore appropriate for the agency to take
into account FedEx’s and the Airport Authority’s expertise in design-
ing and locating a hub.
See Citizens Against Burlington
,
Even if meeting FedEx’s (and the Airport Authority’s) needs is an appropriate consideration, ALA argues, the airport configuration required by the statement of purpose and need is not necessary to sup- port effective cargo hub operations. But the FAA reasonably deter- mined otherwise. The agency found that thе configuration would minimize delays and provide FedEx with several operational advan- tages, such as the ability to launch all of its planes within a seventy- minute window. Because the agency’s determination is supported by substantial evidence, we defer to it. See Roanoke River Basin Ass’n v. Hudson , 940 F.2d 58, 61 (4th Cir. 1991).
ALA also argues that the Airport could support FedEx’s operations with a new runway shorter than the 9,000 feet required by thе state- ment of purpose and need. Although ALA provides alternate calcula- tions suggesting that a shorter runway would serve FedEx adequately, substantial evidence supports the agency’s determination that a 9,000- foot runway is needed. See id.
B.
An EIS must include a discussion of the environmental impacts of
the proposed action. 42 U.S.C. § 4332(C)(i);
Sierra Club v. Morton
,
The agency calculated noise impacts assuming that 95 percent of FedEx’s air traffic would pass over the area to the southwest of the Airport. ALA offers several reasons, including competing traffic and wind direction, why FedEx might not keep its traffic over the south- *9 west, pointing out that the company is under no obligation to follow that pattern. Indeed, the company insisted that the Airport not restrict its pattern. But FedEx’s plan for the hub is built around a traffic pat- tern that will keep its planes to the southwest. FedEx did not want to be tied to this pattern, but the FAA reasоnably assumed that the com- pany would generally operate the hub as it has planned. The calcula- tions based on this assumption are supported by substantial evidence, and we will not disturb them. See Roanoke River Basin Ass’n , 940 F.2d at 61.
ALA also argues that the FAA’s assumptions in its noise calcula-
tions failed to account for the extra noise generated by airplanes heav-
ily loaded with freight, taking off into a hеadwind, or taxiing or
waiting on the ground. Furthermore, an improved version of the noise
analysis program came out seven months before the EIS was com-
plete, but the FAA did not use it. ALA’s major complaint about the
adequacy of the noise analysis is that it takes insufficient account of
the concentration of FedEx’s operations in the middle of the night.
The agency used as its рrimary measurement the daily noise level
(DNL), which averages sound across an entire year. This measure-
ment diluted the noise impact of the FedEx planes. But the FAA also
performed two other types of noise analysis, the Equivalent Sound
Level test (Leq(9)) and the Sound Exposure Level test (SEL), that
provided more information on what the noise impact will be at partic-
ular times of day. ALA complains that even these measurements do
not adequately capture the effects of FedEx’s planes taking off one
after another in the middle of the night. The agency’s expertise on
how to measure environmental impacts is entitled to deference.
See
Hughes River Watershed Conservancy v. Johnson
,
ALA argues that the alternative noise measurements are not pre-
sented in the EIS in a manner that makes them understandable and
useful to the people likely to suffer from the noise. The Leq(9) data
*10
is presented in a table but not on a map; the SEL data is plotted on
a map, but in a way that does not offer any information beyond what
is already available from the DNL map. Providing the public with
information about environmental impacts is one of the essential goals
of NEPA.
Robertson v. Methow Valley Citizens Council
, 490 U.S.
332, 356 (1989). But the agency’s failings on this count in this case
are not significant enough for us to reject an otherwise adequate EIS.
We only ask whether an EIS contains "[a] reasonably thorough dis-
cussion of the significant aspects of the probable environmental con-
sequences."
Trout Unlimited v. Morton
,
ALA identifies two other environmental impacts that it says the EIS should have included: the effect of air pollution from toxic air- plane emissions and the effect of рopulation growth induced by the expansion. On the first, ALA cites several studies suggesting (but not concluding) that toxic airport emissions are dangerous to human health. The EPA, which administers air pollution programs, signed off on the FAA’s determination that the project would conform with cur- rent law. Of course, the fact that the emissions are within legal limits does not mean that they have no impacts that need to be considered. Here, because there is support for the FAA’s contention that there is no known cause-and-effect relationship between airplane emissions and human health, the agency was reasonable in its decision not to study these effects further. With respect to population growth, the FAA projects that construction of the hub will lead to population growth of only 2 percent by 2019. In light of the region’s projected 25 percent growth for the same period, the hub’s projected effects on the area’s population were insignificant enough to be left out of the EIS.
The FAA’s environmental impact statement was not perfect, but it was adequate to support the agency’s decision to approve the expan- sion project. The petition for review is therefore denied.
PETITION DENIED
