75 Colo. 608 | Colo. | 1924
delivered the opinion of the court.
The plaintiffs in error were contractors for a part of the work of building a system, of water works for the city of Sterling, Colorado. Defendants in error, Wells and Clavey, partners under the name of C. Wells and Company, were subcontractors, under plaintiffs in error, on the said work. Wells and Company completed their contract about March 13, 1920, and plaintiffs in error, Allen and Murphy, abandoned their work under said contract with Sterling, on May 5, 1920, before the completion of the work which they had contracted to do. When - Wells and Company finished their work there was a balance due them from the principal contractors, and they filed a verified statement of their claim with the city clerk of Sterling, under section 5408> R. S. 1908, a part of an act passed in 1899.
This action is by Wells and Company against Allen and Murphy to recover the balance due on the subcontract. Special findings were made by the jury to the effect that the work which Allen and Murphy were under contract to perform was completed after the 13th day of March, 1921. Suit was begun September 13, 1921. The plaintiffs had judgment for the amount of their claims, and the defendants bring error.
In behalf of the defendants it is urged, first, that the filing of the certificate of claim was in effect a payment by the defendants to Wells and Company, there being funds in the hands of the city due to Allen and Murphy under their
It is the contention of counsel for the defendants that the statute of 1915 is to be interpreted as requiring this suit to be brought within six months after the contractors, Allen and Murphy, ceased work. So interpreted the action was barred by the statute.
’ As to the first contention we are clearly of the opinion that the filing of the verified claim was not, as counsel contends, an election of remedies. .The statute of 1899, and that of 1915, were intended for the protection of laborers and material men, and we find nothing in either which indicates a purpose to deprive one, who has filed a claim under the earlier statute, from proceeding to recover by suit against the original contractor under the later statute. The statute of ’99 was repealed by an act effective February 15, 1921. If the contention of counsel for defendants is correct, the remedy of the plaintiffs would be against the city of Sterling as agent or trustee for the plaintiffs. The statute did not make the city, under the circumstances of this case, a debtor of Wells and Company. It appears in the record that the city of Sterling completed the work which had been abandoned by the contractors, and at the time of the trial was claiming that Allen and Murphy was indebted to the city in a considerable sum expended in finishing the work after its abandonment by plaintiffs.
We cannot agree with the contention of counsel that the six months period for the bringing of suit is to be computed from the time that the work was abandoned by the principal contractors. Section 9514, supra, requires contractors of public, works to give a bond conditioned for the prompt payment of all amounts due to material men or laborers, or subcontractors, incurred “in the prosecution of the work provided for in such contract.” It provides, further, that “such action for material furnished or labor
Mr. Justice Whitford and MR. Justice Sheafor concur.