5 Mich. 449 | Mich. | 1858
Lead Opinion
McKibbin agreed to cut and haul to the borders of Millington Creek, in Tuscola county, all the pine timber upon an eighty acre lot; to be cut into logs of twelve, fourteen, and sixteen feet in length, and laid on the bank not more than eight abreast, and the bank to be cleared of obstructions opposite where the logs were laid. The logs were to
MeKibbin cut and delivered thirteen hundred and sixty-four logs, and sued for payment therefor on the common counts. Allen pleaded the general issue with notice of recoupment; and introduced evidence to show that the logs were not cut of proper lengths;_ that in some places they were laid more than eight abreast; that the creek was not properly cleared of obstructions; that sixty-four logs, and from fifteen to thirty standing pine trees, were left; and that great loss was suffered from non-performance of the agreement. Evidence was offered to show that the work was not worth the contract-price, and excluded by the Court.
The Court charged the jury that the plaintiff below was not entitled to recover upon the contract at all, unless he had performed it; but that if there had been a partial performance, from which the defendant had derived benefit, the plaintiff was entitled to recover the contract-price, deducting therefrom any damages which the defendant had sustained by reason of non-performance.
The questions arising are, First, Whether the Court erred in excluding evidence of the value of the work, to reduce it below the contract-price; and, Second, Whether the rule of damages laid down was correct.
There is nothing in the case, so far as it appears, which would show that this contract was apportionable. Not only would the value of cutting and delivering logs on the bank differ according- to their location and accessibility, but the condition of the stream on which they were to be floated to market was very essential in determining their value on the bank; For if that was obstructed, the cost of removing
Where a party fails to comply substantially with an agreement, unless it,is apportionable, the rule is well settled that he can not sue upon the agreement, or recover upon it at all. And under the strict common law rule he was remediless. But the doctrine has now grown up, based upon equitable principles, that where anything has been done from which the other party has received substantial benefit, and which he has appropriated, a recovery may be had upon a quantum meruit, based on that benefit. And the basis of this recovery is not the original contract, but a' new implied agreement, deducible from the delivery and acceptance of some valuable service or thing. The idea is well expressed in Read vs. Rann, 10 B. & C. 438, by Parke J., who says: “In some cases a special contract, not executed, may give rise to a claim in the nature of a quantum meruit, e. g. where a special contract has been made for goods, and goods sent, not according to the contract, are retained by the party, there a claim for the value, on a quantum valebant, may be supported; but then, from the circumstances, a new contract may be implied.'1'1 Taking this as the basis of a recovery, there certainly could be no good reason for allowing a party who is in default to recover in any case more than his work or goods maybe worth; for that would allow him to speculate out of his own fraud or default; and he should not be allowed more than the same could be obtained for from any one else. To allow him the contract-price for what is worth much less, would not, in any sense,
And we also think the rule of damages laid down was erroneous. Upon a review of the authorities, they do not, in general, lay down any rule applicable to all cases. In several of them, the rule is given very much as the judge gave it to the jury in this case. But in nearly all, if not. all, of those cases, it appears either that there had been a completion of the thing contracted for, but with some variations in the method of constructing some complete thing, or else the plaintiff showed the work to have been worth more than the contract-price, and this rule was laid down to prevent the recovery of an excess, and to prevent his profiting by his own wrong. The same principle would forbid the application of the rule where the excess was in the contract-price. Without reviewing the cases in detail, we think that the only rule which harmonizes them may be laid down substantially as follows: The defaulting plaintiff can in no case recover more than the contract-price, and can not recover that, if his work is not reasonably worth it, or if, by paying it, the rest of the work wifi cost the defendant more than if the whole had been completed under the contract. The party in default can never gain by his default, and the other party can never be permitted to lose by it; and the price thus determined is the true amount recoverable on a quantum meruit.
There are, or may be, other damages growing out of the non-performance, which do not properly enter into the price, and which therefore can not be allowed or recovered with
We think the Court erred in rejecting evidence to reduce the value of the work done, and also in laying down the rule of damages, and for this reason the judgment below must be reversed, and a new trial granted.
Concurrence Opinion
concurred. Martin Ch. J. gave no opinion on the legal questions, not being satisfied from the evidence that the plaintiff had failed in a eubstantial performance of his agreement.