122 Ky. 825 | Ky. Ct. App. | 1906
These two appeals are prosecuted on the same record and from the same judgment. The facts involved in this litigation are substantially these: In March, 1903, Allen county entered into' a, contract with one B. P. Manley to erect a courthouse, in consideration for which the county obligated itself to pay Manley $12,987. The contract contains several articles. Those that are pertinent to an understanding .and disposal of this case are as follows:
“Article 3. No alteration shall be made in the wiork shown or described by the drawings and specifications except upon a written order of the architects'. "When so made the value of the work added or omitted shall be computed by the architects, and the amount so ascertained shall be added or deducted from the contract price.”
“Article 5. Should the contractor fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect, or failure being certified by the architects, the owner shall be at liberty after ten days’ written notice to the contractor to provide any such labor or material and to deduct the cost thereof from any money then due, or thereafter to become due, to the contractor under this contract. And if the architect shall certify that such' refusal, neglect, or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for said work,' and to employ any other
“Article 6. The contractor shall complete said building on or before October 31, 1903, and in default of his completing the courthouse on or before October 31, 1903, he agrees to pay the owners $2.50 per day on each day thereafter.” ,
“Article 9. If at any time there shall be evidence of any lien or claim for which, if established, the owner of said premises might become liable, and which is. chargeable to the contractor, the owner shall have the right to retain out of any payment then due and thereafter to become due an amount sufficient to completely indemnify him against such lien or claim. Should there prove to be any such claim after all payments are made, the contractor shall refund to. the owner all such moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the contractor’s default.”
For the faithful performance of this contract the county required the contractor to execute to it a bond, which he did, with the United States Fidelity & Guaranty Company as surety. This bond provides that the company is bound to Allen county in the sum of $6,000 conditioned that “if the said principal (Manley) shall well and truly indemnify and save harmless the said obligee (county) from any pecuniary loss, resulting from the breach of any of
The contractor commenced to work some time in April, and abandoned the contract on August 10, 1903, previous to which time he had been paid on the contract the sum of $9,974. A few days thereafter the county notified the guaranty company of the abandonment of the contract by Manley, and about October 1, 1903, the architects certified to the county that Manley had abandoned the contract, and the county' had a right to terminate it upon notice to Manley. Thereupon the county wrote and addressed to Manley at his last known place of address several letters, and also endeavored to ascertain his location that notice might be given him. The letters addressed to Manley were not delivered, nor was the county able to learn of his whereabouts. The c-ounty also wrote two or three letters to the guaranty company, informing it of the inability to locate Manley, and asking its advice as to what should be done in view? of the situation of affairs. The company took no action, however, and on October 31st the county canceled the contract with Manley and entered into a new contract with another contractor .to complete the building. In January, 1904, the county instituted this action on the bond to> recover from the surety $987, the excess it wfas obliged to
The record does not disclose the ground upon which the lower court rejected the claim of the county for $3,132, but it is probable that it was disallowed for the reason stated by‘counsel for the guaranty company in their argument against its validity in
There is no question about the correctness of the accounts, nor is there any dispute that they were valid against the contractor. This being so, we can see no good reason why the county should be obliged to suffer itself to- be sued by these different claimants and have judgment rendered against it for the debts and the court costs; nor is it necessary that this should be done in cases of this; character to enable the owner of the property to recover the amount paid from the surety on the bond of the contractor. If the correctness of these claims was disputed, or any issue was made, supported by proof as to whether or not the claims were due by the contractor, a different question would be presented, and in such a case it might be necessary, in order to recover, that the claim should be prosecuted to a final judgment, giving the interested parties an opportunity to make a defense.
The contention that material changes were made in the contract by the county and the contractor without direction of the architect is not supported by evidence. In fact, there is no evidence at all that any change of any character'was made in the contract
The contract proyides. that upon- the failure of the contractor to prosecute the work with diligence the
The guaranty company resists the payment of the items for $115 and $90 upon the ground that the contract provides that the expense incurred by the county for finishing the work shall be audited and certified by the architect, whose certificate thereof
Upon the whole ease we are of opinion that on the appeal of the United States Fidelity & Guaranty Company the judgment must be affirmed, and on the appeal of’ Allen county the judgment must be reversed, with directions to enter a judgment in favor of the county against the United States Fidelity & Guaranty Company for $3,132.37, with interest from January 27, 1904; and it is so ordered.
Petition for rehearing by appellee overruled.