No. 75 | 2d Cir. | Dec 15, 1914

ROGERS, Circuit Judge

(after stating the facts as above). The plaintiff corporation- is a manufacturer of brick-making machinery of all kinds, and also of brick kilns, and among the latter of the Youngren *480patented continuous fire kilns. It entered into the two written contracts referred to in the preliminary statement.

[1,2] The first of the two contracts is the one in which plaintiff agreed to furnish defendant with complete working drawings for the construction of a kiln and did not specify a time within which delivery was to be made. Defendant in its answer, however, alleged that delivery was agreed to be made within two weeks, but that this portion of the agreement was omitted from the writing by mutual mistake. And it asked that the writing should be reformed by adding to it the words:

“That said license and said complete working drawings are to be furnished by the plaintiff to the defendant within two weeks from the date hereof.”

It is, of course, within the province of a court of equity, in cases of-mutual mistake, to make the written evidence of an agreement correspond to the understanding of the parties. A common-law court, however, possessed no such power. In some of the states the distinction between actions at law and suits in equity has been abolished, and a suit for the reformation of a written contract, which would under the former system have been a suit in equity, is in such states a civil action under the Code. But in the federal courts the distinction between suits in equity and actions at law is maintained, and in a common-law action, such as this is, a federal court is without power to reform a contract; or to recognize as an equitable defense the failure of one of the parties to perform a condition which is alleged to have been omitted by mutual mistake from the contract as written. Moreover, in a court of equity it is not within its province to reform a written agreement, unless the evidence of the mutual mistake is clear, convincing, and satisfactory. And if in this action the court had the power to reform, there is no such clear, convincing, and satisfactory evidence that anything was left out of the writing which the parties intended to put into it as would be required to enable the court to exercise the power.

As respects the second contract, that for the machinery which was to be manufactured, no time was specified for the delivery of the machinery. It is not seriously claimed, however,' in respect to this contract that any certain time was fixed within which delivery of the machinery was to be made. The testimony showed that the matter of time was discussed at the time the contract was written, but objection was made to specifying the time, and it was intentionally omitted.

[3] As no time for performance is specified in either contract the implication is that a reasonable time was intended. What is “a reasonable time” depends upon the circumstances of each particular case. Whether the question of what is reasonable time is one of law for the court, or of fact for the jury, is not important in this case, as each side asked for direction of a verdict and dismissal, respectively, and neither asked to go to the jury on the whole case or any part of it.

[4] It appears that on April 25, 1911, defendant wrote plaintiff inquiring as follows:

“Will you kindly give us this information? In your opinion would your Mr.-be a suitable and competent man for us to hire in the construction of your Youngren kiln?”

*481To this the following reply was returned, dated April 28, 1911:

“Answering your communication of tbe 25th inst., we wish to say that, if we thought the party referred to therein was competent to build, construct, and start a kiln, the connection between him and ourselves would not be severed on the last day of this month, as will be done by request of ourselves. You will doubtless within the next few days receive a communication from a man by the name of-, who has had experience with a kiln, and we are confident is capable of building it. He stated to us that he would be willing to contract for the construction of the kiln; furthermore, wo desire to say to you that during May some time we will have released from Mason City, Iowa, a young man who has built a large kiln and started, or is with Mr. Vater while it is being started. We know that this young man is thoroughly competent to look after your kiln, and if you will not need any one before that time we believe he would be the best party whom we could recommend to you.”

This correspondence does not indicate that any breach of contract had occurred, or that plaintiff was regarded by defendant as being in default. The brick kiln to he built was plaintiff’s Youngren continu - ous brick kiln, and it was to be built according to plaintiff’s plans, specifications and drawings, which defendant now insists plaintiff agreed to furnish within two weeks from March 18, 1911, when the contract was executed. If plaintiff was in default, or was improperly delaying the forwarding of the plans and specifications, the natural thing would have been to have called attention to the matter in defendant’s letter of April 25th, and to have urged immediate delivery. Moreover, there is testimony in the record showing that the machinery which defendant ordered could not he manufactured in less than 90 days, and that plaintiff began the manufacture of it as soon as the order was received.

No other communication than that already mentioned passed between these parties until May 23, 1911, when defendant telegraphed plaintiff that, owing to its long delay in furnishing plans and machinery, the order was canceled.

As both sides left the case to the court, its findings that plaintiff was not in default will be accepted by us. That the trial court found adversely to defendant on the question of reasonable time must be inferred from the fact that plaintiff obtained judgment on both causes of action.

[5] The defendant alleges that nowhere in the complaint has plaintiff alleged that the plans, specifications, drawings, and license, together with the draft for $2,500 attached, were duly presented by plaintiff, and acceptance refused by defendant. The plaintiff alleged that in performance of its contract it prepared the necessary drawings and specifications called for in the contract, and forwarded the same to defendant in Olean, N. Y., in connection with a draft for $2,500, which draft is specifically set forth in words and figures, and that attached to tlie draft was the license, as called for in the contract; that the draft was duly presented to the Exchange National Bank of Olean, N. Y., for payment, and payment was refused. Defendant asserts that a search of the record will reveal that it is barren of any proof whatever showing that the plans, specifications, drawings, and license were ever presented to defendant and refused by it. The evidence shows that plaintiff sent a draft drawn on defendant to the Exchange National Bank of Olean, *482which was returned with notice of protest, and that attached to the draft were drawings, specifications, and the license, as called for by the contract.

It is also argued that if plaintiff relied upon a waiver of presentment, because of the attitude of defendant in refusing to accept any consignments, then this waiver should have been alleged and proved upon the trial. As the complaint was drawn with the idea in mind of due performance, we are told that it was incumbent upon plaintiff to show that it had performed every act necessary to be performed on its part in order to put defendant in default. But plaintiff was under no necessity of alleging tender of performance by plaintiff and refusal to perform by defendant. The law does not require an idle ceremony to be gone through. A tender is waived where a tenderee makes any declaration which amounts to a repudiation of the contract, or takes any position which renders a tender a vain and idle ceremony. Columbia Bank v. Hagner, 1 Pet. 455" court="SCOTUS" date_filed="1828-02-12" href="https://app.midpage.ai/document/president-of-the-bank-of-columbia-v-hagner-85591?utm_source=webapp" opinion_id="85591">1 Pet. 455, 7 L. Ed. 219; Duffy v. Patten, 74 Me. 396" court="Me." date_filed="1883-02-15" href="https://app.midpage.ai/document/duffy-v-patten-4934099?utm_source=webapp" opinion_id="4934099">74 Me. 396. When defendant sent its telegram of May 24, 1911, saying, “All consignments of any kind will be refused by us,” it waived a tender. In the face of this distinct and unqualified repudiation of the contract it is idle to claim that plaintiff should have gone through the futile ceremony of a formal tender.

At the time plaintiff was informed b.y defendant that all consignments of any kind would be refused, it had already manufactured about 40 per cent, of the machinerj' ordered by defendant. It completed the manufacture of the remainder of the machinery. All the machinery manufactured under the contract was sold by plaintiff at public auction. Notice of sale was given in advance to defendant, who was at the same time informed that it would be held liable for any loss which might be occasioned thereby. The sale was also duly advertised. The amount realized from the sale was $7,250, but the property was subsequently sold for $9,900, making a loss of $290, which plaintiff was allowed to recover in the second cause of action, along with certain other charges making the total $390, with interest. In the first cause of action plaintiff was allowed to recover $2,500, with interest.

[6, 7] It is assigned as error that the court dismissed the defendant’s counterclaim. The counterclaim asked damages to the extent of $10,000 for the plaintiff’s failure to perform its contract in accordance with its terms and conditions, thereby preventing defendant from manufacturing brick, to its great loss and damage. The defendant’s right to recover under the counterclaim was based upon the theory of unreasonable delay on the part of plaintiff in complying with the contract. Surely the plaintiff could not be entitled to recover upon its contract, and defendant at the same time have a right to recover upon its counterclaim damages it alleges it suffered by the failure of plaintiff to perform the contract. When the court determined that plaintiff had not been guilty of a breach of contract, the counterclaim, based on the theory that plaintiff had been guilty of a breach, was inevitably eliminated from the case. Moreover, defendant failed as matter of fact to show upon the trial as the basis of its counterclaim that it had actually been delayed by reason of any act or failure to act upon the part of plaintiff. As the trial court, with the assent of both sides, found as a fact that there *483was no unreasonable delay, there is no force in the contention that the dismissal of the counterclaim, which antedated the final disposition of the case, involved a finding of law on conflicting testimony, especially as the counterclaim set up in the answer was not for “unreasonable delay,” but for failure to furnish complete working drawings and specifications “within two weeks after” the parties had entered into the agreement of the 18th day of March, 1911.

There are numerous assignments of error relating to admission or exclusion of testimony. But as there was no unreasonable delay on the part of plaintiff in performing its contract, no error was committed in excluding testimony to show the amount of the damages sustained by defendant because of such delay as actually occurred.

Judgment affirmed, with costs.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.