Allegany Wind LLC v. Planning Board of AlleganyAllegany Wind LLC v. Planning Board of Allegany
It is hereby ordered that the judgment so appealed from is unanimously affirmed without costs.
Memorandum: Petitioner commenced this
Here, respondent issued a special use permit to petitioner on July 11, 2011, allowing it to construct the wind farm. Respondent notified petitioner that its permit would “expire if construction has not commenced within a year of [respondent‘s] approval.” On June 11, 2012, respondent extended the deadline “until the earlier of” one year or 90 days after the “conclusion
We conclude that, contrary to petitioner‘s contention, there was a material change in circumstances since the special use permit had been issued, and that the Planning Board‘s refusal to extend the special use permit for a second time was not arbitrary or capricious. When the special use permit was granted, petitioner contemplated the use of Nordex N1000 turbines. It is undisputed that, by the time petitioner requested its second extension of the permit, petitioner proposed using alternate turbine models. The record establishes that, during a meeting conducted by respondent several months before petitioner requested its second extension, petitioner‘s counsel answered in the affirmative when asked whether a change in turbine models would constitute a change in circumstances sufficient to warrant reconsideration of the project by respondent. Specifically, counsel stated, “Yes, looking at how specific the approvals were with regard to a turbine model, the potential impact may be different based on the characteristics.” We note that respondent‘s consultant concluded that use of the proposed alternate turbines would result in noncompliance with the Town‘s noise setback requirements.
We reject petitioner‘s further contention that the expiration date of its special use permit was tolled during the pendency of the lawsuit filed by CCCC. According to petitioner, the time period should be tolled because, until the litigation was resolved, it could not obtain necessary financing and could not commence construction of the wind farm. We reject that contention. Although several states have recognized an equitable doctrine that would allow for the tolling of the time period (see 3 Rathkopf, Zoning and Planning § 58:24 [4th ed]), New York has not done so and, in any event, this case does not warrant the application of that equitable doctrine.
The record makes clear that the CCCC lawsuit was not the primary reason for petitioner‘s failure to proceed with the project in a timely manner. As representatives of petitioner acknowledged in several media interviews, petitioner did not go forward with construction in large part because it was waiting to find out whether Congress was going to extend the Production
Moreover, when CCCC‘s attorney advised the Town and petitioner that CCCC did not intend to pursue the appeal, petitioner‘s attorney refused to sign a stipulation discontinuing the action. The Town therefore moved to dismiss CCCC‘s appeal, but petitioner threatened the Town with legal action if it did not withdraw the motion. After the Town withdrew its motion, CCCC then moved to dismiss its own appeal, but petitioner opposed the motion, notwithstanding that petitioner was a respondent on the appeal and had not cross-appealed. Thus, it is clear from the record that petitioner engaged in sustained efforts to delay dismissal of CCCC‘s appeal.
We have reviewed petitioner‘s remaining contentions and conclude that they lack merit. Present—Smith, J.P., Fahey, Lindley, Valentino and Whalen, JJ.