60 So. 295 | Ala. | 1912
Appellant sued appellee for the value of work and labor done in the construction of the latter’s line of railroad. The Talley-Bates Construction Company, a foreign corporation, had a contract with the defendant railroad company for the construction of that part of its road located in this state. Appellant had a contract with the Talley-Bates Company for the grading of a part of the road — was a subcontractor. These contracts were in writing, and their terms are not a matter of dispute. The Talley-Bates Company, to which we sometimes refer as the “construction company,” entered upon and for a time prosecuted its work through appellant and other subcontractors. Plaintiff (appellant) sues for an alleged unpaid balance due upon the work done by him.
- Two alternative theories are advanced in separate briefs filed on behalf of appellant. One of them takes the view, on the authority of Alabama Western R. R. Co. v. Talley-Bates Co., 162 Ala. 396, 50 South. 341, that the contract between the railroad company and the construction company was a mere nullity for the reason that the construction company, before entering upon the performance of its contract, failed to comply with that mandatory statute of the state which requires, under penalty of fine, that every corporation not organiz
The statute, the decision in the Talley-Bates Case, and the plea upon which that suit was defeated, if that could be ascertained, are beside the question to be decided. I Plaintiff cannot be allowed to recover against the defendant upon an implied contract for a reason wholly apart from the statute and the result of that suit —for the reason that plaintiff’s work was done, not for the railroad company, but for the construction company on the sole faith and credit of its express promise to pay plaintiff for the work done by him,. as the special contract in evidence shows, or if it be said that plaintiff looked also to defendant for compensation, then inducement to that expectation can be found only in the express collateral promise of the railroad company, alleged to have been made by and through its engineer, the authority and obligation of which will be considered when we come to consider that aspect of the case in which plaintiff relies upon an express promise. In either case there was an express contract covering the same field in which appellant would put into operation the law of contract by implication.^ The effect of all the'authorities is that, where the.parties have entered into a special contract, it is the exclusive source of legal rights and duties as regards the matters to which it pertains. An express contract excludes an implied
As sustaining that theory of his case now under consideration, plaintiff suggests that defendant defeated the claim of the Talley-Bates Company by pleading the latter company’s failure to observe the statute to which we have referred, and that defendant’s engineers, with knowledge of the fact that plaintiff would look to it for compensation, induced plaintiff to continue the work, when otherwise he would have avoided loss by abandoning it, and that defendant is estopped to bring loss and injury to him by defeating his just expectations thus raised. We are not advised by this record of the grounds upon which defendant defeated the suit of the Talley-Bates Company. We will assume to know that that suit was defeated on some ground for the reason that plaintiff offered in evidence the judgment entry in that case proving the fact and has assigned its exclusion for error. But the judgment entry, in the absence of the pleas which were not offered, does not show the specific grounds upon which that case was finally determined. For aught shown by the excluded judgment entry, the railroad company defeated, or might have been able to defeat, that suit on the ground that it had paid the Talley-Bates Company all it had earned. Let it be assumed, however, that plaintiff learned, as he states it, that the Talley-Bates Company was not liable to him, meaning thereby, as we understand, to assert his opinion, or apprehension perhaps, that the Talley-Bates Company could defeat any suit he might bring on the ground that it had not complied with the
We come now to the question whether, on the evidence shown in the record, the jury would have been justified in finding that the engineers had any real or apparent authority to make any express engagements or pledges of credit binding upon the defendant either as
Plaintiff relies upon LaFayette R. R. Co. v. Tucker, 124 Ala. 514, 27 South. 447. In that case plaintiff had a subcontract and sued the railroad company for the value of work done “extra the original specifications.” It appears that the work in question was extra the defendant’s original contract also. Defendant’s engineer requested performance and promised that defendant would pay. As to the matter in dispute there was no intervening contract. Plaintiff was. either an original
(Our conclusion is that there is no principle of law or equity Avhich would require defendant to pay plaintiff for the work done by the latter for the construction company, if indeed he has not been paid. Plaintiff’s remedy, if he has not been fully paid, is against the construction company.
There is no need to rule upon those assignments of error which relate to question of evidence and instructions to the jury. None of them reach or affect the essence of the case. The judgment will be affirmed.