OPINION
N/S Corporation appeals the district court’s denial of its motion to stay litigation and compel arbitration in a diversity action between itself and the Albert M. Higley Company. The issue before this Court is the interpretation of the arbitration clause in a contract between these two companies. For the foregoing reasons, we AFFIRM the district court’s decision denying N/S’s motion to stay the litigation and compel arbitration.
I.
Higley is a primary contractor on a project with the Greater Cleveland Regional Transit Authority. Higley hired N/S as a subcontractor to perform work on the project. The two parties entered into a written agreement (herein referred to as “Subcontract”), authored by Higley. During
II.
We have jurisdiction over this interlocutory appeal based on 9 U.S.C. § 16(a)(1), which states that an appeal may be taken from an order refusing to compel arbitration or refusing to stay an action pending arbitration. We review
de novo
a district court’s denial of such a motion.
Fazio v. Lehman Bros., Inc.,
This Court examines arbitration language in a contract in light of the strong federal policy in favor of arbitration, resolving any doubts as to the parties’ intentions in favor of arbitration.
Great Earth Cos., Inc. v. Simons,
However, the federal policy in favor of arbitration is not an absolute one. Arbitration under the Federal Arbitration Act is “a matter of consent, not coercion.”
Volt Info. Scis., Inc. v. Bd. of Trs. of Leland Stanford Junior Univ.,
The arbitration clause in the Subcontract of this case reads as follows: “Should [N/S] and [Higley] be unable to resolve said dispute(s) through mediation, any and all dispute(s), at the sole discretion of [Higley], shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association.” The dispute between the two parties in this case rests on differing interpretations of the “at the sole discretion of [Higley]” clause. Higley interprets this clause to
Higley relies on
Wilson Elec. Contractors
in support of its interpretation of the arbitration clause.
N/S relies on an interpretation by the Fourth Circuit of an arbitration clause in
Technosteel LLC v. Beers Constr. Co.,
Given the arguments of the two parties and our Court’s precedent, Higley’s interpretation of the contract appears correct. The most intuitive method of coming to this result is to closely examine N/S’s interpretation that the clause is intended to give Higley discretion over whether a dispute even exists. This leads to the irrational result of giving one party absolute control over whether there is any dispute between the two parties. Higley could, therefore, be able to perpetually stall any resolution of any dispute by simply denying the existence of a dispute.
Additionally, the existence of the litigation clause in this case is telling. N/S’s argument that this clause is only in effect for issues not covered by the arbitration is absurd. The arbitration clause specifically
In order for the litigation clause to have any semblance of logic and relevance to the Subcontract, Higley’s interpretation of the arbitration clause must be correct. The Subcontract is consistent in giving Higley sole discretion when it comes to a number of issues, including power to select the commercial mediation service and the power to decide the location of the mediation or arbitration. It is consistent that Higley also has retained the power to decide whether a dispute may be decided by arbitration or litigation.
Finally, N/S argues that the arbitration clause is ambiguous and “[ajmbiguous contractual language will be construed against the drafter of the contract.”
Mead Corp. v. ABB Power Generation, Inc.,
III.
For the above reasons, we AFFIRM the district court’s decision to deny N/S’s motion to stay the litigation and compel arbitration, and REMAND for further proceedings consistent with this opinion.
Notes
. That clause read: "[ejxcept as otherwise specifically provided for in this Subcontract, any controversy or claim arising out of or relating to this Subcontract, or the breach thereof which is not disposed of by agreement, shall, at the election of Contractor, be settled by arbitration ...”
Wilson Elec. Contractors,
. The clause in that case stated: “[any disputes] shall be decided by litigation unless the Contractor, at its sole opinion, advises the Subcontractor within 30 days of the dispute or claim arising that the Contractor elects to have the dispute or claim decided or resolved by way of arbitration.”
Technosteel,
. There has been some discussion within this Court as to the correct amount of deference an appellate body should give an arbitration award and whether this Circuit’s four-part test as enumerated in
Cement Divs., Nat'l Gypsum Co. v. United Steelworkers, Local 135,
