200 Mich. 109 | Mich. | 1918
Both parties to this suit are building contractors and both assisted in the construction of the Morgan & Wright building in Detroit in the year 1913. Plaintiff had the contract to construct the masonry, and defendant had the contract to erect the structural steel. During the progress of the work one John Debinski, a servant of plaintiff, was injured by what is claimed to have been negligent acts of defendant’s servants. Debinski demanded compensation of plaintiff, who was subject to the provisions of the workmen’s compensation act, and was paid a total of $1,-408.33 up to the commencement of this suit. This sum was increased to $2,215 at the time of trial. Plaintiff was permitted by the trial court to recover the sum which Debinski would have been permitted to recover had he elected to pursue his common law remedy. The jury returned a verdict for plaintiff of $10,000. Defendant contends that a recovery on this basis was wrong; that the recovery should have been limited to the sum paid to Debinski in discharge of plaintiff’s obligations imposed by the compensation act. In other words, that the question is one of indemnity only.
“Where the injury for which compensation is payable under this act was caused under circumstances creating a legal liability in some person other than the employer to pay damages in respect thereof, the employee may at his option proceed either at law against that person to recover damages, or against the employer for compensation under this act, but not against both, and if compensation be paid under this act the employer may enforce for his benefit or for that of the insurance company carrying such risk, or the commissioner of insurance, as the case may be, the liability of such other person.”
After Debinski was injured he had his choice of two remedies. He could pursue his common law remedy against the company, whose negligent acts caused his injuries, or he could demand compensation from his employer through the industrial accident board. He chose the latter and received an award of $10 per week for 400 weeks. This election by him under the terms of thé act would amount to a waiver upon hi% part of his common law remedy (section 15, supra). The common law action having been extinguished by Debinski’s election, an assignment of it could not furnish a basis for this suit, and we do not understand it is now so claimed, although one count of the declaration counted upon an assignment of the cause of action. We, therefore, conclude that the basis for this suit must be found in the act itself, if at all. The latter part of the section provides that:
“If compensation be paid under this act the employer may enforce for his benefit, or for that of the insurance company for carrying such risk, or the commissioner of insurance, as the case may be, the liability of such other person.”
This view is strengthened by the holding in Grand
“This case involves a relation of indemnitee and indemnitor in which a liability over is1 placed upon the original tort-feasor whose negligence caused the injury, a relation which may be created by contract or legislation for protection of the party, who, though not actively guilty of the tort, may, by law, be liable therefor to the injured party.”
2. If the question be one of indemnity the further question is raised, when may the amount allowed by the compensation board be recovered by the employer? We think a cause of action would accrue to the employer whenever he has made a payment in pursuance of the order of the commission (22 Cyc. p. 98), and this would be true whether the payment was a weekly payment or of the entire award. Any other rule would likely result in more or less confusion by reason of the right of the commission to revoke its orders, to reduce the number and amount of payments and to discontinue them altogether. In accordance with request of counsel, the case may be remanded to the trial court where the amount paid by plaintiff will be ascertained, and when ascertained a judgment for that amount will be affirmed. The subsequent payments may be sued for and recovered as they become due and payable under the orders of the industrial accident board. In default of the amount being ascertained and entry of judgment thereon within thirty days from the date of filing this opinion, the judgment of the trial court will be reversed and a new trial ordered, with costs to the defendant in either event.