ALASKA DIVERSIFIED CONTRACTORS, INC., and Fischbach & Mоore of Alaska, Inc., d/b/a Alaska Diversified-Fischbach, a joint venture of Alaska Corporations, Appellant, Cross-Appellee,
v.
LOWER KUSKOKWIM SCHOOL DISTRICT, Appellee, Cross-Appellant.
Supreme Court of Alaska.
*582 R. Everett Harris, Jensen, Harris & Roth, Anchorage, and Stuart G. Oles, Arthur D. McGarry, and Douglas S. Oles, Oles, Morrison & Rinker, Seattle, Wash., for appellant/cross-appellee.
Saul R. Friedman, Hedland, Fleischer, Friedman, Brennan & Cooke, Anchorage, and Stephen L. Nourse and John P. Griffin, Carney, Stephenson, Badley, Smith, Mueller & Spellman, P.S., Seattle, Wash., for appellee/cross-appellant.
Before MATTHEWS, C.J., and RABINOWITZ, BURKE, COMPTON and MOORE, JJ.
OPINION
MATTHEWS, Chief Justice.
On remand after our decision in Lower Kuskokwim School District v. Alaska Diversified Contractors, Inc.,
ADF contends that the trial court erred in failing to enter judgment in its favor on a theory of promissory estoppel or, in the alternative, failing to order a new trial on that theory. In addition, ADF argues that this court should reconsider its prior decision.
*583 A. Reconsideration of Prior Decision
We turn first to the contention that our prior decision should be reconsidered. The underlying facts are as follows:
The relevant contracts called for ADF to build several schools for the School District. At trial, the central dispute was over when completion was required.
The contracts state on their face that completion was required by August 31, 1980. ADF, however, presented evidence that the School District told ADF during a рre-bid conference it could actually complete construction up to eleven months later and that this was the purpose behind a contract provision which imposes only nominal liquidated damages for the first eleven months after August 31.
After work began, the School District pressured ADF to complete the schools by August 31, 1980. ADF employees testified that they did accelerate the work pace in response to this pressure. ADF seeks compensation for its costs resulting from what it perceives as this unwarranted acceleration.
Lower Kuskokwim,
We held that the contracts were integrated and that therefore they could not be varied by prior negotiations or agreements. Id. at 64. It followed that the school district did not breach the contraсts by requiring compliance with the August 31 deadline. We therefore reversed the judgment in favor of ADF and remanded for a disposition consistent with the opinion. Id.
ADF now requests that we overrule this decision primarily because (1) it is contrary to "an overwhelming body of Alaska precedent which had as a practical matter rendered the parol evidence rule a dead letter in Alaska," and (2) this court should not have determined that the contracts were integrated.
Our scope of review on the question of reconsideration is narrow. The doctrine of law of the case generally prohibits reconsideration of issues which have been decided in a prior appeal in the same case. Wolff v. Arctic Bowl, Inc.,
No such circumstances appear in this case. ADF's argument that our decision was contrary to an overwhelming body of рrecedent which had made the parol evidence rule a dead letter in Alaska reveals a fundamental misunderstanding of the parol evidence rule.
ADF cites a number of cases "typified" by Wright v. Vickaryous,
The parol evidence rule is a rule of substantive law which holds that an integrated written contract may not be varied or contradicted by prior negotiations or agreements. Before the parol evidence rule can be applied, three preliminary determinations must be made: (1) whether the contract is integrated, (2) what the contract means, and (3) whether the prior agreement conflicts with the integrated agreement.[2]Alaska Northern Dev., Inc. *584 v. Alyeska Pipeline Serv. Co.,
ADF's contention that the parol evidence rule had become ineffective in Alaska is particularly untenable in light of Alaska Northern, where we explicitly recognized that in determining the meaning of a contract prior to the application of the parol evidence rule, extrinsic evidence should be consulted.[4]Id.
This is not to say that the parol evidence rule is easy to apply. There is an obvious tension between using extrinsic evidence of a prior agreement for the purpose of determining the meaning of an integrated contract, and barring the use of a prior agreement to change an integrated contract once its meaning is determined. The evidence which is consulted to determine meaning may be the same evidence which is later excluded, or rendered irrelevant, by the parol evidence rule. However, this apparent conflict is made manageable in most cases by various practical rules. For example, while extrinsic evidence should be consulted in determining the meaning of a written contract, nonetheless "after the transaction has been shown in all its length and breadth, the words of an integrated agreement remain the most important evidence of intention." Restatement (Second) of Contracts § 212 comment b. Further, questions of interpretation of the meaning of written documents are treated as quеstions of law for the court except where they are dependent for their resolution on conflicting extrinsic evidence. O'Kelley,
ADF's argument that this court could not have determined that the contracts were integrated also lacks merit. As we stated in our prior opinion, that question is one for the court. Lower Kuskokwim,
ADF also stresses the absence of an integration clause in the contracts.[6] However, the "Instructions to Bidders" form supplied to ADF contains a clause which is functionally equivalent to an integration clause. It deals specifically with pre-bid oral instructions:
Explanation to Bidders. Any explanation desired by bidders regarding the meaning or interpretation of the drawings and specifications must be requested in writing and with sufficient time allowed for a reply to reaсh them before the submission of their bids. Oral explanations or instructions given before the award of the contract will not be binding. Any interpretation made will be in the form of an addendum to the specifications or drawings and will be furnished to all bidders and its receipt by the bidder shall be acknowledged.
(Emphasis added). The terms of this clause highlight the correctness of the ruling that these contracts were integrated. They were publicly bid contracts whose terms could not be modified materially except in a formal fashion, so that all those interested in obtaining the contract would be treated equally.[7]
We also reject as insubstantial ADF's remaining arguments as to reconsideration. Exceptional circumstances do not exist, thus the law of the case doctrine precludes reconsideration.
B. Promissory Estoppel
ADF contends that on remand the trial court should have entered judgment in its favor based on promissory estoppel. Alternatively, it contends that the court should have ordered a new trial based on this theory. Promissory estoрpel resulted, according to ADF, from the School District's representations prior to signing the contracts and ADF's resulting detrimental reliance. In effect, ADF contends that although parol evidence cannot be admitted to contradict the cоntracts, the same evidence may be admitted in order to show an enforceable promise supported by detrimental reliance.
ADF's promissory estoppel theory necessarily is controlled by this court's prior finding that the contracts at issuе are integrated. Just as the parol evidence rule renders inoperative prior agreements based on consideration, it discharges prior agreements based on detrimental reliance. Peoples Nat'l Bank v. Bryant,
AFFIRMED.
NOTES
Notes
[1] Other cases cited by ADF include Mitford v. de Lasala,
[2] Comment b to § 213 of the Restatement (Second) of Contracts (1981) states:
Whether a binding agreement is completely integrated or partially integrated, it supersedes inconsistent terms of prior agreements. To apply this rule, the court must make preliminary determinations that there is an integrated agreement and that it is inconsistent with the term in question... . Those determinations are made in accordance with all relevant evidence, and require interpretation both of the integrated agreement and of the prior agreement. The existence of the prior agreement may be a circumstance which sheds light on the meaning of the integrated agreement, but the integrated аgreement must be given a meaning to which its language is reasonably susceptible when read in light of all the circumstances.
[3] Restatement (Second) of Contracts § 214 comment b states:
Words, written or oral, cannot apply themselves to the subject matter. The expressions and general tenor of speech used in negotiations are admissible to show the conditions existing when the writing was made, the application of the words, and the meaning or meanings of the parties. Even though words seem on their faсe to have only a single possible meaning, other meanings often appear when the circumstances are disclosed. In cases of misunderstanding, there must be inquiry into the meaning attached to the words by each party and into what each knew or had reason to know.
[4] Alaska Northern was decided less than a year prior to the trial in the present case.
[5] See Restatement (Second) of Contracts § 212 comment d:
Likewise, since an appellate court is commonly in as good a position to decide such questions as the trial judge, they have been treаted as questions of law for purposes of appellate review. Such treatment has the effect of limiting the power of the trier of fact to exercise a dispensing power in the guise of a finding of fact, and thus contributes to the stability and prеdictability of contractual relations.
[6] An example of an integration clause appears in Kupka v. Morey,
[7] See Kenai Lumber Co., Inc. v. LeResche,
[8] Contra Ehret Co. v. Eaton, Yale & Town, Inc.,
