56 So. 767 | Ala. Ct. App. | 1911
This case was tried in the court below without a jury. The plaintiffs (appellees) brought suit to recover damages for alleged false representations and breach of agreement or contract to maintain a certain temperature in the cold storage room of the plaintiffs, by pumping brine from a tank through coils of piping. The defendant (appellant) pleaded the general issue in short by consent, and the case was tried on the issue thus formed, and judgment rendered for plaintiffs on the third count of the complaint; this count being ex contractu, seeking to recover damages for breach of a contract entered into between the parties, whereby the defendant agreed to keep plaintiffs’ storage room at a temperature of 20 degrees Fahrenheit for a period of 5 years for a consideration of $60 per month. Connected with, and as a part of, the contract, the parties entered into a lease, whereby the plaintiffs rented or leased the storage room and certain other space in defendant’s building to operate an ice cream business. On the faith of this lease and contract, the plaintiffs put in a concrete floor, and otherwise fitted up the leased space in defendant’s refrigerator plant for the conduct of their business.
The testimony was in conflict as to the temperature maintained in the cold storage room; the plaintiffs’ be
The appellant’s contention that a judgment could not legally be rendered on the evidence in favor of appellees on the third count of the complaint, for the reason that the allegations of the third count were not proven, is without merit. True the evidence was in conflict, and there was evidence introduced on the part of the appellant tending to prove acts or omissions constituting a breach of the contract on the part of the appellees, and that the low temperature was attributable to the fault of appellees; but the trial court, having weighed and considered all the evidence pro and con upon the breaches of the contract, reached the conclusion that the appellant had breached the contract, and that the appellees were entitled to recover for the breaches committed by the appellant; and this court, upon review of the finding of the lower court, will not disturb its findings on the disputed facts and judgment rendered thereon, unless the evidence plainly fails to support the finding. We are by no means convinced, after a careful examination of the evidence, that the judgment of the lower court is not supported by the evidence. Although the evidence is in serious conflict on the material issue before the court as to the responsibility for a breach of the contract, there was abundant evidence to support the finding that appellant breached the contract by failing to keep the storage room at the temperature agreed and contracted to be maintained.
The breach of the contract was a continuing act, occurring from day to day, and consisting in a failure to keep the room at the contract temperature. While it was the duty of the appellees to use reasonable exertions to prevent loss after a breach of the contract by the appellant, it was also their duty to endeavor to carry out the contract in good faith; and it appears from the evidence that only a part of the ice cream put in the storage room from day to clay was “softened” or rendered unmerchantable, and that appellees, from day to day for 30 or 40 days, continued to use this room in the operation of their business, making complaint from time to time of the high temperature, and requesting appellant to comply with the contract and reduce the temperature to the degree agreed upon. It also appears from the evidence that during this period the appellees were “paddling down” the ice cream, and attempting to save that part of it that “softened,” and to make use
Appellees could not be expected to abandon their contract and lose the valuable improvements installed by them, without giving the storage room a fair and reasonable trial, and it is not shown that they persisted too long or unreasonably in their expectation of appellant’s complying with the contract and reducing the temperature of the-room, or that they did not protect themselves reasonably from loss growing out of a continuing use of the storage room after they had ascertained that it was not kept at a sufficiently low temperature to preserve their product; but, even if they had, the amount of damage thus occasioned, by failing to use reasonable precautions to minimize the loss, is not. shown by the evidence, and it is apparent that ho attempt was made on the trial to separate the damage, if any, accruing after the contract was breached by the appellant; on the .contrary, the case was tried on the general issue, and the contention and efforts of appellant were entirely directed to showing that- there had been no breach of the contract.
It does not appear that the court below committed error in the judgment rendered, and the case will be affirmed.