ALABAMA RIVERS ALLIANCE, AMERICAN RIVERS, INC. AND LAKE WATCH OF LAKE MARTIN, PETITIONERS v. FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT ALABAMA POWER COMPANY, INTERVENOR
No. 01-1408
United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued November 21, 2002 Decided April 11, 2003
On Petition for Review of Orders of the Federal Energy Regulatory Commission
Ronald A. Shems argued the cause for the petitioners.
David K. Mears, Senior Counsel, Office of the Attorney General, State of Washington, argued the cause for amici
Bills of costs must be filed within 14 days after entry of judgment. The court looks with disfavor upon motions to file bills of costs out of time.
David H. Coffman, Attorney, Federal Energy Regulatory Commission, argued the cause for the respondent. Cynthia A. Marlette, General Counsel, and Dennis Lane, Solicitor, Federal Energy Regulatory Commission, were on brief. Timm L. Abendroth entered an appearance.
James H. Hancock Jr. and P. Stephen Gidiere III were on brief for intervenor Alabama Power Company. Jennifer M. Buettner entered an appearance.
Donald H. Clarke and Henri D. Bartholomot were on brief for amici curiae National Hydropower Association and Edison Electric Institute.
Before: HENDERSON, TATEL and GARLAND, Circuit Judges.
Opinion for the court filed by Circuit Judge HENDERSON.
KAREN LECRAFT HENDERSON, Circuit Judge: Petitioners Alabama Rivers Alliance, American Rivers, Inc. and Lake Watch of Lake Martin seek review of the decision of the Federal Energy Regulatory Commission (FERC or Commission) to amend an existing hydroelectric license issued to Alabama Power Company (Alabama Power). The amended license authorizes Alabama Power to replace three existing turbine generators at its Martin Dam Project on the Tallapoosa River with new, more efficient units. The petitioners contend that the Commission erred in issuing the license amendment without first requiring Alabama Power to obtain water quality certification from the state of Alabama. Because we conclude that an increase in the volume of water passing through the dam‘s replacement turbines “may result in any discharge into the navigable waters” within the meaning of section 401(a)(1) of the Clean Water Act (CWA),
I. Background
A. The Regulatory Framework
The Federal Power Act (FPA) authorizes FERC to issue licenses “for the purpose of constructing, operating, and maintaining dams, water conduits, reservoirs, power houses, transmission lines, or other project works necessary or convenient ... for the development, transmission, and utilization of power across, along, from, or in any of the streams or other bodies of water over which Congress has jurisdiction” under the Commerce Clause.
Although “the FPA represents a congressional intention to establish ‘a broad federal role in the development and licensing of hydroelectric power,‘” the CWA “has diminished [the FPA‘s] preemptive reach by expressly requiring the Commission to incorporate into its licenses state-imposed water-quality conditions.” Am. Rivers, Inc. v. FERC, 129 F.3d 99, 111 (2d Cir. 1997) (quoting California v. FERC, 495 U.S. 490, 496 (1990)). FERC‘s hydroelectric licenses are thus subject to, among other conditions, the requirements of section 401 of the CWA. See Escondido Mut. Water Co. v. La Jolla Indians, 466 U.S. 765, 775 (1984) (“[W]hile Congress intended that the Commission would have exclusive authority to issue all licenses, it wanted the individual Secretaries [i.e., the Secretaries of the Interior, War and Agriculture] to continue to play the major role in determining what conditions would be included in the license in order to protect the resources under their respective jurisdictions.“).
Section 401(a)(1) of the CWA provides that “[a]ny applicant for a Federal license or permit to conduct any activity ... which may result in any discharge into the navigable waters, shall provide the licensing or permitting agency a certification
B. The License Amendment Proceedings
Located on the Tallapoosa River in central Alabama, Alabama Power‘s Martin Dam Project has the capacity to generate 154.2 megawatts (MW) of electric power. The dam project generates electricity by taking in water from the reservoir above the dam, funneling the water through four turbine generators and then releasing the water through four penstocks into the river below the dam. The first three 33-MW turbine generators began commercial operation in 1927.
On December 22, 2000, Alabama Power filed an application with the Commission to amend its license to authorize the replacement of the three 33-MW turbine generators. These units had exhibited serious leakage problems and efforts to repair them had been largely unsuccessful. According to Alabama Power‘s estimates, the replacement turbines would increase the flow of water into the river below the dam project by approximately 900 cubic feet per second (cfs), an increase of 8.6%, and would increase each generator‘s capacity by 7 to 10 MW, an increase of roughly 20-30%.
Shortly after the Commission provided public notice of Alabama Power‘s license amendment application, the petitioners moved to intervene, arguing that section 401(a)(1) of the CWA required Alabama Power to obtain state water quality certification before the Commission could amend its existing license. On May 23, 2001, the Commission issued an order approving Alabama Power‘s proposed license amendment. Ala. Power Co., Project No. 349-070, Order Amending License, 95 F.E.R.C. ¶ 62,156 (May 23, 2001) (Order Amending License). In doing so, the Commission rejected the petitioners’ argument that the license amendment required state water quality certification under section 401(a)(1), concluding that “[r]eplacing and upgrading the existing turbine-generator units is not an ‘activity which may result in a discharge’ within the meaning of [s]ection 401(a)(1).” Id. at 64,220.
While the Commission recognized that “replacement of the turbine generators would increase the [dam] project‘s hydraulic capacity, with the result that water would be discharged more quickly [into the river],” it found that “the nature of the discharge would not change,” i.e., that “water from the reservoir would continue to be released through the new turbine generators in essentially the same manner as it is now released through the existing turbine generators.” Id. Rea-
The Commission‘s Order Amending License likewise rejected the petitioners’ argument that 18 C.F.R. § 4.38(f)(7)(iii) required Alabama Power to obtain state water quality certification for its proposed license amendment. Id. Section 4.38(f)(7)(iii) provides that “any application to amend an existing license ... requires a new request for water quality certification ... if the amendment would have a material adverse impact on the water quality in the discharge from the project.” 18 C.F.R. § 4.38(f)(7)(iii). Citing its environmental assessment of the proposed license amendment, the Commission concluded that the proposed modifications to the three 33-MW turbine generators would not have a “material adverse effect” on the water quality of the dam project‘s discharge. Order Amending License, 95 F.E.R.C. at 64,220. Accordingly, the Commission held that section 4.38(f)(7)(iii) did not require Alabama Power to obtain state water quality
The petitioners moved for rehearing. On July 23, 2001, the Commission denied the motion, again rejecting the argument that section 401(a)(1) required Alabama Power to obtain state water quality certification for its proposed license amendment. Ala. Power Co., Project No. 349-078, Order Denying Rehearing, 96 F.E.R.C. ¶ 61,096 (July 23, 2001) (Order Denying Rehearing). Relying on North Carolina v. FERC, 112 F.3d 1175 (D.C. Cir. 1997), the Commission explained that section 401(a)(1) applies only to activities that may ” result in a discharge,” not to those activities that simply alter an existing discharge, Order Denying Rehearing, 96 F.E.R.C. at 61,386. Alabama Power‘s license amendment did not trigger the certification requirements of section 401(a)(1), the Commission reasoned, because replacement of the existing turbine generators “will at most alter an existing discharge by increasing the amount of water flowing through the units at any given time and, concurrently, reducing the amount of time that the units will operate each day.”4 Id.
Noting that all construction would be completed within the existing structures of the dam project as well as “in the dry,” the Commission dismissed the petitioners’ argument that replacement of the turbine generators would result in a
II. Analysis
On review, the petitioners maintain that the Commission erred in issuing Alabama Power‘s proposed license amendment without first requiring Alabama Power to obtain a water quality certification from the state of Alabama.7 Specifically,
A. Standard of Review
We review a Commission licensing decision under the FPA to determine whether it was “arbitrary and capricious.” North Carolina, 112 F.3d at 1189; Bangor Hydro-Elec. Co. v. FERC, 78 F.3d 659, 663 & n.3 (D.C. Cir. 1996). In reviewing such a decision, we must treat the Commission‘s findings of fact as “conclusive” if they are “supported by substantial evidence.”
As a result, we must simply resolve a question of statutory interpretation-whether the installation and operation of the replacement turbines is an activity that “may result in any discharge” within the meaning of section 401(a)(1) of the CWA.
B. The Increased Water Flow
The petitioners’ argument is a straightforward one. As previously discussed, section 401(a)(1) requires state water quality certification for “any activity ... which may result in any discharge into the navigable waters.”
The Commission contends, however, that the petitioners misinterpret the plain language of section 401(a)(1) and thereby misunderstand what must be shown in order to establish that an activity “may result in any discharge.”11
[T]he existence of certification rights under [s]ection 401(a)(1) does not depend on whether a discharge is “altered.” Section 401(a)(1) certification rights vests only if an activity “may result in” a discharge. This distinction is of no small moment. The word “alter” means to change something from its previous state, WEBSTER‘S NEW INT‘L DICTIONARY 63 (3rd ed. 1961) (“to cause to become different“), implying that the thing changed was already in existence. By contrast, the word “result” implies causation. See id. at 1937 (“arise as a consequence“). Obviously, a subsequent event cannot be the cause of something that is already in existence. Given the disparity between petitioners’ proposed test and the words of the [CWA], we elect to remain faithful to the language chosen by Congress and require that an activity “result in” a discharge in order to trigger the certification requirements of [s]ection 401(a)(1).
Citing “the lack of equivalence between [an] activity that may increase [per-second water flows] and [an] activity that ‘may result in’ such flows,” Br. for Resp‘t at 12 (emphasis in original), the Commission contends that our reasoning in North Carolina applies with equal force here. Replacement of the turbine generators cannot, in the Commission‘s view, possibly “result in” water flows that “pre-existed and will continue, in some form, regardless of whether that replacement is approved.” Id. at 14-15. At most, the Commission argues, replacement of the turbine generators will “‘alter an existing discharge by increasing the amount of water flowing through the units at any given time and, concurrently, reduc-
Yet the Commission‘s argument ignores the critical feature of the licensing activity at issue in North Carolina: operation of the pipeline project-i.e., the “activity” authorized by the license amendment-resulted in the withdrawal of water from the Lake Gaston reservoir. North Carolina, 112 F.3d at 1187. In our view, the distinction between an increased discharge and a decreased discharge is “of no small moment.” Id. at 1188. But this should hardly come as a surprise, for we recognized as much in North Carolina itself. Relying on the definition of “discharge of a pollutant” and “discharge of pollutants,”12 we observed that “the word ‘discharge’ contemplates the addition, not the withdrawal, of a substance or substances.” Id. at 1187 (emphasis added). Because the operation of the pipeline project would not result in the “addition” of anything to Lake Gaston, we held that “[a] decrease in the volume of water passing through the dam turbines cannot be considered a ‘discharge’ as the term is defined in the CWA.” Id. at 1188 (“Obviously, the withdrawal of water from Lake Gaston will add nothing; nor will the withdrawal of water from Lake Gaston increase the volume of water flowing through the turbines of the Project dams.“).
Our rejection in North Carolina of the “altered discharge” argument does not preclude this conclusion. North Carolina, 112 F.3d at 1188 (distinguishing activities that “alter” discharge from those that “may result in” discharge). While a decreased discharge does not “cause” a discharge under section 401(a)(1), see id., an increased discharge does in fact cause or, in the words of the statute, “result in” a discharge requiring state water quality certification,
III. Conclusion
For the foregoing reasons, we conclude that section 401(a)(1) of the CWA requires Alabama Power to obtain
Accordingly, we decline to consider whether the Martin Dam Project‘s draft tube aeration system would prevent DO levels from dropping below Alabama‘s water quality standards. See supra notes 3-4.
So ordered.
