Opinion by
This is an appeal by the A1 Hamilton Contracting Company (Hamilton) from an order of the Environmental Hearing Board (EHB) dismissing Hamilton’s appeal of an abatement order as moot. On September 3, 1983 a Dеpartment of Environmental Resources (DER) inspector conducted an inspection of Hamilton’s operation. During his inspection, the inspector noticed that an underdrain constructed by Hamilton was plugged with silt .and other debris. In his written report the inspector included an instruction that Hamilton clean the underdrain. On September 19,1983 two supervisory inspectors conducted a partial exаmination of Hamilton’s operation; they noted that a catch basin .and diversion ditch needed cleaning and further noted that the underdrain, which had been examined ■on September 3, 1983, was still plugged. Consequently, on Séptember 19, 1983 the two supervisors ordered Hamilton to clean up the diversion ditch, catch basin and underdrain by September 30, 1983. This September 19,1983 order apparently, was not formalized until it appeared ,as an abatement order dated .September 29, 1983 and issued pursuant to Section 4.3 of the Act of May 31, 1945, P.L. 1198, as amended, 52 P.S.
On October 28,1983 Hamilton filed an aрpeal from the September 29,1983 abatement order with the EHB alleging, inter alia, that the ¡abatement order was devoid of any factual basis, that it was arbitrary and capricious, that compliance by Sеptember 30, 1983 had been physically impossible because the order had not •been received until October 4, 1983, ¡and that the order violated constitutional and statutory rights because no hearing had been afforded to Hamilton prior to the administrative order. At no time did Hamilton seek a stay of the September 29, 1983 order. By order dated February 23, 1984 the EHB concluded that the September 29, 1983 order hаd been fully complied with and, thus, that there was no relief which the EHB could grant. Accordingly, it dismissed the appeal as moot. Hamilton has appealed that dismissal to this Court.
Where there is no fact finding bеlow, our scope of review is, of necessity, limited to determining whether there has ¡been a constitutional violation or an error of law. Section 704 of the Administrative Agency Law, 2 Pa. C. S. §704. In determining whethеr a case is moot, the appropriate inquiry is whether the litigant has been deprived of the necessary stake in the outcome, In Re Gross,
In attempting to demonstrate the necessary stake, Hamilton first maintains that by complying with the DEE abatement order it expended time and money •and is now deprived of the opportunity to challenge whether it was, in fact, guilty of the named violations. It argues that denial of a hearing constituted deprivation of property without due process. Hamilton has already cоmplied with the abatement order; certainly the EHB would not issue an order after a hearing directing them to again plug the catch basin, diversion ditch and underdrain. While sums of money may have been expended, the clean up is now complete. Had Hamilton .seriously questioned the propriety of the abatement order it could have requested a stay pursuant to DEE regulation - 21.76, 25 Pa. Code §21.76. This it fаiled to do. Thus, it took the clean-up action at its own .risk that .such action would not, in fact, be found to .be legally required. The fact that Hamilton was deprived of property without a hearing because of its compliance with the ¡abatement order does not justify ignoring the fact that the appeal is moot with respect to the injury of expenditure of time and money to achievе compliance with the abatement order. To the contrary, where a case is moot and a constitutional issue is raised the courts are most reluctant to consider the constitutional claim. In Re Gross,
Hamilton-next maintains that a civil penalty has been assessed against it pursuant to Section 18.4 of the Act,
Finally, Hamilton maintains that in assessing future civil penalties one factor which is considered by DEB is prior violations and that by precluding Hamiltоn from litigating the propriety of the abatement order the result is to subject Hamilton to the penalty escalation provision in DEB regulation 86.194, 25 Pa. Code §86.194. That regulation provides:
System for assessment of penalties.
(b) Civil penalties shall be assessed as follows :
(6) History of previous violations. In determining a pеnalty for any violation, the Department will consider previous violations of the applicable laws for which the same person or municipality has been found to have been respоnsible in any prior adjudicated proceeding, agreement, consent order, or decree which became final within the previous two-year period. The penalty otherwise assessable for each violation shall be increased by a factor of 5.0% for each previous violation. The total increase in assessment based on history of previous violation shall not еxceed $1,000.
*233 (ii) Each previous violation shall be counted without regard to whether it led to' a civil penalty assessment.
This regulation thus requires consideration of prior violations in assessing future civil penalties.
This Court realizes that had Hamilton obtained a stay, and that is not necessarily a tenable assumption, the instant problem would not have arisen. We note in particular that the DER regulations contain no indication that requesting or obtaining ,a stay is a mandatory .step to presеrve appeal rights. 25 Pa. Code §21.76 provides, “Ta] petition for supersedeas . . . may be filed at any time during the proceeding.” (Emphasis added.) Moreover, a civil penalty can be reduced by swift compliance with a DER order pursuant to 25 Pa.
DER vigorously asserts that this case is identical to Highway Auto Service v. Department of Environmental Resоurces,
Order
Now, June 20,1985, the order of the Environmental Hearing Board, Department of Environmentаl Resources, No. 83-248-G-, dated February 23,-1984 which dismissed Petitioner’s appeal as moot is hereby va
Notes
The Act of May 31, 1945, P.L. 1198 was formerly titled, pursuant to Section 2, the “Bituminous Coal Open Pit Mining Conservation Act.” A subsequent amendment resulted in the Act being retitled the “Surface Mining Conservation and Beclamation Act.” 52 P.S. §1396.2.
Added by Section 13 of the Act of October 10, 1980, P.L. 835.
We need not decide whether the abatement order is an adjudication, agreement, consent order or decree as those terms аre used in the regulation, since, at oral argument, counsel for DER acknowledged that the alleged September, 1983 violation could be considered in applying the penalty escalation provision.
