Al-Ev Construction Corp. v. Ahern Maintenance & Supply Corp.Al-Ev Construction Corp. v. Ahern Maintenance & Supply Corp.
In an action to
Ordered that the judgment is reversed on the law and the facts, with costs, and the plaintiff is awarded the sum of $62,581.09, with interest from March 21, 1984, and the defendant Ahern is awarded the sum of $1; and the matter is remitted to the Supreme Court, Nassau County, for the entry of an appropriate amended judgment.
The plaintiff entered into a contract to perform certain construction work on six buildings at an agreed price for the defendant Ahern. The parties agree that the plaintiff had completed the work on four buildings and the trial court found that the plaintiff had completed 45% of the work on the two remaining buildings when the contract was terminated by the defendant Ahern on March 21, 1984. The contract price, adjusted for change orders deleting certain items, was correctly found to be $461,725. Therefore, the contract price per building was $76,954, as the parties now concede, rather than $79,954 as found by the trial court. Since the plaintiff had completed four buildings and had finished 45% each of two buildings, it should have been credited with completing $377,074.60 worth of work, rather than $391,774. It appears that this error was merely mathematical and clerical rather than judicial in nature and therefore it may be corrected by this court even in the absence of a cross appeal (CPLR 5019 [a]; Herpe v Herpe,
With respect to the defendant Ahern’s counterclaims to
In any event, in computing the defendant Ahern’s damages, the trial court should have taken into consideration the cost the defendant Ahern avoided as a result of not having to complete the contract with the plaintiff (see, Sarnelli v Curzio,