AKZO COATINGS, INCORPORATED, and The O‘Brien Corporation, Plaintiffs-Appellants, v. AIGNER CORP., et al., Defendants-Appellees.
No. 92-3820
United States Court of Appeals, Seventh Circuit
Decided July 11, 1994
Rehearing and Suggestion for Rehearing En Banc Denied Aug. 12, 1994
30 F.3d 761
Argued May 5, 1993.
For the reasons set forth above, the order of the District Court is
AFFIRMED.
U.S. 750, 776, 66 S.Ct. 1239, 1253, 90 L.Ed. 1557 (1946)). See also
* Honorable Walter J. Cummings did not participate in the consideration of this petition.
Bradley D. Jackson, Foley & Lardner, Madison, WI, Pierre C. Talbert (argued), Robert Dupuy, Foley & Lardner, Chicago, IL, for Aigner Corp., American Can Co., Dexter Corp., Duplicolor Products Co., Graham Paint & Varnish Co., Inc., Illinois Bronze Paint Co., Motorola, Inc., Prefinish Metals, Inc., Reynolds Metals Co., S & E Elec. Co., Sherwin Williams Co., Valspar, Inc., Whittaker Corp. and Morton Intern. Inc.
Richard W. Paulen, Barnes & Thornburg, Elkhart, IN, Pierre C. Talbert, Robert Dupuy, Foley & Lardner, Chicago, IL, for Rollcoater.
Catherine R. McCabe, Anne S. Almy, Dept. of Justice, Environmental Defense Section, Washington, DC, for U.S. amicus curiae.
Before EASTERBROOK and ROVNER, Circuit Judges, and WILLIAMS, District Judge.**
ILANA DIAMOND ROVNER, Circuit Judge.
After completing the emergency clean-up work they were ordered to perform at a hazardous waste site in Indiana, Akzo Coatings, Incorporated and The O‘Brien Corporation (collectively, “Akzo“) brought suit for contribution against Aigner Corporation and a number of other companies (collectively, “Aigner“) that allegedly had generated wastes which had been treated or disposed of at that site. The district court granted summary judgment in favor of Aigner, finding that Akzo‘s work was a “matter addressed” by the consent decree that Aigner had entered into with the government. See
I. FACTS
Between 1972 and 1985, more than 200 firms generated hazardous wastes that were sent to various facilities within the Kingsbury Industrial Park in Kingsbury, Indiana comprising what we refer to as the “Fisher-Calo” site. Among these facilities was the “Two-Line Road” facility, where Fisher-Calo Chemicals and Solvents, Incorporated and its predecessor corporations had conducted solvent recycling operations from 1981 until 1985.
In 1988, the federal Environmental Protection Agency (“EPA“) concluded that the wastes stored at the Two-Line Road facility posed an imminent danger of release into the surrounding environment. Exercising the authority granted under section 106 of the
**The Honorable Spencer Williams, of the Northern District of California, sitting by designation.
In May 1990, approximately thirty-five companies that had generated wastes disposed of at the Fisher-Calo site and were thus “potentially responsible parties” (“PRPs“) under CERCLA (see n. 1, supra) initiated efforts to quantify the nature and extent of the liability of any and all PRPs for clean-up of the site and to evaluate the types of work that the EPA and Indiana might order them to perform. Akzo was among the firms that engaged in this effort, and it incurred further costs in doing so. However, Akzo withdrew from the group in February 1991 after concluding that it was not liable for any contamination of the Fisher-Calo site beyond the Two-Line Road facility.
In August 1990, the EPA published a Record of Decision (“ROD“) outlining the work it believed necessary to accomplish a complete decontamination of the site. With respect to the work mandated by the 1988 Order, the ROD stated:
A removal action at the north end of the Two-Line facility is being conducted under a Unilateral Removal Order issued by U.S. EPA. The removal action is being carried out in two phases: Phase I involves the staging of drums for removal during Phase II. Phase II includes the excavation of the contaminated soils and buried tanks and drums located on the north end of the Two-Line Road property. The visibly contaminated soils, tanks and drums will be removed from the north end of the Two-Line Road facility and transported to an appropriate disposal facility. A further removal action is being scoped for the south end of the Two-Line facility. For the purposes of this Record of Decision, it is assumed that all drums, tanks, and containers on the Two-Line Road property requiring remedial action are being addressed by these actions.
ROD Summary at 5 (emphasis supplied). The EPA began to negotiate with the PRPs to implement the clean-up outlined in the ROD, and by the end of the following year, it had finalized an agreement with more than 200 PRPs. The EPA filed suit against these PRPs in late December 1991 and asked the court to approve the proposed consent decree it filed contemporaneously with its complaint. United States v. Accurate Partitions Corp., Civ. No. S91-00646 M (N.D.Ind.). Pursuant to the decree, the settling PRPs agreed to undertake the actions specified by the 1990 ROD and to compensate the EPA for some of the costs it had incurred to date. In late February 1992, following the requisite notice period, see
In 1991, Akzo brought suit against Aigner seeking, inter alia, contribution under CERCLA for the initial clean-up work it had performed at the behest of the EPA as well as the voluntary costs it had incurred in studying the long term clean-up of the site with other PRPs.4 Aigner moved to dismiss the complaint, arguing that the work for which Akzo sought contribution was a “matter addressed” by the Accurate Partitions consent decree and thus Akzo‘s claim was barred by the statute. The district court converted the motion into one for summary judgment in accordance with
II. ANALYSIS
Section 113(f) of CERCLA, added to the statute in 1986, authorizes claims for contribution, subject to the limitation set forth in paragraph (2):
(1) Contribution
Any person may seek contribution from any other person who is liable or potentially liable under section 9607(a) of this title, during or following any civil action under section 9606 of this title or under section 9607(a) of this title.... In resolving contribution claims, the court may allocate response costs among liable parties using such equitable factors as the court determines are appropriate. Nothing in this subsection shall diminish the right of any person to bring an action for contribution in the absence of a civil action under section 9606 or section 9607 of this title.
(2) Settlement
A person who has resolved its liability to the United States or a State in an administrative or judicially approved settlement shall not be liable for claims for contribution regarding matters addressed in the settlement. Such settlement does not discharge any of the other potentially liable persons unless its terms so provide, but it reduces the potential liability of the others by the amount of the settlement.
That Akzo‘s claim is one for contribution we have no doubt. Akzo argues that its suit is really a direct cost recovery action brought under
Akzo suggests that whether its claim is one for contribution may depend on whether the harm done to the Fisher-Calo site is divisible. If, for example, all of Akzo‘s solvents were deposited at Two-Line Road while Aigner‘s were deposited at a different facility, Akzo‘s claim for cleaning up the Two-Line Road site looks less like one for contribution and more like a
Our attention thus turns to whether the contribution that Akzo seeks is for “matters addressed” by the consent decree that Aigner signed. The statute itself does not specify how we are to determine what particular “matters” a consent decree addresses.
Our starting point, naturally, is the consent decree itself. The decree is expansive, not just in terms of its length (sixty-four pages, exclusive of its appendices) but its scope as well. It addresses the Fisher-Calo site as a whole, defining the relevant “Facility” as “the location where treatment, storage, disposal or other placement of hazardous substances was conducted by Fisher-Calo Chemical Company, and those areas where such substances have come to be located.” Consent Decree at 7, ¶ 4. It also incorporates wholesale the far-ranging remedial plan set forth in the EPA‘s 1990 ROD (id. at 5, 11; ¶ 1, 15), a plan which, barring unforeseen problems, would accomplish a complete clean-up of the site at an anticipated cost of more than $30 million. The decree also requires the settling defendants to pay the EPA and the State of Indiana nearly $3.1 million for their costs to date. Id. at 38-39, ¶ 49. Finally, and most significantly from Aigner‘s perspective, the decree includes a covenant not to sue the settling defendants for “covered matters,” which include “any and all claims available to the United States under Sections 106 and 107 of CERCLA ... relating to the Facility, and any and all claims relating to the Facility available to the State under Indiana Code 13-7-8.7 and common law nuisance.” Id. at 46, ¶ 66. Consequently, with certain specific exceptions that are immaterial here (id. at 46-49, ¶¶ 67-71), Aigner has been released of any liability to either Indiana or the United States.
If the covenant not to sue alone were held to be determinative of the scope of contribution protection, the United States would not be free to release settling parties from further litigation with the United States, without unavoidably cutting off all private party claims for response costs.
Amicus Br. at 19. Surely this is not what Congress intended. Rather than give undue weight to a provision of the decree having nothing on its face to do with the claims of non-settling parties, we must look to the decree as a whole to decide whether its provisions encompass the type of activity for which Akzo seeks contribution.7
Other courts have suggested that the “matters addressed” by a consent decree be determined with reference to the particular location, time frame, hazardous substances, and clean-up costs covered by the agreement. United States v. Union Gas Co., 743 F.Supp. 1144, 1154 (E.D.Pa.1990); accord Akzo Coatings of America, Inc. v. American Renovating, 842 F.Supp. 267, 271 (E.D.Mich.1993); United States v. Colorado & E. R.R., 832 F.Supp. 304, 307 (D.Colo.1993); United States v. Pretty Products, Inc., 780 F.Supp. 1488, 1494-95 n. 4 (S.D. Ohio 1991). See also Akzo Coatings, Inc. v. Aigner Corp., 803 F.Supp. at 1384. The United States correctly observes that this should not be treated as an exhaustive list of appropriate considerations, for the relevance of each factor will vary with the facts of the case. Amicus Br. at 17 n. 15. Ultimately, the “matters addressed” by a consent decree must be assessed in a manner consistent with both the reasonable expectations of the signatories and the equitable apportionment of costs that Congress has envisioned. See Transtech, 798 F.Supp. at 1088.8
Settlement negotiations are presumably conducted with affected parties able to participate and work toward a joint clean-up goal. Previous cleanup activities already conducted and paid for by private parties are not likely to be addressed by the government in negotiations of this sort.
Burlington N. R.R. Co., 738 F.Supp. at 1342. Because Akzo‘s preliminary clean-up work is thus so clearly distinct from the long-range remedial matters addressed by the decree, Akzo is entitled to seek contribution from the settling PRPs under
Our conclusion is different with respect to the voluntary costs that Akzo incurred in conjunction with other PRPs in attempting to anticipate the claims that might be asserted against them by the EPA. In contrast to the limited nature of the initial removal work required by the EPA‘s 1988 order, the focus of these efforts was on the long-term remedial action necessary to effect a permanent clean-up of the site. In essence, Akzo and its fellow PRPs were attempting to predict, and perhaps shape, the provisions of the consent decree. In that sense, these efforts were necessarily “matters addressed” by the decree, and in the absence of some indication that they accomplished tasks distinct from what the consent decree called for, claims for contribution based on these efforts are barred by
The flexible, fact-based approach we have used to determine what matters are ad-
Our dissenting colleague takes a different tack, implying that because it lies within the EPA‘s power to draft the release language more narrowly, we should simply take the language in this settlement on its face and construe it broadly to include the clean-up work for which Akzo seeks contribution. Post at 774. There is some allure in that argument, and had Akzo itself been a party to the agreement, we might find it persuasive. But whatever opportunity Akzo may have enjoyed to comment on the consent decree, it had no control over the language ultimately adopted; indeed, neither the EPA, nor Aigner, certainly, had any incentive to take care with Akzo‘s contribution rights.13 Given the sweeping power Congress has given the EPA to extinguish the contribution rights third parties would otherwise enjoy under
Indeed, we are convinced that a contrary outcome would leave firms like Akzo in an
If defendants were permitted to settle with the government for part of the clean-up costs of a site, and then become immune from suit for contribution by private entities who paid for other cleanup costs, it would defeat the policy of CERCLA. Settling PRPs should not be made to pay twice for the same clean-ups, but they also should not get a windfall because they settled.
Akzo Coatings of America, 842 F.Supp. at 271 (emphasis in original).15
The dissent suggests that our rationale is at odds with the Supreme Court‘s recent opinion in McDermott, Inc. v. AmClyde, U.S. -, 114 S.Ct. 1461, 128 L.Ed.2d 148 (1994). Post at 773. We disagree. As the dissent points out, McDermott disavows a rule of liability allocation in admiralty cases that would permit nonsettling parties to seek contribution from parties that have settled. Id. at -, 114 S.Ct. at 1467. We do not begin with the blank slate that the Supreme Court confronted in McDermott, however. See id. at -, 114 S.Ct. at 1464-65. Here, Congress has spoken directly to the question of contribution and permitted non-settling parties to seek contribution for any matter not addressed in the settlement.
Of course, policy considerations of the kind discussed in McDermott to some extent have informed our decision on how broadly to construe the “matters addressed” by the consent decree. Thus, the dissent urges that the decree be accorded a generous sweep that shields Aigner from contribution claims and makes settlement more attractive, while we have construed the decree more narrowly based on the underlying circumstances and avoided the potentially inequitable result that might otherwise befall Akzo. As we see it, McDermott‘s careful balancing of these competing interests lends as much support to our approach as it does to the dissent‘s. In McDermott, the Court was called upon to decide how settlement with some defendants affects the liability of other defendants who take their chances and proceed to trial. In deciding which of three rules to adopt, the Court was motivated in part by a desire to protect settling parties from further liability and thus to foster settlement, - U.S. at -, 114 S.Ct. at 1466-67, but in equal measure by a concern that nonsettling parties not be made to pay damages that exceed their equitable portion of the blame for the injury, id. at -, 114 S.Ct. at 1467-68. In adopting what is referred to as the “proportionate share” rule, the Court served both interests: although the nonsettling party is barred from seeking contribution against a settling party, the nonsettling party‘s liability for damages is limited to its equitable share of the judgment as determined at trial. Id. at -, 114 S.Ct. at 1468-70. Here, we do not have the option of capping Akzo‘s liability in this way. Akzo is not in the position of a party that opts not to settle and instead to take its chances at trial; it was forced to pay out long before settlement was even on the table. Having concluded that the work the EPA ordered Akzo to perform was not a “matter addressed” by the subsequent consent decree, we do not find it inequitable to permit Akzo to seek contribution from Aigner in this situation.
For that reason, we suspect that if we were to bar Akzo from pursuing contribution, parties who found themselves in a similar position in the future would simply exercise the intervention right granted them by section 113(i) and oppose the approval of any consent decree that might be construed to foreclose their right to contribution. See
We have no “disdain” for the contribution protection Congress has bestowed on settling parties in section 113(f)(2). See post at 774. We do, however, think it inconsistent with the legislature‘s intent to give “matters addressed” the broad sweep that the dissent proposes. Even the EPA, which stands to gain from any precedent that makes settlements more attractive, does not embrace that approach. The language of the statute, after all, does not create a blanket prohibition against all suits for contribution; the bar extends only so far as the “matters addressed” by the settlement. When the parties to the settlement have not themselves defined those matters explicitly, we believe it in keeping with congressional intent to do so with an eye to the practicalities of the situation underlying the settlement and the reasonable expectations of the settling parties.
III. CONCLUSION
Based on the totality of the circumstances surrounding the work for which Akzo seeks contribution and the subsequent consent decree between the government and Aigner, we conclude that initial removal work that Akzo was compelled to perform was not a “matter addressed” by the consent decree but that Akzo‘s voluntary efforts toward long-term clean-up were. Akzo is thus entitled to seek contribution from Aigner for the former, but not the latter. The district court‘s judgment against Akzo and in favor of Aigner is therefore AFFIRMED IN PART and REVERSED IN
EASTERBROOK, Circuit Judge, concurring in part and dissenting in part.
The district judge who approved the consent decree concluded that this settlement resolved Aigner‘s liability for the entire Fisher-Calo site, activating the rule in
Section 113(f)(2) provides:
A person who has resolved its liability to the United States or a State in an administrative or judicially approved settlement shall not be liable for claims for contribution regarding matters addressed in the settlement. Such settlement does not discharge any of the other potentially liable persons unless its terms so provide, but it reduces the potential liability of the others by the amount of the settlement.
If the subjects for which Akzo claims contribution are among the “matters addressed in the settlement,” then
How then can it be that Akzo‘s claims are not “matters addressed in the settlement“? The majority answers: everything is subject to “equitable” adjustments. It plucks some language from
There is a second element to the majority‘s argument. The consent decree and the covenant not to sue regulate only the settling parties’ liability to the United States and to Indiana. How, my colleagues ask, can language so limited extinguish claims by strangers? The answer is: Because
Finally, the majority observes that “Akzo‘s work stands apart in kind, context, and time from the work envisioned by the consent decree“. Opinion at 767. True enough as a factual matter; the decree does not require duplicative work. Akzo performed some tasks; Aigner agreed to perform additional tasks. But why should this matter? Unless the first attempt at a cure failed, the settlement always will require work distinct from what has gone before. A project-by-project approach drains most meaning from
Section 113(f)(2) permits the EPA to negotiate global settlements—to promise that if certain firms perform projects A and B, they will not be liable for the costs of projects C and D, which other persons have undertaken. The EPA‘s ability to make such promises gives it a valuable bargaining chip. The agency may demand that polluters do more as a condition of discharging their full responsibility. Freedom from contribution may be the key to a settlement. Consider a simple illustration. Recycling Industries has two plants, East and West. Toxic substances seep from both plants. The EPA identifies two firms that sent toxic substances to Recycling Industries. PRP #1 spends $10 million to clean up the East plant. The EPA approaches PRP #2 with a proposal that it spend $10 million to clean up the West plant. If the “matters addressed” under
Consider, too, the second sentence of
If
Akzo thinks that it has paid more than its share; for all we can tell, the Aigner parties have paid too much and Akzo too little. Finding out who is “really” responsible for how much of the pollution, in order to know who should pay what to whom, could require exhaustive litigation. Section 113(f)(2) enables everyone to avoid such questions. Indeed, the main function of
Statutes that create rights of contribution generally come with limitations, of which
[A] right of contribution against the settling defendant is clearly inferior to [other options], because it discourages settlement and leads to unnecessary ancillary litigation. It discourages settlement, because settlement can only disadvantage the settling defendant. If a defendant makes a favorable settlement, in which it pays less than the amount a court later determines is its share of liability, the other defendant (or defendants) can sue the settling defendant for contribution. The settling defendant thereby loses the benefit of its favorable settlement. In addition, the claim for contribution burdens the courts with additional litigation. The plaintiff can mitigate the adverse effect on settlement by promising to indemnify the settling defendant against contribution,.... This indemnity, while removing the disincentive to settlement, adds yet another potential burden on the courts, an indemnity action between the settling defendant and plaintiff.
McDermott, Inc. v. AmClyde, U.S. -, -, 114 S.Ct. 1461, 1467, 128 L.Ed.2d 148 (1994) (footnote omitted). Notwithstanding the Supreme Court‘s conclusion that contribution actions against parties that have settled are undesirable, the majority today goes out of its way to authorize this device. It evidently disagrees with McDermott‘s view of the effect of requiring settling parties to pay more money in contribution—a position evident not only from the use of the “equity” language in
If the EPA shares the majority‘s disdain for
McDermott shows that if Congress had not enacted
Firms such as Akzo may find their solace in the last part of
