Ahrens & Ott Mfg. Co. v. Moore

131 Tenn. 191 | Tenn. | 1914

Mr. Chief Justice Neil

delivered the opinion of the Court.

This suit was brought upon the following paper:

“Whereas, we, G-. C. Anderson & Company, of Jackson, Tennessee, a firm composed of G-. C. Anderson and S. P. Anderson, are indebted to the Ahrens & Ott Manufacturing Company, in the sum of $1,641.20';
“And whereas, we are desirous of securing payment of said indebtedness to the amount of $1,000;
“And whereas, George Moore & Sons, of Nashville, Tennessee, are indebted to the firm of G. C. Anderson & Company, in excess of the sum of $1,000;
“Now, therefore, we do hereby make over, transfer, and assign to the Ahrens & Ott Manufacturing Company, $1,000 of the indebtedness due us by George Moore & Sons of Náshville, Tennessee, the sum to be applied as a credit on the amount due by us to the Ahrens & Ott Manufacturing Company, and we do hereby authorize and request George Moore & Sons bf Nashville, Tennéssee, to pay to the Ahrens & Ott Manufacturing Company, the sum of $1,000 on the presentation to George Moore & Sons, of Nashville, Tennessee, of this transfer and assignment.
*194“Witness our Rands this tRe 5 th day of June, 1911.”

1. TRe respective counsel in presenting tRis case Rave treated tRe foregoing instrument as an order; tRe complainants’ as an order nonnegotiable; tRe defendants ’ as a negotiable order, in substance an inland bill of exchange. Treating it as an order, counsel Rave discussed the question whether an oral acceptance has been proven. For the present, treating it as an order, and addressing ourselves to the question whether there was an oral acceptance, we find that, according to the weight of the evidence, when the paper was presented to defendants in July or. August, 1911, and payment of the $1,000 demanded, they admitted they owed Gr. 0. Anderson & Co. the sum mentioned, and promised to pay it as soon as they could obtain a settlement from the government of the United States on the contract under which the alleged indebtedness arose; defendants being the original contractors, and Gr. C. Anderson & Co. subcontractors, under contract with defendants. If the instrument be an order, we think the facts stated would show a verbal acceptance.

2. It is insisted, as matter of law, that the acceptance, being verbal, was not binding. This contention is based on the postulate that the instrument is a negotiable inland bill of exchange, and that, under our negotiable instrument law, the acceptance, to be binding, must be in writing. Acts of 1899, ch. 94, section 132. But under subsection 4 of section 1 of the same act, an instrument, to be negotiable, “must be payable to order or to bearer.” The instrument sued on is *195not so payable, and therefore does not fall within the negotiable instruments law. Gilley v. Harrell, 118 Tenn., 122, 101 S. W., 424. A nonnegotiable order may be accepted verbally. Montague v. Myers, 58 Texm., (11 Heisk.), 539.

3. It may be fairly inferred, from the language of the instrument sued on, that the intention was to appropriate some special fund in the hands of the defendant, and this fact clearly appears from the oral evidence submitted by both parties. , Defendants had been employed by the United States government to erect a government building in the. city of Jackson. G. C. Anderson & Co. were subcontractors. The $1,000 which is the subject of the order was expected to be paid out of the money which would be due to Anderson & Co. under that contract. When the order was given and accepted, Anderson & Co. had not yet completed their work. Under the terms of defendants’ contract with the government, they were compelled to pay for all materials and for all work. Anderson & Co. were under a similar contract with defendants. When Anderson & Co. completed their subcontract, nothing was due them, because, after the order was given and accepted, it became necessary for defendants to pay for other material essential to fill the subcontract of Anderson & Co., so that, at the close of the work of the- latter, they were indebted to defendants. The latter paid nothing to Anderson & Co. personally after the acceptance of the order, but *196only for such things as were necessary to complete the work of Anderson & Co., pursuant to their contract.

Under these facts it is insisted by defendants that they are not liable to pay complainants anything on the order. We think this contention is sound. In the case of Montague v. Myers, supra, the order was drawn on Montague, requesting him to pay $200 “out of the twenty-five per cent, back pay for foundation at old Crutchfield grounds,” and was signed W. A. Howard & Co. The latter soon after absconded without completing the work, but Montague hired hands and finished it. It seems that Montague accepted the order generally, though the terms of the acceptance are not stated in the opinion of the court. The court said:

“We think the facts show a verbal acceptance; but this order was drawn on a particular fund, and Montague was only bound to pay it in the event there was such fund.”

It was held in that case, however, that inasmuch as Montague did not insist on a forfeiture of the back pay due to Howard & Co. by reason of their failure to complete the contract, but himself finished the work, and as on this basis there was found to be due Howard & Co. enough to pay the order, it was his legal duty to pay it. Other eases in point are Jenkins v. Wells, 90 Mich., 515, 51 N. W., 636, and Beardsley v. Cook, 143 N. Y., 144, 38 N. E., 109.

In the first of these cases it appeared that Mason & Co. had agreed to finish the drilling of a salt well for *197"Wells. They gave an order to Jenldns on Wells for a certain sum of money. The order conclnded:

‘ ‘ Said money to be paid when the undersigned shall have reached the depth of 1,800 feet in the drilling aforesaid, or as soon as salt be found therein at any time before said depth shall have been reached.”

The acceptance was:

“I hereby accept the foregoing order; the depth to he 1,850 feet, instead of 1,800 as above, and subject to all the conditions expressed in my contract with said Masons. ’ ’

The order was dated August 9,1886, and Mason quit work on the 16th or 18th. Wells had to complete the work at his own expense. It was held that he was entitled to credit for what it cost him to complete the work. The case does not show what were the terms of the contract referred to in the acceptance.

In the second case it appeared that Cook had employed certain builders to construct some houses for him. The builders entered upon the performance of their contract, and on the 11th of December, 1890, a considerable part of the work had been done, when the plaintiff Beardsley procured from the builders a written order upon defendant Cook in which they requested him to retain and pay to Beardsley from the last payment to he made to them under their contract the sum of $1,175, according to the terms of their contract with the plaintiff. Cook wrote across the face of the order his acceptance. An action subsequently brought on the accepted order. The builders never completed the *198liouses. There was a clause in the building contract to the effect that in case the builders failed to complete the houses, and furnish the necessary materials and labor for that purpose, the defendants might do it, and deduct the expense of completion from any sums unpaid upon the contract. Cook did complete the houses under this provision. The court held that Cook was entitled to credit for the costs of completion, and that only the balance that might be left in his hands would be liable to Beardsley.

4. In what has been said we have treated the instrument sued on as an order rather than as an assignment. We are of the opinion, however, that under a proper construction the instrument sued on is really an assignment. It not only uses appropriate words to assign the indebtedness, but in the last line it is called an assignment. It is not even addressed to George Moore & Sons, although in the body of it a request is made that the latter pay the $1,000. It also appears from the paper that it was taken for purpose of security. The assignment being for the security or payment of a pre-existing debt, and the instrument being also nonnegotiable, it would, in any event, be open to offsets, or counterclaims, in favor of George - Moore & Sons, arising out of the nature of the indebtedness as above indicated. Nolen Bros. Lumber Co. v. Dudley Lumber Co., 128 Tenn., 11, 156 S. W., 465, Ann. Cas., 1914D, 744. It should be further remarked that shortly after receiving this paper the complainants, treating it as a mere assignment, gave the usual *199notice to George Moore & Sons, to the effect that the assignment had been made to them. In addition to this complainants deny that they ever demanded a formal acceptance on the part of defendants. What transpired, according to the weight of the evidence, was: Two representatives of complainants called on defendants and had a talk with Mr. Charles C. Moore, a member of the firm. The chief one of these witnesses and the strongest in his statements testified:

“Mr. Moore stated to ns that the assignment was all right, and that the same wonld be .paid as soon as he could get a settlement from the government for the work that was done on their contract on the post office at Jackson, Tenn. I asked Mr. Moore particularly if he owed George C. Anderson & • Co. $1,000', and he stated that he owed them something more than $1,000, and that he was just simply waiting for the work to be approved by the inspector that the government had sent to Jackson. . . . He stated positively he would pay it as soon as he could get a settlement with the government.”

The necessity requiring payment of other sums in order to complete the contract of G. C. Anderson & Co. developed after this conversation with the representatives of complainants, as a result of which there was nothing left or owing with which to pay the sum assigned.

5. The promise to pay, quoted, was not binding because not supported by any consideration.

6. The facts do not make out a case of novation.

*200We are of the opinion that the decree of the court of civil appeals, in favor of defendants, should, on the grounds we have stated, be affirmed, with costs.