74 P. 41 | Cal. | 1903
This is an action to enforce certain laborers' liens for work done upon a tunnel for the purpose of developing water. The court made an order consolidating *502 the two cases, and judgment passed for plaintiffs. Defendants moved for a new trial, which was denied, and they appeal from the judgment and from the order.
It appears that on May 3, 1900, defendants the Whites were the owners of the premises sought to be charged with the liens, and on that day executed an option to purchase the said land, together with certain other land, to defendant Harwood. This option was for sixty days, — to wit, until July 3, 1900. There was appended to it a blank for an extension, but is was never filed, and the option made no provision for its extension. On June 7, 1900, the Whites executed a deed of the land in question and some other lands to defendant Harwood, which was deposited in escrow, and to be delivered only upon certain written conditions which accompanied the escrow as part thereof. On October 10, 1900, this escrow deed was recalled and canceled by agreement, and the Whites conveyed the premises to Harwood, the latter executing to the former his note and mortgage as security for the purchase price. Harwood entered into possession of the land and went to work to develop water, under the option while it existed, and later under the escrow deed, and the subsequent arrangement. It was provided in the option that he should "work all the men practicable for water development," and "certainly work himself and two men." It was also provided "that the undersigned [the Whites] shall in no manner be held responsible or liable, nor shall any portion of said premises be held liable for any material furnished or labor performed, or caused to be furnished or performed by said J.H. Harwood in his efforts to develop water upon said premises." Plaintiff Ah Louis was employed by Harwood on July 9th, and plaintiff Geung Hong on August 15, 1900, to work for the compensation of forty dollars per month each, from which dates until October 19th following the lien is claimed. All the land in question was admitted to be convenient and necessary for the use and occupation of the tunnel.
1. It is claimed that the evidence does not justify the enforcement of a lien for the reason that the evidence does not show either one of the claimants to have been employed directly to labor upon the tunnel in question. The point urged *503
is thus stated: "A laborer in the course of a general employment who may happen to work upon a structure or excavation which ordinarily would be subject to lien, had he been employed directly for such purpose, will not be entitled to a lien unless he does labor in pursuance of such direct employment." This position is taken in analogy to the rule laid down as to furnishing material for the structure, in Roebling's Sons v. BearValley etc. Co.,
2. It is contended that the notices of lien are insufficient, for the reason, — 1. That two notices of lien are set forth in each notice; 2. That the names of the owners of the property are not stated as required by law; and 3. That plaintiffs were employed by the month. It is claimed that there should have been a separate lien filed against the Whites under section 1192 of the Code of Civil Procedure for the claim accruing prior to October 10th, when they conveyed absolutely to Harwood, and another lien against Harwood, as owner, under section 1183 of the Code of Civil Procedure. The notice of lien stated "that all the times herein mentioned, Stillman C. White, Myra H. White, and James H. Harwood were and now are the names of the owners, and reputed owners of said premises, and said James H. Harwood caused said tunnel to be . . . . constructed," etc. It was held inCorbett v. Chambers,
3. It is further contended that the land is not subject to lien because of the contract or option under which Harwood went into possession. This contention is based on the provision of the option that the Whites were not to be held liable, nor was the land for any material furnished or labor performed, and because of the further provision that Harwood was to furnish at his own cost all material and labor. Cases are cited in other jurisdictions which, it is claimed, sustain this proposition. Such is not the law in this state. The owner of land cannot protect it from the statutory liens, except he give the statutory notice or some notice equivalent thereto. An agreement with a lessee or conditional purchaser that improvements must be at his cost, and that the lessor or seller will not be liable for labor or materials, will not alone satisfy the statute or protect the land from the lien. The Whites knew of the proposed work, for the option expressly provided that the purpose was to enable Harwood to develop water on the land. (Hines v. Miller,
4. The court found generally that all the allegations of the complaint are true, and all the denials of the answer untrue. It was alleged in each case as follows: "Plaintiff is informed, and thereon alleges, that seventy-five dollars is a reasonable attorney's fee for plaintiff's attorney in this case in said superior court, and plaintiff has incurred the obligation to pay an attorney fee for plaintiff's attorney herein."
It is claimed that the finding is insufficient to support the judgment, because there being no direct allegation, it simply means that plaintiffs had the information. Section 1195 of the Code of Civil Procedure says that "The court must allow . . . reasonable attorneys' fees in the superior and supreme courts." No allegation as to attorneys' fees was necessary in the complaint and no finding was necessary. (Clancy v. Plover,
It is advised that the judgment and order be affirmed.
Gray, C., and Haynes, C., concurred.
For the reasons given in the foregoing opinion the judgment and order are affirmed.
Shaw, J., Angellotti, J., Van Dyke, J.