Aguilera v. Pistilli Construction & Development Corp.Aguilera v. Pistilli Construction & Development Corp.
Ordered that the order dated February 8, 2008 is modified, on the law, by deleting the provision thereof which, upon reargument, adhered to so much of the original determination in the order dated July 19, 2007, as denied that branch of the motion of the defendant Tex Development Co., LLC, which was for summary judgment dismissing the
The defendant Tex Development Co., LLC (hereinafter Tex), owned a warehouse that it was converting into residential apartment units. Tex retained the defendant Pistilli Construction & Development Corp. (hereinafter Pistilli) to act as the general contractor for the conversion and renovation. Pistilli subcontracted with Faro Construction Group, Inc. (hereinafter Faro), to perform carpentry work on the building. The plaintiff was employed by Faro as a carpenter.
The plaintiff allegedly slipped on debris while walking down a staircase from the work site on the fourth floor to a lower level. The plaintiff commenced this action against Tex, Pistilli, and Faro, alleging causes of action based, inter alia, on common-law negligence and
The Supreme Court properly denied those branches of Tex’s motion which were for summary judgment dismissing the causes of action based on common-law negligence and
The plaintiff’s cause of action pursuant to
However, Tex established prima facie that