This is an agency case. The issue on appeal is whether the trial court erred in failing to submit to the jury the issue of whether the alleged agent acted within the scope and course of his alleged agency with the defendant. We hold that it did so err and that it therefore correctly granted the defendant’s motion for a new trial. Accordingly, we affirm. The issue on cross-appeal is whether the trial court should have granted the defendant’s motion for judgment notwithstanding the verdict in that, as a matter of law, the alleged agent lacked the authority to bind the defendant. We hold that a reasonable juror could have found that the alleged agent had apparent authority sufficient to bind the defendant. Accordingly, we affirm.
Facts and Procedural Background 1
Appellant-Respondent Agri Process Innovations, Inc. (“Agri Process”) entered into an agreement with Alen Hoover for installing ceramic insulation on bio-diesel fuel tanks. The only aspect of the contract that is relevant to this appeal is whether Respondent-Appellant Envirotrol, Inc. (“Envirotrol”) was bound by the agreement.
Representatives of Agri Process testified that, in negotiating the contract, Hoover held himself out as a representative of Envirotrol. Hoover’s business cards stat *385 ed that he was an employee of Envirotrol. Envirotrol’s website listed Hoover as a technical consultant. When Agri Process began having problems with the insulation, it contacted Envirotrol, and Envirotrol’s president travelled to the site to review the problem. Envirotrol’s president stated that Envirotrol would correct the problem. Envirotrol paid Hoover $136,593.81 in 2006, the year before he entered into the contract with Agri Process.
Hoover himself testified that he had not been representing Envirotrol in the subject transaction. Rather, he testified that he had represented a company called Thermal Corrosion Solutions and that Agri Process knew that Thermal Corrosion Solutions was the contracting party. Thermal Corrosion Solutions is a sole proprietorship, and Hoover is its owner, operator, and sole employee. Thermal Corrosion Solutions subcontracted the work on Agri Process’s tanks to a separate company called Mid South Thermal Coatings. Chris Bennett of Mid South Thermal Coatings purchased product from Enviro-trol to use on the Agri Process job. Hoover directed Agri Process to submit payment for the project to Thermal Corrosion Solutions, which Agri Process did. Agri Process’s personnel testified that they believed that Thermal Corrosion Solutions was affiliated with Envirotrol.
Agri Process alleged that only three instead of eight coats of insulation were installed on the tanks, resulting in moisture being trapped and inconsistency in the thickness of the insulation. The defective application of the insulation allegedly caused Agri Process damages. Agri Process sued Envirotrol for breach of contract and pled that Hoover, in entering into and performing under the contract, had acted as Envirotrol’s agent.
In the course of discovery, Envirotrol propounded the following request for admission to Agri Process: “The contract upon which Plaintiffs claim is based contained no promise by Envirotrol.” Agri Process responded: “Admit.”
The circuit court held a jury trial on Agri Process’s claims. Over Envirotrol’s objection, the court submitted the following instruction to the jury:
Your verdict must be for Agri Process Innovation, Inc. if you believe:
First, Agri Process Innovation, Inc. and Envirotrol, Inc. entered into an agreement ... and
Second, Agri Process Innovation, Inc. performed its agreement, and
Third, Envirotrol, Inc. failed to perform its agreement, and
Fourth Agri Process Innovation, Inc. was thereby damaged.
Envirotrol objected to the instruction because it did not require the jury to find that Hoover acted within the scope and course of his agency with Envirotrol. The trial court overruled the objection, stating that “it’s the discretion of the Court to make the apparent agency [instruction] part of and include it on the verdict director or not.” The court stated further that, if it included within the verdict director a required finding that Hoover acted as the agent of Envirotrol, it would be “adding additional elements into the burden of proof placed upon the plaintiff which are simply not required by Missouri law.”
The court did, however, submit to the jury an instruction defining “scope and course of agency”:
Acts of Allen Hoover were within the “scope and course of agency” as that phrase is used in these instructions .if:
First, the conduct of Allen Hoover was such that an ordinarily careful person would believe that Allen Hoover had *386 authority to perform such acts on behalf of Envirotrol, Inc., and
Second, Envirotrol, Inc. knew or had reason to know of such conduct and allowed such conduct, and
Third, Agri Process Innovations, Inc. reasonably relied on such conduct of Allen Hoover at the time of the transaction mentioned in the evidence.
The jury returned a verdict for Agri Process. Envirotrol filed a motion for a new trial, or, in the alternative, for judgment notwithstanding the verdict. In its motion for a new trial, Envirotrol argued that the court improperly submitted the verdict director in that the instruction did not require a finding that Hoover acted within the scope and course of his agency with Envirotrol. In its motion for judgment notwithstanding the verdict, Enviro-trol argued that a verdict should be entered in its favor because Agri Process judicially admitted that Envirotrol had made no promise.
In its judgment, the trial court granted the motion for a new trial and denied (sub silentio) the motion for judgment notwithstanding the verdict. 2 Agri Process appeals the former part of the judgment; Envirotrol cross-appeals the latter.
Standard of Review
“When a motion for new trial is granted because of prejudicial error in the instructions, the question presented on appeal is [a] question of law.”
Luyties Pharmacol Co. v. Frederic Co.,
A case may not be submitted unless each and every fact essential to liability is predicated upon legal and substantial evidence. In determining whether the evidence was sufficient to support the jury’s verdict, the evidence is viewed in the light most favorable to the result reached by the jury, giving the plaintiff the benefit of all reasonable inferences and disregarding evidence and inferences that conflict with that verdict. [An appellate court] will reverse the jury’s verdict for insufficient evidence only where there is a complete absence of probative fact to support the jury’s conclusion. Accordingly, a motion for JNOV is properly granted when the motion identifies at least one element of the plaintiffs case that is not supported by the evidence.
Clevenger,
Legal Analysis
I. Agri Process’s Appeal
Agri Process argues that the trial court erred in granting the motion for a new trial in that the verdict director was sufficient to submit all necessary issues for the jury to decide. We disagree.
*387
“An instruction authorizing a verdict must require a finding of all ultimate facts necessary to sustain the verdict except those which have been unmis-tak[ab]ly conceded by both parties.”
Young v. Kan. City Power & Light Co.,
a. The erroneous instruction
Here, whether Hoover acted within the scope and course of his alleged agency with Envirotrol was an “ultimate faet[] necessary to sustain the verdict.”
See Young,
A principal can be held liable for breach of contract when its agent entered into the contract within the scope of his apparent authority.
3
Alexander v. Chandler,
(1) the [apparent] principal manifested his consent to the exercise of such authority or knowingly permitted the [apparent] agent to assume the exercise of such authority; (2) the person relying on this exercise of authority knew of the facts and, acting in good faith, had reason to believe, and actually believed, the agent possessed such authority; and (3) the person relying on the appearance of authority changed his position and will be injured or suffer loss if the transaction executed by the agent does not bind the principal.
Id.
(quoting
Bost v. Clark,
*388
Moreover, this is not a case where there was “no serious dispute” regarding the agency issue, nor is it one where the trial court could have properly decided the issue as a matter of law.
Cf. Rice,
The trial court did not submit the agency issue as required by Missouri law. Missouri Approved Instruction 18.01 provides that, when agency is in issue, the verdict director shall be modified to submit to the jury the question of whether the agent acted within the “scope and course of his [agency].” Though the example given by MAI 18.01 relates to a negligence case, the instruction also applies to a breach of contract case when agency is in issue.
Rice,
Here, the jury instructions met one of these requirements but not both. The term “scope and course of agency” was defined in a separate instruction, but the question of
whether
Hoover acted within the scope and course of his alleged agency with Envirotrol was not actually submitted to the jury in the verdict director. Defining a necessary term does not constitute submission of a necessary issue,
Galemore,
Since the trial court failed to follow MAI 18.01, we presume that the error
*389
caused prejudice.
See Rice,
b. Agri Process’s attempts to show that prejudice did not occur
Agri Process argues that the trial court’s error did not cause prejudice. First, it argues that the law was clear to the jurors because the court defined “scope and course of agency” in a separate instruction. But the court in
Galemore
specifically addressed that issue. There, the trial court submitted an instruction that defined “scope and course of employment,” but it did not mention that term in the verdict director, nor did it otherwise require the jury to actually find that the alleged employee had acted in the “scope and course of [his] employment.”
Gale-more,
[T]his recognition of the issue by the giving of [the definitional] instruction ... did not constitute submission of it. For [the definitional] instruction ... did nothing more than define “scope and course of employment,” a term not found in any other instruction, and thus was a meaningless exercise in futility. The issue as to whether or not [the alleged employee] was acting within the scope and course of his employment ... should have been submitted in plaintiffs verdict-directing instruction in a manner compatible with that outlined in MAI 18.01, followed by MAI 13.05 defining “scope and course of employment” as that term is used “in these instructions.”
Id.
Thus, the inclusion of the definitional instruction in this case did not cure the error, nor does it rebut the presumption of prejudice. The jury was told what “scope and course of agency” means “when used in these instructions,” but then the instructions never used those terms. Without including the defined terms in a verdict director, it was pointless to define them. That is, the jurors knew what “scope and course of agency” meant but they were not asked to do anything with that knowledge. Envirotrol was entitled to a factual finding on the agency issue, and the trial court prejudiced Envirotrol by not requiring the jury to make one. See id.
Next, Agri Process argues that the law was clear to the jurors because Envirotrol’s lawyer “was allowed to explain the law during closing arguments, several times.” We rejected a similar argument in
Rice,
The trial court erred in failing to include a modification to the verdict director based on MAI 18.01, and Agri Process has not rebutted the presumption of prejudice that applies to such errors. Accordingly, the trial court did not err in granting Enviro-trol’s motion for a new trial. Agri Process’s point on appeal is denied.
II. Envirotrol’s Cross-Appeal
Envirotrol argues that the trial court erred in denying its motion for judgment notwithstanding the verdict in that Agri Process judicially admitted that the subject contract contained no promise from Envirotrol. We disagree.
Envirotrol is apparently arguing that no contract existed between it and Agri Process as a matter of law. For a contract to exist, there must be an offer, an acceptance, and consideration.
Walker v. Rogers,
An offer is “ ‘the manifestation of willingness to enter into a bargain, so made as to justify another person in understanding that his assent to that bargain is invited and will conclude it.’”
Vollcer Court,
However, conti’ary to Envirotrol’s argument, the trial court was not inquired to grant judgment notwithstanding the verdict on the basis of Agri Process’s “judicial admission” that the subject contract contained no promise from Enviroti'ol. In response to a request for admission, Agri Pi'ocess admitted that “[t]he contract upon which [its] claim is based contained no promise by Envirotrol” (“the l-esponse” or “the admission”). Envirotrol apparently believes that the effect of the response was to admit that no one — including Hoover— made a promise on Envirotrol’s behalf. But the admission is not neeessai'ily so broad. The admission could mean that Envirotrol itself — for example, by its officer's or directors — made no promise but that Hoover — as Enviroti'ol’s agent — did.
A party’s response to a i'e-quest for admission conclusively establishes a matter admitted unless the court permits withdrawal or amendment of the response. Rule 59.01(b). However, when the request or the response is fairly susceptible to more than one interpretation, the trial court may allow each party to argue its intei'pretation to the jury as op
*391
posed to giving conclusive effect to one of the interpretations.
See Rolscreen Co. v. Pella Prods, of St. Louis, Inc.,
Here, in response to Envirotrol’s argument on this point, the trial court stated:
I would say that [counsel for Agri Process] can probably explain that argument away in about 15 seconds.... That is a legal argument which has a different point of perspective that can be just as adequately expressed as yours, and I do not find that persuasive enough [to grant the motion for directed verdict].
The court then permitted Envirotrol to argue its interpretation of the response to the jury.
The trial court did not abuse its discretion in so ruling. As noted above, the request for admission is susceptible to more than one interpretation. It is true that, as a corporation, Envirotrol can only act through its agents,
see, e.g., Standard Meat Co. v. Taco Kid of Springfield, Inc.,
Although it did not include the argument in its point on appeal, Envirotrol also argues that Agri Process adduced insufficient evidence to prove the elements of a contract. This argument has not been preserved,
see
Rule 84.04(e), and, in any case, it is meritless. An agent invested with apparent authority has the power to bind the apparent principal to a contract.
Alexander,
Since the trial court was not required to give conclusive effect to Envirotrol’s interpretation of the response, and since there was sufficient evidence that Hoover acted *392 with apparent authority sufficient to bind Envirotrol, we deny Envirotrol’s point on cross-appeal.
Conclusion
Both parties were entitled to a submission of the agency issue. Therefore, the trial court erred neither in granting the motion for a new trial nor in denying the motion for judgment notwithstanding the verdict. Accordingly, we affirm.
JOSEPH M. ELLIS, Judge, and VICTOR C. HOWARD, Judge, concur.
Notes
. "When presented with the grant of a new trial following a plaintiff's verdict, [courts of appeal] view the evidence and all inferences therefrom in the light most favorable to the plaintiff.”
Lindquist v. Scott Radiological Grp., Inc.,
. By not ruling on the motion for judgment notwithstanding the verdict within ninety days after the last authorized post-trial motion was filed, the trial court denied it. Rule 78.06. This is not a case where the post-trial motion requires a ruling on the weight of the evidence, and therefore we need not remand for an explicit ruling on the motion for judgment notwithstanding the verdict.
Cf. Taylor v. F.W. Woolworth Co.,
. An agent can also bind his principal when he acts pursuant to actual authority (whether it be express or implied),
Bus. Bank of St. Louis v. Old Republic Nat’l Title Ins. Co.,
. Envirotrol presented no affirmative evidence but rather elicited evidence through cross-examination.
. For example, Agri Process could have made Envirotrol an offer that invited acceptance by actual performance rather than by a promise of performance. See Restatement (Second) of Contracts § 50 (1981).
. Payment was actually made to Thermal Corrosion Solutions, but, given that that entity was owned and operated by Hoover, a jury could reasonably have found that Hoover, and by extension his alleged principal Envirotrol, benefited from such payments.
