227 Ct. Cl. 730 | Ct. Cl. | 1981
This construction contract case is before the court on cross-motions for summary judgment, including review of the granting by the Board of the defendant’s counterclaim for $21,840.00. Plaintiff contracted with defendant to furnish and install a heating, ventilating and air conditioning system in the Government’s V.A. hospital in Bronx, New York. A dispute over interpretation of the contract’s specifications ensued and plaintiff now seeks Wunderlich Act review, 41 U.S.C. §§ 321, 322 (1976), of a decision of the Veterans Administration Contract Appeals Board
HH
Under Contract No. V 101C-256, dated January 9, 1976, AFGO agreed to install a heating, ventilating and air conditioning system in the Veterans Administration Hospital in Bronx, New York. The contract required AFGO to furnish and install six large underground fuel tanks including trench earthwork and rock excavation. During job performance, a disagreement arose concerning whether AFGO was obligated to excavate the holes for the fuel tanks. The contracting officer decided that AFGO was required to perform the work. Plaintiff thereafter performed accordingly and sought additional compensation therefor, which was denied by the contracting officer.
On appeal before the Board, AFGO contended that its obligation to excavate was limited by clause 1-4A
Before this court plaintiff contends its interpretation of the contract was reasonable and, therefore, under the rule of contra proferentem, plaintiff was under no duty to seek clarification. Under Wunderlich standards, we uphold the Board’s decision.
There is ample evidence in the record to support the Board’s conclusion. AFGO’s reliance on the rule of contra proferentem is misplaced. That rule is well established and
As the court in Beacon Construction Co. v. United States, 161 Ct.Cl. 1, 6-7, 314 F.2d 501, 504 (1963) said:
The bidder who is on notice of an incipient problem but neglects to solve it as he is directed to do by this form of contractual preventive-hygiene, cannot rely on the principle that ambiguities in contracts written by the Government are held against the drafter. . . . Even more, the bidder in such a case is under an affirmative obligation. He "should call attention to an obvious omission in a specification, and make certain that the omission was deliberate, if he intends to take advantage of it.” Ring Construction Corp. v. United States, 142 Ct.Cl. 731, 734, 162 F. Supp. 190, 192, (1958).
See also Space Corp. v. United States, 200 Ct.Cl. 1, 5, 470 F.2d 536, 538-39 (1972).
II.
We next discuss the Government’s counterclaim
The record is clear that the parties entered into a contract which, through the Payment Clause,
However, the issue of quantum remains. Plaintiff never appealed that determination pursuant to the Disputes Clause and is now time-barred from doing so. See 41 C.F.R. 8-1.318-1(e) (1978). Defendant argues, therefore, that the contracting officer’s decision as to quantum should now be final since plaintiff failed to exhaust its administrative remedies as to that issue. We agree with defendant. AFGO was told of the amount it owed, yet AFGO sat on its rights. It has given us no reason for its failure to appeal the
Accordingly, after consideration of the record and submissions of the parties, without oral argument of counsel, plaintiffs motion for summary judgment is denied. Defendant’s motion for summary judgment is granted. Plaintiffs petition is dismissed.
"Section 1 (Earthwork)
1-4 Scope:
A. trench earthwork includes all trench work required by the drawings and specifications.”
Defendant’s counterclaim before the Board was confined to the issue of entitlement. Subsequent to the Board’s decision, the contracting officer calculated the quantum to be $21,840, and withheld that amount from payments due AFGO. Plaintiff never appealed that quantum determination to the Board.
payment: The contract price and time will be adjusted for overruns or underruns at the unit price shown herein in accordance with [the Differing Site Conditions clause]. A. UNIT PRICES: the bidder agrees to the following unit prices for rock excavation over or under the estimated quantity of rock excavation noted on the drawings regardless of its location on the site and the depth of excavation required. Unit prices are net and include resulting change in quantity of earth excavations, as well as all labor, materials, overhead, supervision, insurance, profit and taxes. Trench Rock Excavation; ADD $185.00 per cubic yard overrun. Trench Rock Excavation; DEDUCT $130.00 per cubic yard underrun.
GENERAL PROVISIONS (SF 23-A, Oct. 1969 Ed.)
4. differing site conditions (a) The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract. . . The Contracting Officer shall promptly investigate the conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly.
With reference to the counterclaim for $21,840, it is our understanding that the money was withheld by the Government and remains rightfully in its possession.