112 Mich. 560 | Mich. | 1897
The plaintiff constructed a sewer under a contract between himself and the city of Detroit. The charter of the city in force when the contract was made provided:
“No contract shall be let or entered into for the construction of any public work, or for any work to be done, * * * until a tax or assessment has been levied to defray the cost and expense of the same, and no such work * * * shall be paid for, or contracted to be paid for, except out of the proceeds of the tax or the assessment thus levied.”
‘ ‘ And it is expressly agreed by and between the parties hereto that the said city of Detroit, the party of the second part, shall in no event be liable to the party of the first part for any part or portion of the cost of the labor and materials, and that the said party of the first part shall never ask for or receive, from the city any part or portion thereof, but shall depend entirely upon such special assessments for their compensation.”
An assessment was made upon adjoining premises, and, after the collection of a portion of the sum assessed, an injunction bill was filed, and an injunction issued, to restrain further steps to collect the remainder, and apparently the city authorities have no confidence in their authority to collect the same; and, although no decree has been taken, the restraining order is in force, and no attempt has been made to bring the litigation to a close, or to make another assessment. The ground of the suit to enjoin the collection appears to be that the city authorities constructed a new sewer under a resolution to reconstruct an old one. Whether or not the assessment was void has not been decided, and we cannot, upon this record, determine that question, or whether, if so, a new assessment might be lawfully made. As already seen, the charter expressly forbids that work shall be paid for except out of the proceeds of the assessment. A special agreement to do otherwise would be null and void, yet we are asked to say that the law will imply a promise which will be binding. In other words, the city shall not have power to contract to pay for this sewer except from the proceeds of a special assessment, yet if, for any reason, it does not pay for it from such assessment, then it shall be liable generally for the work done. This would enable the council to evade the organic law, and accomplish by indirection what it cannot do directly. All contracting with the city are bound to know that there is this limitation upon its power. Whatever other remedy such persons may have, they cannot compel the city to do
The judgment must be reversed, and a new trial ordered.