Aetna Casualty & Surety Co. v. United StatesAetna Casualty & Surety Co. v. United States
delivered the opinion of the court:
This case, before the court on the parties’ cross-motions for summary judgment, involves a dispute between a Miller
The facts essential to a decision are not in dispute. In 1968 and 1969, the United States Postal Service (USPS), acting through its predecessor, the United States Post Office Departmеnt (POD) ,
In May 1911, upon learning that Corrigan had failed to meet its obligations to subcontractors and materialmen on those contracts, Aetna notified the POD of Corrigan’s default and advised the POD that, by virtue of an assignment of the contract funds and Aetna’s equitable rights as surety, Aetna was entitled to any contract funds remaining in the hands of the Government. As payment bond surety, Aetna has paid debts owed by Corrigan to the subcontractоrs and materialmen on eight of the contracts in the amount of $234,704.36.
The primary offsets asserted by the Government arise out of a contract (No. 70-1-00698) that the POD awarded Corrigan on December 30, 1969, for the construction and installation of a mail handling system in the Milwaukee, Wisconsin, pоst office. Although Corrigan was required to file payment and performance bonds within 10 days from the award of that contract, none were ever filed. The POD, however, did nоt discover Corrigan’s failure to file the bonds until April 1971. Thereafter, the POD determined that Corrigan’s failure was willful and on May 10, 1971, terminated the contract.
A portion of the work on thе Milwaukee contract was subcontracted by Corrigan to the Kennedy Electric Company (Kennedy). On March 3, 1972, Kennedy brought suit against the USPS in the United States District Court for the District of Colorado to recover amounts due for work and materials provided Corrigan.
As its first offset, defendant claims that it has the right to offset the Kennedy Electric judgment against the unpaid contraсt balances. Plaintiff, on the other hand, contends that the Government’s failure to require Corrigan to file payment and performance bonds rendered the Milwaukee contract illegal and, therefore, that any costs incurred by the Government thereunder cannot be claimed as an offset.
We l’eject plaintiff’s contention for two reasons. In the first place, we are convinced that the Government’s failure to obtain the required bond did not render the contract illegal. The better view, and the one which we adopt, is that upon the Government’s acceptance of Corrigan’s bid, a valid contract came into existence and that by failing to furnish the bonds within the required period of time, Corrigan breached an existing and enforceable contract. United States v. Pennington,
Secondly, even assuming the contract was illegal, we are of the opinion that defendant nevertheless is entitled to the offset which it now claims. The practical effect of the Kennedy Electric judgment was to require the Government to utilize its own funds to satisfy Corrigan’s obligation to its subcontractor, Kennedy. As a result of its having paid Corri-gan’s obligation, the Government clearly has a claim against Corrigan that must bе satisfied. Since Corrigan is now bankrupt, the only source of funds available from which defendant is able to satisfy this obligation is the contract funds it now holds.
It is a well-settled principle that the Government has inherent authority to recover sums illegally or erroneously paid, and that it cannot be estopped from doing so by the mistakes of its offiсers or agents. See United States v. Wurts,
[W]hen a payment is erroneously or illegally made it is in direct violation of article IV, section 3, clause 2, of the Constitution, [case citation.] Under these circumstances it is not only lawful but the duty of the Government to sue for a ref und thereof * * *.
Defendant’s contention that, under the circumstances of this case, it is entitled tо recover the losses that it has incurred in satisfying the Kennedy Electric judgment from the funds earned by Corrigan on its other contracts with the Government, is clearly consistent with these cogently expressed mandates.
Plaintiff appears to argue that, since the costs incurred by defendant in satisfying the Kennedy Electric judgment result from defendant’s failure to comply with the Miller Act, equity should nоt permit defendant to recoup its losses by setting them off against the legitimate claims of a surety. Plaintiff, however, derives no legal or equitable rights from any action tаken or not taken in connection with the un-bonded Milwaukee contract. Aetna had no relationship to, nor participation in, that contract. The Miller Act’ requirement that the contractor file a payment bond is intended to protect subcontractors and materialmen on the particular contract for which thе bond is required. See Kennedy Elec. Co. v. United States Postal Service,
As a second offset, defendant claims that it has the right to withhold $58,691 to cover Corrigan’s liability to defendant for the excess costs of reprocuring the Milwaukee contract.
Having determined that defendant is entitled to offsets in an amount that exceeds the contract funds remaining in defendant’s hands, we conclude that plaintiff is not entitled to recоvery. Accordingly, it is ordered that defendant’s cross-motion for summary judgment is granted; plaintiff’s motion for summary judgment is denied, and plaintiff’s petition is dismissed.
Notes
USPS succeeded to the Interest of the POD, under the terms of the Postal Reorganization Act, 84 Stat. 719 (1970), on July 1, 1971. All assets and liabilities of the POD were transferred to the USPS. See 39 U.S.C. § 2002.
Aetna Incurred no losses as a result of Its perfоrmance bond obligations.
By tais time, Corrigan was In bankruptcy. Since there was no surety from whom Kennedy could seek recovery, Kennedy was forced to proceed against ÜSPS.
Defendant claims that It Is entitled to offset the fall amount of the Kennedy Electric judgment. There is some question, however, as to whether defendant Is entitled to offset that entirе amount or whether that amount must be reduced by any funds from the Milwaukee contract remaining in defendant’s hands. The District Court opinion in Kennedy Electric indicates that $35,739.47 remains in defendant’s hands. See
The amount of this offset is established by the contracting officer’s final decision, dated January 14, 1975. The decision was not appealed.