75 Colo. 185 | Colo. | 1924
delivered the opinion of the court.
The North Sterling Irrigation District, plaintiff below, is a quasi municipal corporation which was organized by owners of arid lands in Logan county. Their purpose was by such instrumentality to acquire a supply of water for the irrigation of 83,000 acres of land within the proposed district. This corporation, under the statutes of this state
Plaintiff’s grievance is set out in three causes of action. The first is to recover the difference between the contract price for excavating the ditch and the actual cost of completing it; the second is to recover three separate items of damage: the first item is for money which the plaintiff was compelled to pay to the Union Pacific Railroad Company for the repair of its track which was washed out by the escaping water; the second for the repair of the ditch itself; the third for extra compensation paid to additional ditch riders which the plaintiff was obliged to employ to guard against further breaks and which would have been unnecessary had it not been for the alleged de
At considerable length in their briefs counsel for the surety company discuss various questions whose proper solution was solely for the jury. In various answers and affirmative defenses and under appropriate assignments are discussed the alleged failure of the district to supply and furnish the contractors with quantities, a technical term including estimates of the yardage to be excavated; the places where excavation was to take place; the disposition of waste; that the contractors and the owner, without the knowledge or consent of the surety, had settled and adjusted all the differences between them, including the matters involved in this action; that various material changes and alterations were likewise made by the contractors and owner in the terms of the contract without the surety’s consent; that the cause of the breaking of the banks of the ditch was not because of defects in the work of the contractors as claimed, but was due to the negligence of the district in turning into its ditch water which at the time carried large quantities of ice, and by attempting to divert into the ditch a greater quantity of water than it was calculated safely to carry. As to these and other alleged similar errors, it is sufficient to say that we have examined with care the record and the briefs of counsel, and are satisfied that no prejudicial error as to any of them was committed either by the court or the jury. One further observation we indulge is as to the assignments of error to instructions given and to instructions refused. These we can not consider, if for no other reason, because the abstract of the record does not contain all of the instructions which the court gave to the jury. The abstract on its face shows that only a part of, but not all, of the instructions delivered to the jury are therein included. Some of these omitted from the printed abstract may have cured the alleged defects now complained of and might have been sufficiently broad and comprehensive properly to present to the jury the issues of fact
1. The complaint alleges the execution of the contract and its breach by the contractors to the injury of the district. One item of damage claimed was for the difference between the amount the district would have been obliged to pay had the contractors completed the' entire work, and the price that must be paid if the work was done by the district or by some other contractor employed by the district. There is a clause in this contract which provides that no suit on the bond for any default whatever shall be brought after twelve months from the date on which the final payment under the building contract falls due. It was necessary, therefore, that this suit should be brought, if at all, within the time alleged. For reasons elsewhere herein stated it was impossible within that time to know the exact cost to the district of having the work, unfinished by the contractors, actually completed by the district. So, in the complaint it is in effect alleged not that this excess amount “did cost,”’ or “has cost,” but “will eost,”a specific sum. At the trial, however, the work had been actually done and the exact amount was known. The complaint1 sufficiently advised and warned the defendants of the elements of damage and they must have known also, for the reasons stated, that this particular element could not be definitely known until the work not done by the contractors had been completed by the district or by some other contractor. For this alleged indefiniteness and for the uncertain or wrong measure of damage relied upon,
The real objection argued under these assignments concerning the motion and the demurrer is to the alleged improper measure of damage thereby indicated. The defendant itself relies upon, and has cited authority to, the proposition that where a contractor fails to perform a contract to do certain work, the measure of damage is the cost to the owner of having it done by another, less the contract price if that has not been paid. As we understand the record, that is the rule invoked by the plaintiff and the one which the court applied in its instructions to the jury. The real objection made to the pleadings does not raise the point in question, for if the contract, as it does, alleges that it has been breached to the damage of the plaintiff, a cause of action is alleged even though the measure of damage relied upon is not the one that governs. It is presumed that the court, at the appropriate time, will properly instruct as to the measure of damage and there is nothing in this record to show that the court did not do so.
2. In the building contract is this paragraph: “It is further agreed between the parties hereto that the party of the second part (the contractors) shall not be required to do any work for which the money to pay the same has not first been made available by proper levy and collection of taxes and in the hands of the Treasurer of the said District and set aside in a fund provided by the Treasurer’s office for this purpose.”
It will be observed that there is no inhibition in this clause which prohibits the contractors from beginning this work, if they see fit, before such levy and collection are made and the separate fund set aside. It merely says that the contractors shall not be required to do any work before these specified things have been done. In its first
3. The point apparently upon which chief reliance for reversal is based is that the district failed to retain 10 per cent of the amount due the contractors until the completion of the contract. A clause in the contract requires the district to retain this percentage. In United States Fidelity & G. Co. v. Citizens Bldg. & Imp. Co., 62 Colo. 440, 163 Pac. 281, this Court, as to a similar clause in the contract before it, said that it was for the benefit of the surety as well as for the owner, for such provisions “create a sum in the hands of the owner for the surety’s protection, and at the same time act as an incentive to the contractor to complete the building.” The court there held that for a violation of the stipulation by the owner, the surety was discharged. If the facts of this, case were the same as in that, we would follow the rule there laid down, but the facts are essentially different here and there is also a provision of this contract that seems not to have been in the contract there, or, at least not referred to. The facts are that the 10 per cent was retained by the district until after the contractors had abandoned the work and had been paid the full amount due them. It seems that some part of this 10 per cent was thereafter applied by the district to the payment of labor and material bills that went into the construction of the ditch, which payment the district claimed it had the right to apply under the following provision of the surety bond:
“The condition of this obligation is such that if the Principal shall faithfully perform the contract on its part to be performed, according to plans and specifications, and hold the obligee harmless from any damages resulting*196 from the acts of the Principal, either carelessly, negligently or otherwise, and pay all bills for labor, material, and other bills which might in any manner become a lien against the property of the obligee .were the same unpaid, then this obligation shall be null and void; otherwise it shall remain in full force and effect.”
This contract contemplated that one object of the retained 10 per cent was to enable the surety to pay bills of this character which it was the primary duty of the contractors to pay and the secondary duty of the surety to pay if the contractors defaulted. This contract itself would seem to justify the district in so applying the retained percentage. Counsel for the surety company say this is not so, because the bills in question which the percentage retained was applicable to were only such bills as might constitute a lien against the property of the district, the obligee in the bond. If it were .necessary to a decisioiT of the point presented, the language employed might be held to mean that the surety company bound itself to pay absolutely all bills for labor and material, and, in addition, further bills, that is, bills that were not for labor and material, but which might in any manner constitute a mechanic’s lien. In other words, two kinds or classes of bills are contemplated; one for labor and material, the other, such as might become a lien. If that construction is permissible the surety should not be heard to say that the entire clause in question is meaningless because no bills of any kind against an irrigation district could become liens against its property. Unquestionably such is the law as to liens, but the surety company would not be in a position to claim that the clause in question is meaningless merely because there can be no mechanic’s lien against an irrigation district if such construction was adopted by us.
But if not so, aside from this, and that is as far as we need to go, and even if the clause has no meaning and the owner has no right to apply any part of the percentage to the payment of labor and material bills, the surety
Considering the record in its most favorable light to the defendant surety, it has no grievance. There being no substantial or prejudicial error, the judgment is affirmed.
Mr. Chief Justice Teller and Mr. Justice Sheafor concur.