OPINION
We are asked to decide whether substantial compliance with our contractor licensing statute can satisfy the licensing prerequisite to a civil action under A.R.S. § 32-1153. We hold that it can.
I. BACKGROUND
Aesthetic Property Maintenance, Inc. (APM) is in the landscaping business. It became a licensed contractor in January, 1990, and renewed its license in December, 1990. It had recently moved and included its new address with the renewal.
In late 1991, the Registrar of Contractors erroneously sent a renewal notice to APM’s old address. APM’s forwarding order with the post office had since expired. APM therefore did not receive the notice and did not renew its license, which was suspended by operation of law on January 1, 1992. APM discovered its suspension in late June, 1992, and immediately sought and received reinstatement. During the lapse, APM maintained its general liability insurance, workers’ compensation insurance and contractor’s license bond.
APM entered into a contract with Howell Constructors, Inc. in mid-December, 1991, (and thus before suspension) to do landscaping and irrigation work on a City of Glendale park. APM finished that project on March 5, 1992 (during suspension). In mid-January, 1992, (during suspension) it entered into another contract with Howell to do similar work for Dysart Junior High School. APM finished that project on August 25, 1992 (after reinstatement).
Because Howell failed to pay in full, APM brought an action against it and its surety, Capitol Indemnity Corporation (Capitol), for the balances due. Howell defaulted. Capitol raised the defense of nonlicensure. Acknowledging a preference for ruling otherwise, but believing that it was constrained by our cases, the superior court granted judgment in favor of Capitol on APM’s and Capitol’s cross-motions for summary judgment.
The court of appeals affirmed. It shared the trial court’s concern, but felt similarly limited by earlier case law. It held that A.R.S. § 32-1153 barred APM from recovering for either project because APM was not licensed at the time the cause of action arose for the Glendale project and at the time it entered into the Dysart contract. We granted review to decide whether § 32-1153 is a bar to an action even where there has been substantial compliance with the licensing statute.
APM concedes that it was not licensed during portions of critical times as required by § 32-1153, but argues that we should follow cases from other states and adopt a *76 substantial compliance test. Capitol argues that § 32-1153 requires strict compliance.
II. ANALYSIS AND RESOLUTION
A. Arizona’s Licensing Scheme
A.R.S. §§ 32-1101 to -1170.03 set forth the requirements for obtaining and keeping a contractor’s license. Among other things, contractors must qualify under § 32-1122, maintain a surety bond or cash deposit, § 32-1152, and not commit any act or omission listed in § 32-1154(A). A.R.S. § 32-1153 sets forth prerequisites for bringing an action for unpaid work. It provides:
No contractor as defined in § 32-1101 shall ... commence or maintain any action in any court of the state for collection of compensation for the performance of any act for which a license is required by this chapter without alleging and proving that the contracting party whose contract gives rise to the claim was a duly licensed contractor when the contract sued upon was entered into and when the alleged cause of action arose.
Although we have not decided whether substantial compliance with the licensing statute satisfies § 32-1153, we have applied the statute before.
In
Northen v. Elledge,
B. Substantial Compliance and Statutory Purpose
Our eases suggest that whether a rule of strict or substantial compliance applies depends upon which rule promotes legislative purpose. In
Matcha v. Wachs,
We have found substantial compliance adequate in a variety of statutory settings.
E.g., Pima County v. Cyprus-Pima Mining Co.,
But we have required strict compliance when less would defeat a statute’s purpose. For example, in
Estate of Ball v. American Motorists Ins. Co.,
In short, whether substantial or strict compliance is required is largely a question of which test best promotes legislative purpose. See AR.S. § 1-211(B) (“Statutes shall be liberally construed to effect them objects and to promote justice.”).
C. Legislative Purpose
Capitol argues that the purpose of § 32-1153 is to penalize contractors who do not strictly follow the licensing statute. But our cases are to the contrary.
We have repeatedly held that the purpose of § 32-1153 is to protect the public from unscrupulous, unqualified, and financially irresponsible contractors.
E.g., Westinghouse Elec. Corp. v. Rhodes,
Several states with similar statutes have adopted rules of substantial compliance. In
Koehler v. Donnelly,
*78
Other states have based their own substantial compliance tests on
Latipac,
but the underlying theme is that substantial compliance is adequate when it satisfies the general policy or purpose of the statute.
McNairy v. Sugar Creek Resort, Inc.,
We thus conclude that substantial compliance can be adequate under § 32-1153.
D. Factors and Application
The cases are suggestive of some of the factors relevant to whether there has been substantial compliance. Is suspension by operation of law under § 32-1125(A) or for cause under § 32-1154(A)? Did the Registrar’s failure contribute to noncompliance?
Because the statute is designed to protect the public, the public must in fact be protected while the license is under suspension. Was the contractor financially responsible while its license was suspended? A contractor does this by maintaining its liability insurance, surety bond, workers’ compensation insurance, and any other requirement imposed by the Registrar. Failing that, there can be no substantial compliance.
Did the contractor knowingly ignore the registration requirements? If so, this is fatal to a claim of substantial compliance. Did the contractor, immediately upon learning of the license suspension or other statutory noncompliance, apply to reactivate the license or remedy the statutory violation? This is a necessary condition to a finding of substantial compliance. Finally, did the failure to comply with our statute prejudice the party the statute seeks to protect?
The facts here are not disputed. APM filed a statement of facts in support of its motion for summary judgment under Rule IV(f), Unif.R.Prac.Super.Ct. APM asserted that: (1) its license was suspended for failure to pay the annual fee; (2) it maintained its general liability insurance, workers’ compensation insurance, and its contractor’s license
bond
2
while its license was suspended; and (3) it paid a late fee and had its license reinstated immediately upon learning of the suspension. Capitol did not dispute any of these facts, but did object to their relevance. It thus admitted them. Rule 56(e), Ariz. R.Civ.P.
See, e.g., Sato v. Van Denburgh,
APM satisfies the substantial compliance test. APM’s license was suspended by operation of law for its failure to timely pay a renewal fee. As soon as it learned of the suspension, it paid a late fee and had the license reinstated. The Registrar contributed to the problem by failing to honor APM’s notice of change of address. At all times during the suspension, APM remained financially responsible by keeping current its surety bond, workers’ compensation insurance, liability insurance, and financial documents. Capitol was not prejudiced by APM’s suspension.
III. CONCLUSION
Because APM substantially complied with our licensing statute, it was entitled to sum *79 mary judgment and Capitol was not. The judgment of the superior court is reversed and the case is remanded to that court for entry of judgment in favor of APM and against Capitol. The memorandum decision of the court of appeals is vacated.
APM is entitled to its reasonable attorneys’ fees under A.R.S. § 34-222(B) upon compliance with Rule 21, Ariz.R.Civ.App.P.
Notes
. Nor has the court of appeals been asked to decide the question of substantial compliance. Neither
B & P Concrete v. Turnbow,
. Capitol did not dispute the facts associated with the validity of the bond, but did claim the bond was legally ineffective during APM’s suspension. We reject that argument.
