OPINION AND ORDER
This matter is presently before the court on plaintiffs application for a temporary restraining order and motion for preliminary injunction, which plaintiff filed pursuant to 28 U.S.C. § 1491(b) (1994), as amended by Administrative Dispute Resolution Act of 1996, Pub.L. No. 104-320, 110 Stat. 3870, 3874-75 (1996), and RCFC 65.
Factual Background
On February 11, 1997, defendant, acting through the Department of the Air Force, issued Solicitation No. F41608-96-R-0254 (the solicitation). The purpose of the solicitation was “to determine whether the C-5 depot maintenance activity currently performed at the San Antonio Air Logistics Center!, Kelly Air Force Base, Texas,] should be privatized or transferred to another public depot for performance.”
By letter dated May 21, 1997, defendant’s contracting officer notified plaintiff that its proposal had been eliminated from the competitive range. Under the terms of the solicitation, a proposal could be excluded from the competitive range based upon: (1) an unrealistic cost or price; (2) evidence that an offeror does not understand the requirement; or (3) major technical or business deficiencies, or omissions, that cannot reasonably be cured through discussions with the
Plaintiff received a debriefing from defendant regarding its disqualification on June 4, 1997. During the debriefing, defendant gave a slide presentation that identified the allegedly deficient technical areas in plaintiffs proposal with either a red or a yellow marking. A red marking signified the areas that “fail[ed] to meet a minimum requirement of the [solicitation]’ and were uncorrectable through discussions or negotiations.”
On June 12, 1997, plaintiff filed its application for a temporary restraining order and motion for preliminary injunction. In its filings, plaintiff asserts that defendant violated the solicitation and applicable law by excluding plaintiff from the competitive range based upon the alleged deficiencies listed in the Determination and described during the debriefing. In support of its position, plaintiff argues that the Determination contains erroneous factual assertions regarding the contents of plaintiffs proposal, and cites alleged major technical requirements that either are not part of the solicitation or are incorrectly interpreted. Plaintiff maintains that its proposal complies with all of the essential requirements of the solicitation. Plaintiff therefore alleges that defendant’s actions deprive plaintiff of the opportunity to compete for this contract without substantial justification. Accordingly, plaintiff asserts that its proposal should be reinstated in the competitive range before the remaining offerors begin discussions and negotiations with defendant. After the start of such discussions, plaintiff contends that it will not have a fair opportunity to compete for award. Defendant refutes these claims and maintains that plaintiff has not shown a need for the emergency relief it seeks.
The court heard oral argument on plaintiffs application for a temporary restraining order and motion for preliminary injunction on June 17, 1997. The parties’ filing and statements made by counsel during oral argument indicate that the offerors who were found to be within the competitive range (remaining offerors) have submitted clarification requests (CRs) and deficiency requests (DRs) to defendant. During oral argument, counsel for defendant further stated that, unless the court grants the requested injunctive relief, defendant plans to proceed with all aspects of the procurement short of contract award.
Discussion
It is well-settled that the court’s review of an agency’s pre-award procurement decision is extremely limited in scope. Bean Dredging Corp. v. United States,
A. Irreparable Harm
Plaintiff claims that it will be irreparably harmed if the requested injunctive relief does not issue, arguing that, absent such relief, it will be denied the opportunity to compete for the contract award at issue.
In plaintiffs view, allowing the remaining offerors to submit two BAFOs, while only allowing plaintiff to submit one, would constitute irreparable harm to plaintiff. In presenting its argument, plaintiff makes much of the fact that 48 C.F.R. § 15.611(b) (1996), requires a common cutoff date for the submission of BAFOs. It also should be noted, however, that 48 C.F.R. § 15.611(a) (1996), provides that the contracting officer, upon completion of discussions, shall issue requests for BAFOs to “all offerors still within the competitive range.” Id. (emphasis added). Thus, a request for BAFOs will be issued to plaintiff only if it prevails on the merits of its claim and its proposal is found to be within the competitive range. In such circumstances, a second BAFOs round would be initiated with a cutoff date that would be the same for plaintiff and all offerors still within the competitive range.
In sum, plaintiff has not demonstrated that any possible harm it may suffer would be irreparable. Cf. Cincom,
B. Balance of Harms
Plaintiff further contends any harm that injunctive relief may cause defendant is less significant than the harm plaintiff will suffer if its request is denied. Initially, plaintiff notes that, although consideration of plaintiffs claim may cause a slight delay in the evaluation/negotiations process of the procurement, such delay will not prejudice defendant’s interests. Similarly, plaintiff argues that, if the requested relief is granted and defendant is directed to evaluate plaintiffs proposal as within the competitive range, the procurement process will suffer only an additional slight delay; whereas, in absence of such relief, the resulting harm to plaintiff will be great.
The court, however, is not convinced that any harm which may be suffered by plaintiff outweighs the harm which may be suffered by defendant. As previously noted, any perceived immediate harm to plaintiff could be remedied should plaintiff ultimately prevail on the merits of its claim. By contrast, if the court were to grant the requested injunctive relief and then reject plaintiffs claim on its merits, the resultant harm to defendant, as well as the remaining offerors, would be great.
Specifically, defendant would be forced to delay its consideration of the remaining proposals in anticipation of a decision by the court on the merits of plaintiffs claim. As such, if plaintiffs claim were to be denied on its merits, the progress of this procurement would have been needlessly delayed. As pointed out in the declaration of Major General James S. Childress, the solicitation addresses military preparedness concerns and thereby implicates interests of national defense, which are a factor that the court must consider in the balance-of-harms analysis. Section 1491(b)(3); see also Cincom,
The balanee-of-harms scale further tips in defendant’s favor because defendant has guaranteed that no contract award will be made until after the court issues its decision on the merits of plaintiffs claim. In light of this promise and in accordance with the preceding discussion, the court is satisfied that, should plaintiff ultimately prevail on its claim, defendant will fully and fairly consider plaintiffs proposal prior to rendering a final award decision. The court therefore concludes that the potential harm to defendant outweighs any possible harm to plaintiff.
C. Public Interest
Plaintiff also contends that the public interest will be served by the granting of the requested injunctive relief. Specifically, plaintiff asserts that granting such relief not only will preserve the integrity of the federal procurement process, but also will protect the fisc because inclusion of plaintiffs proposal in the competitive range will help to insure cost savings to defendant.
Clearly, the public interest in honest, open, and fair competition in the procurement process is compromised whenever a plaintiff is improperly excluded from that process. Cincom,
In brief, the court’s prompt review of the merits of plaintiffs claim will both protect the public interest in fair competition and preserve defendant’s right to conduct procurements with minimal judicial interference. Therefore, public interest considerations do not require that the court grant the injunctive relief plaintiff seeks.
D. Likelihood of Success on the Merits
It is well-settled that, in order to succeed on a request for injunctive relief, a plaintiff must satisfy every element of the requisite four-part test. See Cincom,
Indeed, in making such a determination, the court would be required to decide whether the action taken by the procuring officials in excluding plaintiffs proposal from the competitive range had a rational or reasonable basis. See Caddell Constr. Co. v. United States,
Conclusion
For the above-stated reasons, plaintiffs application for a temporary restraining order and motion for preliminary injunction are denied. Further proceedings in this case are to be conducted in accordance with the court’s order dated June 17,1997.
IT IS SO ORDERED.
Notes
. Based upon the representations of plaintiffs counsel that plaintiff's memorandum in support of its motion for preliminary injunction also supports its application for a temporary restraining order, for purposes of this opinion and order, the court treats plaintiff's application for a temporary restraining order and motion for preliminary injunction together.
. Solicitation Documents, Complaint for Injunctive and Declaratory Relief (Compl.), Attachment 1 at 1.
. Id., § M-900, V 3.0.
. Notification of Exclusion from Competitive Range (Notice), Compl., Attachment 2 at 2.
. Memorandum in Support of Motion for Preliminary Injunction (Mem.) at 3 (quoting Debriefing Slides (Slides), Compl., Attachment 3 at 2).
. Id. (quoting Slides, Compl., Attachment 3 at 2).
. Transcript (Tr.) at 43.
. Id.; see also id. at 14. At the present time, the contemplated award date is August 12, 1997. Although defendant's counsel has indicated that defendant will wait longer if need be, id. at 14, the court is committed to rendering its decision on the merits of plaintiff’s claim prior to that date.
. Plaintiff estimates the cost of the work, as currently performed by defendant, to be in excess of $100 million per year.
. Further, the regulations specifically contemplate that a second round of BAFOs may be required in certain circumstances. In that regard, 48 C.F.R. § 15.611(c) (1996), provides that a contracting officer may reopen discussions af
. The same also is true of plaintiff’s contention that it will suffer irreparable harm due to the loss of potential profits on the contract. See Keco Indus., Inc. v. United States,
. Tr. at 19.
