Lead Opinion
delivered the opinion of the court:
Plaintiff, Adkins Energy, LLC (Adkins), sought declaratory relief in response to alleged litigation threats by defendant, Delta-T Corporation (Delta-T), in connection with an ethanol plant that Adkins was building. The trial court granted summary judgment for Delta-T on count I of Adkins’s amended complaint. It also granted Delta-T’s motion to dismiss counts II and III, holding that the parties’ rights were fixed and not subject to determination in a declaratory judgment action. Adkins timely appeals. We dismiss in part, reverse in part, and remand the cause.
BACKGROUND
Adkins owns a corn-to-ethanol processing plant, which, at all times pertinent to this cause, was being built in Lena, Illinois. Delta-T is a provider of technology and engineering services. Beginning in July 2001, a dispute arose between Adkins and Delta-T regarding whether a contractual or other relationship existed between them. In November 2001 Adkins filed a four-count complaint for declaratory relief. Delta-T moved to dismiss the complaint, and the trial court stayed discovery until it resolved the motion. The trial court denied the motion to dismiss count I but granted the motion to dismiss counts II through IV The trial court permitted Adkins to replead and ordered Delta-T to respond to Adkins’s discovery request. Adkins submitted an amended complaint with three counts, seeking declarations that Delta-T was not and had no right to be a member of Adkins or an equity participant in Adkins in relation to the ethanol plant (count I); had no contractual rights against Adkins, including the right to be a subcontractor in the ethanol plant project (count II); and had no right to compensation from Adkins for expenses that Delta-T allegedly incurred in connection with the ethanol plant (count III).
Adkins attached to the complaint three letters it received from Delta-T. In a July 6, 2001, letter, Delta-T stated that, if a satisfactory subcontract agreement could not be arranged with Lurgi PSI, one of the entities comprising Adkins, then “Adkins is bound to enter into a contract directly with Delta-T, or to pay Delta-T a fair amount to compensate for Delta-T’s efforts.” Delta-T repeated this assertion in a letter dated July 12, 2001, stating, “[w]e firmly believe that Adkins, and one or more of its members, do have an obligation to Delta-T to include it in the project, or to compensate it for the services it has provided to Adkins and Adkins’ predecessors since 1995.” Finally, Delta-T’s owner wrote in an October 26, 2001, letter, “[m]y attorneys feel we have a strong legal case to prove that we were wronged and financially damaged.” He also stated that he had written the letter “to see if there was a way to work this situation out in a civilized manner” and hoped Adkins would “do the right thing” to avoid a “legal battle.”
Delta-T’s discovery response admitted the substance of count I. Delta-T moved for summary judgment on that count, admitting that it was not entitled to be an equity participant in Adkins or the ethanol plant. In its motion, Delta-T averred, “Count I involves no actual controversy for the Court to adjudicate and the Court should grant summary judgment in favor of Delta-T.” Adkins filed a cross-motion for summary judgment. Delta-T also filed a motion to dismiss counts II and III pursuant to section 2 — 615 of the Code of Civil Procedure (735 ILCS 5/2 — 615 (West 2002)). The trial court granted Delta-T’s motion for summary judgment on count I. The trial court also granted Delta-T’s motion to dismiss counts II and III, holding that Adkins was seeking a finding of nonliability for past conduct between the parties. The court determined that the parties’ rights were fixed and not subject to determination in a declaratory judgment action.
Adkins appeals, arguing that the trial court (1) erred when it granted summary judgment for Delta-T on count I; (2) erred when it dismissed counts II and III, which, Adkins claims, sought the resolution of an actual controversy and did not seek a declaration of nonliability for past conduct; and (3) abused its discretion when it stayed discovery until it determined whether Adkins’s initial complaint stated a cause of action.
ANALYSIS
A declaratory judgment action requires (1) a plaintiff with a tangible, legal interest; (2) a defendant with an opposing interest; and (3) an actual controversy between the parties concerning such interests. Beahringer v. Page,
We first examine count I of the amended complaint, in which Adkins sought a declaration that Delta-T was not and had no right to be a member of Adkins or an equity participant in the ethanol plant. Adkins argues that the trial court erred when it granted Delta-T summary judgment on count I. Delta-T maintains that the issue is moot because Delta-T admitted the substance of count I.
Appellate jurisdiction is based upon the existence of a real controversy, and this court will dismiss an appeal involving only moot questions. La Salle National Bank, N.A. v. City of Lake Forest,
We next turn to counts II and III. In count II, Adkins sought a declaration that Delta-T has no contractual or other rights against Adkins, including the right to be a subcontractor. In count III, Adkins sought a declaration that Delta-T was not entitled to any compensation from Adkins for expenses that Delta-T allegedly incurred in connection with the ethanol plant. A trial court’s grant of a section 2 — 615 motion to dismiss a declaratory judgment action is subject to de novo review. Beahringer,
Delta-T first maintains that Adkins’s declaratoiy judgment action lacked an actual controversy because it was premature, citing Howlett. In Howlett, the Secretary of State sought a declaratory judgment that his receipt of consulting fees was not a conflict of interest with his position on the Vehicle Recycling Board. An investigation by the Attorney General’s office had found that a conflict of interest existed, but the investigative report recommended delaying any action until the supreme court had reviewed two relevant appellate court decisions. The Howlett court concluded that the Secretary’s legal action was premature because the Attorney General did not indicate an intent to prosecute and the declarations sought depended on the future outcome of the two pending cases. Howlett,
Adkins contends that Miller v. County of Lake,
In the present case, Delta-T repeatedly asserted its belief that Adkins had to either include it in the ethanol project or compensate it for expenses. Delta-T also indicated that, if an agreement was not reached with Adkins, Delta-T would file a lawsuit. Unlike the circumstances in Howlett, Adkins’s rights were not dependent on future events. Further, as in Miller, Delta-T clearly threatened litigation, thus creating an actual controversy. See also Roland Machinery Co. v. Reed,
Delta-T also maintains that the trial court was correct in granting Delta-T’s motion to dismiss because Adkins sought declarations of nonliability for past conduct, which are not obtainable under the declaratory judgment statute. See Howlett,
The doctrine of nonliability for past conduct bars an action for declaratory judgment when the conduct that makes a party liable, that is, amenable to suit, has already occurred. The fact that the amount allegedly owed under a contract is already fixed does not preclude a declaratory judgment action, because a party is not amenable to suit until a breach occurs. Therefore, declaratory judgment could guide future conduct in such a situation because a court could determine whether or not a valid contract exists and, thereby, inform the party that potentially owes the money whether or not it would be in breach of contract should it refuse to pay. In such a situation, only when a party refuses to pay does a declaratory judgment action become improper because, at that point, the refusal to pay either is or is not a breach of contract and there is no future action to guide. A close examination of the case law in this area supports our interpretation.
The court in Miller found that Howlett was distinguishable because, unlike in Howlett, there was clear intent to prosecute and the relationship forming the basis of the suit was still ongoing. Miller,
In Eyman v. McDonough District Hospital,
The recent decision in Roland demonstrates that when the potentially breaching act has not yet occurred, a declaratory judgment action is proper. In Roland the plaintiff had contracted to sell the defendant a bulldozer. Roland,
This case involves the determination of whether Adkins has any obligations to Delta-T. Therefore, Adkins would be liable to Delta-T only if it breached any such obligations. The instant situation is similar to that of an insurance company that seeks to determine whether it must pay an insured under an insurance contract. Although there is scant Illinois case law on the application of the doctrine of nonliability for past conduct to insurance cases, we may look to foreign jurisdictions for guidance. Beahringer,
Delta-T points out that a court must refuse to enter a declaratory judgment if it will not terminate the controversy or some part of the controversy. See 735 ILCS 5/2 — 701(a) (West 2002). Delta-T contends that this doctrine should bar count II because, if the trial court concludes that Delta-T is entitled to a subcontract, the controversy will continue. However, Delta-T misapplies the rule. If the trial court grants the relief sought in count II, a declaration that Delta-T does not have subcontractor rights, this portion of the controversy will be resolved.
Accordingly, we reverse the trial court’s dismissal of counts II and III and remand for further proceedings.
Lastly, Adkins asserts that the trial court erred when it stayed discovery until it ruled on Delta-T’s first motion to dismiss. Adkins contends that the case could have been resolved earlier or even settled if discovery had not been postponed. A trial court has great latitude in ruling on discovery matters. Mutlu v. State Farm Fire & Casualty Co.,
Counts II through IV of Adkins’s original complaint were disposed of on Delta-T’s motion to dismiss. A trial court may properly quash a discovery request when it has sufficient information upon which to decide a defendant’s motion to dismiss. Mutlu,
CONCLUSION
Accordingly, we dismiss the portion of the appeal challenging the trial court’s grant of summary judgment in favor of Delta-T on count I of Adkins’s amended complaint. With respect to counts II and III, we reverse and remand the cause for further proceedings consistent with this opinion.
Dismissed in part and reversed in part; cause remanded.
Concurrence Opinion
concurring in part and dissenting in part:
While I agree with the majority’s resolution of counts I and II, I disagree that the trial corut’s decision dismissing count III of Adkins’s complaint must be reversed.
In count III Adkins sought a declaration that Delta-T had no right to compensation from Adkins for expenses that Delta-T had incurred in connection with the ethanol plant. The letters sent to Adkins by Delta-T reflect that Delta-T was requesting compensation in some manner for its “efforts.” As such, Delta-T sought to enter into a contractual agreement with Lurgi PSI, one of Adkins’s entities, or in the alternative, to be compensated “for the services it has provided to Adkins and Adkins’ predecessors since 1995.” Based on these representations, it appears that Delta-T was seeking compensation for services that it had provided in the past on behalf of Lurgi PSI, a related entity of Adkins.
The purpose of a declaratory judgment is “ ‘to settle and fix rights before there has been an irrevocable change in the position of the parties that will jeopardize their respective claims of right.’ ” Beahringer,
Accordingly, I would have affirmed the trial court’s dismissal of count III of Adkins’s complaint. I therefore respectfully concur in part and dissent in part.
