ADC Contracting & Construction, Inc. v. Town of SouthamptonADC Contracting & Construction, Inc. v. Town of Southampton
Ordered that the order and judgment is affirmed insofar as appealed from, with costs.
The plaintiff filed a timely notice of claim against the defendant, the Town of Southampton (hereinafter the Town), alleging breach of contract. Throughout the next four years, the case proceeded through litigation, and culminated in a jury trial which resulted in a verdict awarding the plaintiff damages. During the trial, the plaintiff‘s owner Anthony Chiodi testified that he had notarized the documents submitted to the court by using his wife‘s expired notary stamp and forging her signature. In a posttrial motion, the Town moved, in effect, pursuant to
In contrast to other notice statutes,
The plaintiff‘s contentions that the Town waived its right to pursue a notice of claim defense, or that the doctrine of estoppel applies, are without merit. The plaintiff did not disclose the improper verifications until its owner testified during the trial, and, as such, the Town neither waived its rights nor engaged in conduct that induced the plaintiff not to comply with the statutory requirements warranting the application of the estoppel doctrine (cf. Lebanon Val. Landscaping v Town of Nassau, 192 AD2d 902 [1993]; Town of Smithtown v Jet Paper Stock Corp., 179 AD2d 634 [1992]).
Miller, J.P., Ritter, Covello and McCarthy, JJ., concur.