131 N.Y.S. 519 | N.Y. App. Div. | 1911
The plaintiffs were copartners engaged in the business of excavating for foundations in .the city of New York, and the defendants were general contractors and had taken a contract from the owners of premises on Longwood avenue, Kelly and Beck streets, in the borough of the Bronx, for the excavation for and the. construction óf a foundation for a building to be erected thereon. On the 24th day of December, 1908, the plaintiffs entered into a contract in writing with the defendants, by which they evidently intended to sublet to plaintiffs the excavation work. Plaintiffs, however, contend that only part of the excavation work was included in their contract. The part of the contract most material to a decision of the
“ That the said parties of the second part herein hereby agree to do all the excavating and blasting of all the rock and stone on the plot 200'xllO', said premises being 200 feet on the south side of Longwood avenue, and being 110' on Kelly street, and 110 feet on Beck street, in the Borough of Bronx, city of New York, to the depth of 8 feet 6.inches below the curb, of the entire plot, according to the plans of the owner of the said premises, subsequently to be shown.”
The plans of the owner,- to which the contractor refers, provided not only for the excavation of the entire plot of the dimen- . sions stated in the contract, and to the depth therein stated, but to a depth in the main of about six inches more, and further for excavation work connected therewith or necessary for the construction of. the foundation for the building, as follows: First, for an areaway on Longwood avenue two hundred feet in length by seven feet in width to the depth of nine feet; second,. an areaway on Kelly street seven feet in width, thirty-seven feet in length and nine feet in depth; third, an areaway on Beck street of the same dimensions; fourth, two boiler pits thirty-three feet in length by eighteen feet in width and five feet deep, and of á depth from the highest point of the curb adjacent to the premises, one, eighteen feet and ten inches, and the other, fourteen feet ten and three-eighths inches; fifth, two elevator pits six by seven feet, four feet deeper than cellar bottom; and sixth, for certain trenches for foundation walls.
The plaintiffs also excavated two feet beyond the rear line of the premises described in the contract for the width of two hundred feet and to the depth of ten feet. This, however, was not required by the plans, and the question as to whether it was authorized by the defendants was properly submitted to the jury, and we find no error with respect to this item.
The action is brought to recover a balance claimed to be due on the contract, and for the' excavation work below the depth of eight and a half feet and beyond the precise description given in the contract as for extra work. The court ruled as matter of law that this was all extra work, and that the plaintiffs were entitled to recover as compensation therefor the
The court, in submitting the case to the jury, instructed them as matter of law that plaintiffs were entitled to recover for all of these items as extra/ work, with the excéytion of the item for excavating two feet in the rear of the premises, which was left to the jury as a question of fact, as already stated. Counsel for the defendants duly excepted to the charge in this regard, and requested the court to instruct the jury as follows: ■“ I ask your Honor to charge the jury that if the jury believe that the plans called for by the contract were in fact delivered to the plaintiffs early in January, 1909, and that the work claimed by the plaintiffs as extra work was in fact shown to be called for by the plans, the plaintiffs can recover only for the work actually performed by them at the rate provided for in the contract, and the jury can award the plaintiffs only the balance due them from the defendants at that rate.”
This request was declined, and an exception was duly taken. Counsel for the defendants also duly requested the court to instruct ,the jury on the same point as follows: “If the jury find that the plans called for by the contract were in fact delivered to plaintiffs early in January, 1909, and that the work claimed, by plaintiffs as extra work was in fact shown and called for by the plans, plaintiffs can only recover for the work actually performed by them at tlie)rate of $1.50 per cubic yard, and the jury can award plaintiffs only the balance due them from defendants at that rate.” Which was likewise refused and an exception was duly taken.
We are of opinion that the court erred in ruling as matter of law that the contract was to be taken alone, and the plans excluded, in determining the work that the plaintiffs were required to do, and also erred -in refusing to instruct the jury as requested in the requests quoted. This contract should receive a reasonable interpretation. It is manifest that, in letting rock excavation work for a foundation, the owner or contractor letting the work would ordinarily in the interests of economy provide for doing it all at the same time. ' The plaintiffs knew the purpose for which this excavation was to be
The only question which I regard as not free from doubt is whether the specification in the contract with respect to the depth of the excavation is controlling. If so, the . plaintiffs "could have been compelled to éxcavate to the depth of precisely eight and a half feet below the curb at every point. Manifestly that was not intended. The plans called for an excavation on the slant of the Longwood avenue curb along Longwood avenue to the depth of nine feet, extending over about one-half of the plot, and provided that the bottom of the other half of the plot should be level, and that about one.-half of it should be seven and half feet below the curb of Beck street and the other half seven and. a half feet below the curb of Kelly street. I am of opinion that the depth given in the contract should be regarded as an estimate, or approximate, only, to be read with the plans, and that the dépth called for by the plans is not so materially greater as to entitle the plaintiffs to recover for the additional depth as for extra work, at least, not if the plaintiffs saw the plans before proceeding with the work, and then proceeded without objec
. It follows that the.judgment and order should be reversed and a new trial granted, with costs to appellants to abide the event.
Ingraham, P.. J., and Dowling, J., concurred; Scott and Miller, JJ., dissented.
Judgment and order reversed and new trial ordered, with costs to appellants to abide event.