After Margaret Adams sustained serious injuries in a vehicle collision which occurred as a result of icy conditions on a newly reconstructed road, she sued the road contractor, APAC-Georgia, Inc. Adams appeals the trial court’s grant of APAC’s motion for summary judgment and the denial of summary judgment to her.
In February 1995, APAC was engaged in a project under contract with Cobb County to widen various sections of Atlanta Road. The collision occurred on an area of the road first opened to the general driving public on Sunday, February 5. On Monday, the temperature was below freezing during the entire work day, and at 2:00 a.m. on Tuesday it began to snow. By 6:00 a.m., .02 inch of precipitation from snow and dew had fallen, and an icy glaze covered the widened roadway. At approximately 6:20 a.m., Oscar Harris was driving his automobile on the road in a northerly direction. At the same time, Adams was a passenger in a vehicle driven by her husband in a southerly direction. As Harris was traveling up a long hill, he passed over an icy patch in the road, lost control, crossed the centerline, and struck the Adamses’ car. The investigating officer concluded that the sole cause of the accident was Harris’ loss of control of his car resulting from the weather conditions.
At the time of the accident, the roads in Cobb County were generally icy. Approximately 70 weather-related accidents were reported in the unincorporated part of the county. APAC’s work site traffic supervisor was aware of the weather conditions and had equipment and personnel which could have been used to remove ice from the road. Following the accident, Cobb County placed sand on the icy areas of the road. The county did not request such action by APAC
Adams initially sought to hold APAC liable by claiming that the accumulation of ice resulted from improper drainage caused by APAC’s negligent construction of the road.
Adams sues as a third-party beneficiary of the contract. She relies on decisions which are exemplified by Lee v. Petty
Adams also claims standing to sue APAC under § 324A of the Restatement of the Law, Torts 2d. This section, adopted as Georgia law in Huggins v. Aetna Cas. &c. Co.,
But “ ‘the duty owing toward the public by a contractor in the performance of public work cannot be increased by a contract with a public official as such, beyond the sum of the legal duty of such public official toward the public and the legal duty of the contractor toward
APAC would be under no such duty, because “a contractor constructing a road or bridge owes a duty to the public to exercise ordinary care to protect it from injuries arising by reason of such construction,”
As to Cobb County, Adams asserts that it has a duty to remedy or warn of weather-related hazards on the roadway under OCGA §§ 32-4-41 (1) (requiring a county to both construct and maintain an adequate county road system) and 32-6-50 (c) (requiring counties to place and maintain upon their public road systems such traffic control devices as are necessary to regulate, warn, or guide traffic).
Other contractual provisions require APAC to perform work required to protect the work site from damage from “both existing conditions and performed work” and to “be responsible for all damages to all persons and property due to the non-maintenance of the project site”; to maintain existing traffic control devices and to install “additional necessary devices to protect traffic from existing as well as created hazards”; and to be available on a 24-hour basis “with access to all equipment, personnel, and materials needed to maintain traffic control and handle traffic related situations” and to have the construction area patrolled at all times “for the purpose of early detection and correction of traffic related problems before they interfere with traffic flow or safety.” The trial court correctly interpreted these provisions as only requiring APAC to install traffic control devices, or to take preventative or corrective action, where traffic-related problems are caused either from preexisting hazards or by APAC’s construction activities. This interpretation is consistent with that given the highway construction contract in Purvis v. Virgil Barber Contractor,
Even if the contract was sufficiently ambiguous to be interpreted as imposing broader obligations on APAC, neither APAC nor the county interpreted the contract in such manner.
The court did not err either in denying Adams’ motion for summary judgment or in granting summary judgment to APAC.
Judgment affirmed.
Notes
See Bob v. Scruggs Co.,
(Citations and punctuation omitted.) Id. at 205.
(Punctuation omitted.) Id. Section 324A and the holding in the Petty line of cases are exceptions to the rule in OCGA § 51-1-11 (a) that if a “tort results from the violation of a duty which is itself the consequence of a contract, the right of action is confined to the parties and those in privity to that contract, except in cases where the party would have a right of action for the injury done independently of the contract.” See Stuart v. Berry,
State Constr. Co. v. Johnson,
(Citations and punctuation omitted.) Gleaton v. APAC-Ga.,
Marshall v. Hugh Steele, Inc.,
See Nat. Foundation Co. v. Post, Buckley &c.,
Purvis v. Virgil Barber Contractor,
Whether a statute imposes a duty on a county and whether a county can be held liable for a breach of such duty are two separate questions. See Kordares v. Gwinnett County,
For a review of foreign cases deciding whether a government entity can be held liable for a motor vehicle accident resulting from ice or snow on the roads, see 97 ALR3d 11, Anno: Liability, in Motor Vehicle-Related Cases, of Governmental Entity for Injuries or Death Resulting from Ice or Snow on Surface of Highway or Street (1980).
Supra,
Compare Hoffmaster v. County of Allegheny,
By its terms, § 324A applies to a duty which the promisor “has undertaken to perform.” Moreover, it was not the intent of this section to overrule cases holding that breach of an unperformed promise can give rise only to a contract action and does not result in tort liability. See Comment f to § 324A and Comment d to § 323.
Bailey v. Ga. Mut. Ins. Co.,
