78 A. 615 | N.H. | 1910
If it is conceded that the facts as reported show a liability on the part of the defendants to recompense the plaintiff for his loss, upon the theory of quantum meruit (Britton v. Turner,
In Smith v. Newcastle, supra, the defendant leased to the plaintiff a house for the term of five years. The plaintiff was to pay for his occupancy of it by making during the first two years some repairs upon it. He failed to make all the repairs within that time, and in accordance with the terms of the lease the defendant evicted him. He then brought his action for the repairs he had made. While it was held that upon quantum meruit the plaintiff might recover in an action properly instituted, it was also held that he could not maintain a suit upon that ground until after the expiration of the term of five years stipulated in the lease. The court say (p. 73): "Plaintiff claims . . . his action is in no respect founded upon the special agreement, but upon the implied contract, and that the terms of the special agreement are admissible only to show the amount of the damage sustained by the defendant by its non-fulfillment, to be recouped against the plaintiff's claim for the value of his services and property. But this position . . . has been repeatedly overruled."
In that case the plaintiff received pay on account for his services, by his occupancy of the house; but under the contract he was not entitled to full compensation until the end of the term. So, in the present case, the plaintiff has received a part of his pay from time to time; but if he had performed his contract, he would not have recovered full pay for his labor until the termination of the lease. If it is just and equitable to the plaintiff that the defendants should pay him in money the amount reported by the referee, it is not just or equitable to them that they should be compelled to pay it at an earlier date than the plaintiff had agreed upon for a final settlement under the contract which he has refused to perform. If in violation of the contract the defendants had discharged him from his employment, it is clear that the defendants had discharged him from his employment, it is clear that the defendants could not take advantage of their own breach of faith to compel the plaintiff to wait for his damages until the end of the lease (Lee v. Dow, supra); and it is equally clear that the plaintiff ought not to be permitted to take advantage of his voluntary failure to perform his contractual duty, to deprive the defendants of the benefit of *579 the term of credit which he agreed to in the original contract. According to the provisions of the case there must be,
Judgment for the defendants.
All concurred.