215 F.R.D. 645 | D. Kan. | 2003
MEMORANDUM AND ORDER
Pending before the Court is Plaintiffs’ Motion to Amend the Complaint (doc. 49). For the reasons set forth below, the Court will deny in part and grant in part the motion.
I. Background Information
This is a negligence action in which Plaintiffs seek monetary damages for alleged property damage resulting from flooding that occurred on their property on October 4, 1998. On October 2, 2000, Plaintiffs filed a “Petition for Negligence” (Petition) in the District Court of Wyandotte County, Kansas,
Defendant opposes the motion to amend on the grounds that (1) the motion is untimely, (2) Defendant will suffer undue prejudice if amendment is allowed, and (3) amendment would be futile because the new claims are barred by the applicable statutes of limitations. Defendant also opposes Plaintiffs’ request to amend to add a claim for punitive damages, asserting that Plaintiffs’ claim for fifty million dollars exceeds the five-million dollar cap placed on punitive damages awards under K.S.A. 60-3701(e).
II. Standard for Ruling on a Motion to Amend
Rule 15 of the Federal Rules of Civil Procedure allows a party to amend the party’s pleading once as a matter of course before a responsive pleading is served.
Leave to amend should be denied when the court finds “undue prejudice to the opposing party, bad faith or dilatory motive, failure to cure deficiencies by amendments previously allowed, or futility of amendment.”
III. Futility of Amendment Based on Statute of Limitations Grounds
A. Applicable Law
Defendant asks the Court to deny Plaintiffs leave to amend on the basis of futility, i.e., that the proposed new claims are barred by the applicable statutes of limitations. It is well settled that a court may deny a motion to amend as futile if the proposed amendment would not withstand a motion to dismiss or if it otherwise fails to state a claim.
Defendant contends that Plaintiffs’ proposed claims are governed by the statute of limitations found in K.S.A. 60-513(a). That statute provides a two-year limitations period for trespass, unlawful taking, and any other actions for injury to the rights of another (excluding contract actions) that are not otherwise provided for in the statutes.
According to Defendant, Plaintiffs’ proposed causes of action accrued on October 4, 1998, and therefore must have been asserted by October 4, 2000. Defendant argues that because Plaintiffs did not file the • instant motion to amend to add these claims until December 2, 2002, the claims are time-barred.
Plaintiffs do not dispute the applicability of the two-year statute of limitations and do not assert that any other statute of limitations applies. Plaintiffs’ sole argument is that their proposed amendments are not time-barred because they relate back to the date of filing of the original Petition, i.e., to October 2, 2000.
Plaintiffs assert that the Court should apply the relation-back provision of K.S.A. 60-215(c), and Kansas state court cases applying that statute, to determine whether the proposed amendments relate back. The Court disagrees. It is well settled that the relation back of amendments to pleadings in a federal court action is governed by the Federal Rules of Civil Procedure.
Federal Rule of Civil Procedure 15(e)(2) provides that “[a]n améndment of a pleading
The premise underlying Rule 15(c) is that the defendant, “once notified of pending litigation over particular conduct or a certain transaction or occurrence ... has been given all the notice required for purposes of the statute of limitations.”
Generally speaking, amendments are deemed to relate back “if they only flesh out the factual details, change the legal theory, or add another claim arising out of the same transaction, occurrence or conduct.”
B. Summary of the Parties’ Arguments and the Proposed Amendments
Defendant argues that the proposed amendments arise out of different conduct and occurrences. Plaintiffs initial Petition alleges that Defendant negligently placed eighteen of its railcars onto its tracks running along Turkey Creek to prevent the tracks from being moved by an increased flow of water caused by a heavy rain.
The proposed Amended Complaint contains allegations similar to those pled in the Petition regarding Defendant placing its railroad cars on the track during the heavy rain of October 4, 1998, allegedly causing Turkey Creek to overflow and flood Plaintiffs’ land and factory
Defendant, BN, wrongfully, willfully, and negligently constructed and/or maintained the 4.4 mile bridge, its track, embankments, culverts and the roadbed along and over said bridge so as to obstruct and impede the natural and foreseeable flow of water in times of foreseeable rainfall and water flow, and said structures diverted foreseeable water flows from its property, thereby causing and contributing to cause said waters on October 4, 1998, to back up and accumulate on the upstream side of said bridge and thereafter flow upon Plaintiffs’ lands damaging personal property of Plaintiffs businesses and inventories, damaging the structures located thereon, and causing other damages as alleged hereafter.29
The proposed Amended Complaint further alleges that Defendant breached its duty to design and maintain its improvements and structures so as to accommodate the flooding
Further, the proposed Amended Complaint pleads claims for trespass based on flooding of Plaintiffs’ property allegedly caused by (1) Defendant’s construction and maintenance of the 4.4 mile bridge and its approaches, and (2) Defendant’s placement of the railroad cars on the tracks.
In addition to making these claims for negligence, nuisance, and trespass, Plaintiffs assert claims for unlawful taking and strict liability, based on some, if not all, of the above alleged conduct.
The question this Court must decide is whether the new, proposed claims arise out of the same conduct, transaction, or occurrence asserted in the Petition so as to give Defendant fair notice of litigation arising out of the specific factual situations asserted in the proposed Amended Complaint.
C. The Supreme Court’s Decision in Tiller v. Atlantic Coast Line Railroad
One could argue that the new proposed allegations are all part of the events that led to the same injury alleged in the initial Petition, i.e., the flooding of Plaintiffs’ property, and that they should therefore relate back. One could also argue that the United States Supreme Court’s decision in Tiller v. Atlantic Coast Line Railroad Company,
Both of [the complaints] related to the same general conduct, transaction and occurrence which involved the death of the deceased----The cause of action now, as it was in the beginning, is the same — it is a suit to recover damages for the alleged wrongful death of the deceased____There is no reason to apply a statute of limitations when, as here, the respondent has had notice from the beginning that petitioner was trying to enforce a claim against it because of the events leading up to the death of the deceased in the respondent’s yard.50
Thus, under Tiller, one could argue that as long as the ultimate injury or harm remains the same, the proposed amendments should be deemed to relate back. Plaintiff in this case could thus argue that because the ultimate damage, i.e., the flooding, is the same in both the Petition and proposed Amended Complaint, all of the proposed amendments should relate back, regardless of whether they differ from the conduct alleged in the Petition. In other words, regardless of the
The Court does not interpret Tiller as standing for this proposition, and, furthermore, finds that the facts of Tiller are distinguishable from this case. Tiller concerned factual allegations that were much more closely related in time and in transaction to the original allegations than the amendments proposed here. All of the allegations in Tiller were closely related in time and in scope to the accident that killed the plaintiffs husband. The new allegation that the railroad had failed to properly light the locomotive was almost identical to the previously pled allegation that the railroad had failed to light the head car.
This Court holds that Tiller stands for the proposition that a claim adding new factual allegations relates back to the original complaint where a sufficiently close relationship exists between the original and the new claims. In such a case, the allegations all relate to the same occurrence, out of which the litigation arose, and Rule 15(c)’s crucial notice requirement is met. In this regard, the temporal proximity of the facts is relevant, although not always dispositive.
D. Application of the Law to Plaintiffs’ Proposed Claims
With these standards in mind, the Court will now decide which of the proposed claims relate back.
1. Proposed claims concerning Defendant’s design, construction, and maintenance of the mile bridge, tracks, and other items; placement of concrete abutments; and failure to perform risk management assessments
The Court finds virtually no temporal proximity between the facts and the negligence claim originally pled in the Petition and the new facts and claims relating to (1) Defendant’s design, construction, and maintenance of the 4.4 mile bridge and the railroad track, embankments, culverts, and roadbed around the bridge, (2) Defendant’s placement of the concrete abutments along the track, and (3) Defendant’s failure to perform the necessary risk management assessments regarding the bridge’s construction and maintenance. Although the Court does not know the exact dates when the 4.4 mile bridge, track, and other items were designed and constructed, their design and construction obviously took place long before the railroad cars were parked on the tracks. The same is true with respect to Defendant performing or failing to perform any risk management assessments in connection with its construction and maintenance of the bridge. Indeed, Plaintiffs aver in their Petition that Defendant owned and maintained the railroad tracks and bridges running along Turkey Creek “for many years prior to [Plaintiffs] filing this action.”
Furthermore, the newly alleged conduct of Defendant in improperly designing, constructing, and maintaining the 4.4 mile bridge, track and other items, in placing the concrete abutments around the bridge, and in failing to perform the necessary risk management assessments, is obviously separate and distinct from Defendant’s alleged conduct in parking the railroad cars on the track.
Moreover, the Court finds that the critical issue of notice to Defendant is missing with respect to these new claims. The Court finds nothing in the Petition to put Defendant on notice that it might have to defend itself against claims relating to the design, construction, or maintenance of the 4.4 mile bridge, track or other items, relating to its placement of the concrete blocks around the bridge, or relating to the any risk management assessments involving its construction and maintenance of the bridge. The Petition merely focuses on Defendant’s allegedly negligent actions in placing the train on the tracks in an attempt to keep Defendant’s railroad cars from being moved by the increased flow of water from Turkey Creek.
In light of the above, the Court holds that the proposed amendments concerning the alleged acts of Defendant in improperly designing, constructing, and maintaining the 4.4 mile bridge, track and other items, in placing the concrete abutments around the bridge, and in failing to perform the necessary risk management assessments, do not arise out of the same conduct, transaction, or occurrence set forth the original Petition. These amendments therefore do not relate back under Fed.R.Civ.P. 15(e)(2) and are time-barred. The Court will therefore deny Plaintiffs’ Motion to Amend the Complaint to the extent Plaintiff seeks to add claims based on these acts of Defendant. This would include all of the proposed nuisance claims
2. Proposed claim that Defendant failed to use ordinary care when operating its train
Plaintiffs also assert a proposed negligence claim based on Defendant’s failure to use ordinary care in operating its train and allowing it to proceed over the flooded tracks on October 4, 1998.
3. Proposed trespass claims
As noted above, one of Plaintiffs’ proposed trespass claims is based on Defendant’s construction and maintenance of the 4.4 mile bridge.
b. Proposed unlawful taking and strict liability claims
Plaintiffs’ proposed Amended Complaint asserts claims for strict liability and unlawful taking. It is unclear, however, what specific acts of Defendant constitute the claimed unlawful taking
E. Summary of the Court’s Ruling Regarding Futility of Amendment Based on Statute of Limitations Grounds
To summarize, the Court holds that Plaintiffs’ proposed claims relating to the following do not relate back and that amendment so as to allow those claims would be futile: (1) Defendant’s design, construction, and maintenance of the 4.4 mile bridge and the railroad track, embankments, culverts, and roadbed around the bridge, (2) Defendant’s placement of the concrete abutments along the track, and (3) Defendant’s failure to perform risk management assessments regarding the bridge’s construction and maintenance. This would include all of the proposed nuisance claims and some of the proposed negligence, trespass, strict liability, and unlawful taking claims. The Court will deny the motion to amend as to those claims. The Court will also deny the motion to amend to the extent Plaintiffs base their increased claim for actual damages and their punitive damages claim on those time-barred allegations.
The Court will grant the motion to amend to the extent Plaintiffs seek to add the following: (1) negligence claim based on Defendant’s failure to use ordinary care in operating its train and allowing it to proceed over the flooded track; (2) trespass claim based on Defendant’s abandonment or placing of its railroad cars on the track; and (3) unlawful taking and strict liability claims to the extent Plaintiffs are alleging that the placement or abandonment of Defendant’s railroad cars on the track forms the basis of the unlawful taking and strict liability claims. The Court will also grant the motion to amend to increase the claim for actual damages, but only to the extent the amended damages claim is predicated on claims that are not time-barred.
Defendant asks the Court to deny the motion to amend to add a punitive damages claim totaling fifty million dollars. Defendant argues that leave to amend should be denied to the extent the proposed claim exceeds the five million dollar statutory cap set forth in K.S.A. 60-3701(e).
The Court does not agree. As Plaintiffs point out, K.S.A. 60 — 3701(f) provides an exception to the statutory cap. It states:
In lieu of the limitation provided by subsection (e), if the court finds that the profitability of the defendant’s misconduct exceeds or is expected to exceed the limitation of subsection (e), the limitation on the amount of exemplary or punitive damages which the court may award shall be an amount equal to Vk times the amount of profit which the defendant gained or is expected to gain as a result of the defendant’s misconduct,65
The Court questions whether Plaintiffs will be able to establish that the profitability of Defendant’s alleged misconduct exceeds the limitation set forth in subsection (e). The issue before this Court, however, is not whether Plaintiffs will ultimately prevail on their claims for punitive damages, but whether they are entitled to offer evidence to support their allegations.
V. Timeliness of the Motion to Amend and Prejudice to Defendant
The Court will now proceed to examine whether other grounds exist to deny Plaintiffs leave to amend those claims that relate back to the date of the original filing. Defendant argues that amendment should be denied because the motion to amend was not timely filed and because Defendant will suffer prejudice if the amendments are allowed at this stage of the litigation.
Prejudice under Rule 15 means “undue difficulty in defending a lawsuit because of a change of tactics or theories on the part of the other party.”
The Court finds that Defendant has failed to show prejudice that is sufficient to preclude the proposed amendments. The Court is allowing only those amendments that relate back to the original claims, and, thus, the scope and nature of this case has not been radically altered. The mere fact that Plaintiffs’ actual damages claim has increased and a punitive damages claim has been added is insufficient to show that Defendant faces “undue difficulty” in defending the lawsuit.
Moreover, the Court does not find that the amendments should be denied based on untimeliness. The Court recognizes that this case has been on file since October, 2000, and that this motion was not filed until December 2, 2002. While the Court certainly does not encourage such delay, the Court cannot find that the delay in this case justifies denying leave to amend. The motion to amend was filed within the deadline for filing motions to amend.
IT IS THEREFORE ORDERED that Plaintiffs’ Motion to Amend the Complaint (doc. 49) is denied in part and granted in part, as set forth herein.
IT IS FURTHER ORDERED that Plaintiffs shall revise their proposed Amended Complaint so as to comply with this Order. Plaintiffs shall file and serve their Amended Complaint within ten (10) days from the date of filing of this Order. Defendant shall plead in response to the Amended Complaint as set forth in D. Kan. Rule 15.1(a).
IT IS SO ORDERED.
. See Ex. A attached to Notice of Removal (doc. 1).
. In their Petition, the individual Plaintiffs assert a claim for actual damages exceeding seventy-five thousand dollars. Plaintiff Everseal Gasket, Inc. asserts a similar claim.
. Fed.R.Civ.P. 15(a).
. id.
. Id.
. Foman v. Davis, 371 U.S. 178, 182, 83 S.Ct. 227, 9 L.Ed.2d 222 (1962).
. Woolsey v. Marion Labs., Inc., 934 F.2d 1452, 1462 (10th Cir.1991).
. Frank v. U.S. West, Inc., 3 F.3d 1357, 1365 (10th Cir.1993).
. Steinert v. Winn Group, Inc., 190 F.R.D. 680, 684 (D.Kan.2000) (citing State Distrib., Inc. v. Glenmore Distilleries Co., 738 F.2d 405, 416 (10th Cir.1984)).
. Lyle v. Commodity Credit Corp., 898 F.Supp. 808, 810 (D.Kan. 1995) (citing Ketchum v. Cruz, 961 F.2d 916, 920 (10th Cir.1992)).
. Bullington v. United Air Lines, Inc., 186 F.3d 1301, 1311 n. 3 (10th Cir.1999).
. K.S.A. 60-513(a).
. See, e.g., Resolution Trust Co. v. Scaletty, 257 Kan. 348, 353, 891 P.2d 1110, 1114 (1995) (applying K.S.A. 60-513(a)(4)).
. See, e.g., Isnard v. City of Coffeyville, 260 Kan. 2, 5, 917 P.2d 882, 885 (1996) (applying K.S.A. 60-513(a)(4)).
. See, e.g., In re Estate of Kout v. U.S., 241 F.Supp.2d 1183, 1191 (D.Kan.2002); Lemmons v. Board of County Comm'rs of Brown County, No. 00-2297-CM, 2002 WL 370227, at *2 (Feb. 21, 2002) (citations omitted).
. Fed.R.Civ.P. 15(c).
. Kidwell v. Board of County Comm’rs of Shawnee County, 40 F.Supp.2d 1201, 1217 (D.Kan.1998) (citing Wilson v. Fairchild Republic Co., Inc., 143 F.3d 733, 738 (2d Cir.1998)).
. Marsh v. Coleman Co., Inc., 774 F.Supp. 608, 612 (D.Kan.1991) (citing Baldwin County Welcome Center v. Brown, 466 U.S. 147, 149 n. 3, 104 S.Ct. 1723, 80 L.Ed.2d 196 (1984)).
. Kidwell, 40 F.Supp.2d at 1216.
. Id. (citations and quotations omitted).
. Marsh, 774 F.Supp. at 612 (D.Kan.1991) (citing 3 James W. Moore & Richard D. Freer, Moore’s Federal Practice, 1115.15[2] at 15-148-15-151).
. Marsh, 774 F.Supp. at 612 (citing Holmes v. Greyhound Lines, Inc., 757 F.2d 1563, 1566 (5th Cir.1985)).
. 6A Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure, § 1497 (2d ed.1990).
. Petition, H 6.
. Id., 11117,9.
. Id.
. Id., 11 9, Wherefore Clause.
. Proposed Amended Complaint, 1140.
. Id., H 18.
. Id., H19.
. Id., 1122.
. Id., 111141-42.
. Id., VU 27-30.
. Id., H 33.
. Id., 1135.
. Id., H1144, 47.
. Id., HI! 44-48.
. Id., 111140.
. Id., Wherefore Clause.
. Id.
. Spillman v. Carter, 918 F.Supp. 336, 340 (D.Kan.1996).
. Kidwell v. Board of County Comm'rs of Shawnee County, 40 F.Supp.2d 1201, 1217 (D.Kan.1998) (quoting Marsh v. Coleman Co., 774 F.Supp. 608, 612 (D.Kan.1991)).
. Petition, 117.
. Id., 115.
. 323 U.S. 574, 65 S.Ct. 421, 89 L.Ed. 465 (1945).
. Although Plaintiffs do not cite or rely upon Tiller, the Court finds it necessary to discuss its application to this case.
. Id. at 580-81, 65 S.Ct. 421.
. Id.
. Id. at 581, 65 S.Ct. 421.
. Id.
. In re Olympia Brewing Co. Sec. Litig., 612 F.Supp. 1370, 1373 (N.D.Ill.1985).
. Id.
. Petition, V 5 (emphasis added).
. See Moore v. Baker, 989 F.2d 1129, 1132 (11th Cir.1993) (holding that a patient’s proposed claims that the defendant surgeon was negligent during and after surgery did not arise out of the same conduct, transaction, or occurrence as the initial complaint alleging that defendant failed to inform her that certain therapy was available as an alternative to surgery; the initial and proposed claims occurred at different times and involved separate and different conduct on the part of the defendant). See also Dahn v. U.S., 127 F.3d 1249, 1251-52, n. 1 (10th Cir.1997) (citing Moore with approval and upholding denial of motion to amend where proposed amended complaint asserted "a distinctly different claim;” taxpayer plaintiff originally brought quiet title
. Moore, 989 F.2d at 1132.
. Petition, 1111 6, 7.
. The proposed nuisance claims concern only the construction of the 4.4 mile bridge, its approaches and embankments. The proposed Amended Complaint alleges: (1) "The construction of the 4.4 mile bridge and its approaches across the channel of Turkey Creek, without an opening sufficient to carry all the water through;” and (2) "The construction of embankments .. without opening sufficient to carry all the water through ... renders such embankments a nuisance ....” Proposed Amended Complaint, UU 41 — 42.
. These claims as they pertain to other factual allegations are discussed below.
. Id., UV 34-36.
. Id., U 44.
. Id., 1147.
. 6A Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure, § 1497 (2d ed.1990). See also Southern Colo. Prestress Co. v. Occupational Safety & Health Review Comm’n, 586 F.2d 1342, 1346 (10th Cir. 1978) (amendment alleging violation of different OSHA standard related back to filing of original complaint where amendment alleged same basic facts, circumstances, and omissions complained of in original complaint); Spillman v. Carter, 918 F.Supp. 336, 340 (D.Kan.1996) (proposed Title VII and ADA claims related back to filing of original claims for wrongful constructive discharge and breach of covenant of good faith and fair dealing, where factual allegations of initial complaint were the same as those giving rise to the proposed claims).
. The proposed Amended Complaint generally alleges that "Defendants’ action constituted an unlawful taking of the Plaintiffs’ property," and that "Defendant deprived Plaintiffs of their property without due process of law and without just compensation in violation of the United State’s [sic] Constitution.” Proposed Amended Complaint, 111148-49.
. The proposed Amended Complaint avers that “Defendant should be held strictly liable for the Plaintiffs' damages,” and that "Defendant cannot injure the property of the Plaintiffs without rendering itself liable for the resultant damage.” Proposed Amended Complaint, VH 45, 46.
. K.S.A. 60-3701(0.
. Beach v. Mutual of Omaha Ins. Co., 229 F.Supp.2d 1230, 1234 (D.Kan.2002) (citations omitted).
. Heslop v. UCB, Inc., 175 F.Supp.2d 1310, 1313 (D.Kan.2001) (citing LeaseAmerica Corp. v. Eckel, 710 F.2d 1470, 1474 (10th Cir.1983); Sithon Maritime Co. v. Holiday Mansion, 177 F.R.D. 504, 508 (D.Kan.1998)).
. Schmitt v. Beverly Health and Rehab. Serv’s, Inc., 993 F.Supp. 1354, 1365 (D.Kan.1998) (citing Beeck v. Aquaslide 'N' Dive Corp., 562 F.2d 537, 540 (8th Cir.1977)).
. See Scheduling Order (doc. 48), H Ill.a.