Lead Opinion
OPINION
The City of Chandler (Chandler) and Jeri-Co Group, Inc. (Jeri-Co) petition for review of the court of appeals’ opinion granting special action relief to AchenGardner, Inc. (Achen-Gardner). Achen-Gardner v. Superior Court,
FACTS AND PROCEDURAL HISTORY
In June 1989, Chandler and D.W.C. Commercial Properties (D.W.C.) entered into a development agreement (Agreement) pursuant to A.R.S. § 9-500.05, which authorizes municipalities to make agreements with prospective developers regarding various conditions and terms of the development, including “the financing of public infrastructure and subsequent reimbursements over time.” A.R.S. § 9-500.-05(F)(1)(g). D.W.C. agreed to develop a retail commercial facility, Sun Tech Center (Sun Tech), and to “cause” certain street improvements made necessary by Sun Tech’s development “to be performed.”
The Agreement further provided that D.W.C. was to award the contract for the off-site improvements “to [the] lowest reasonable bidder; if for some reason Developer rejects bid, then Developer pays the difference between lowest bid and bid selected.” Chandler’s reimbursement obligation was thus limited to the amount of the lowest reasonable bid whether or not that bid was accepted. D.W.C. subsequently assigned its interest in the Agreement to Jeri-Co and is not a party to this action.
In November 1989, Achen-Gardner received a “Notice of Call for Bids,” on City of Chandler letterhead, requiring that bids for performing the off-site improvements be submitted to the Chandler purchasing office no later than December 18, 1989. A representative of Achen-Gardner attended a pre-bid conference at the Chandler purchasing office, and Achen-Gardner later submitted a timely bid. When the bids were opened, Achen-Gardner’s bid of $394,553.87 was approximately $31,000 lower than the only other bid. Chandler’s engineer recommended to Jeri-Co that it award the contract to Achen-Gardner, and Chandler informed Jeri-Co that, pursuant to the Agreement, Jeri-Co would be reimbursed for the off-site improvements only up to the $394,553.87 bid by Achen-Gardner, regardless of who ultimately performed the work.
Jeri-Co refused to award the contract to Achen-Gardner and eventually decided to perform the work itself. After several attempts to obtain the contract, Achen-Gardner brought a special action in superior court seeking an order enjoining the actions of Chandler and Jeri-Co and awarding the contract to Achen-Gardner. The superior court denied Achen-Gardner relief, explaining that “[n]o reason has been shown as to why the developer must comply with the competitive bidding statute in awarding the contract.” The court stated that “the City and the public are protected by the bidding procedures used because reimbursement is limited to the amount of the low bid.” Minute Entry, April 13,1990, at 2.
Achen-Gardner then filed a petition for special action in the court of appeals, which accepted jurisdiction and reversed the decision of the superior court. The court of appeals held that the off-site improvements were “structures,” and therefore the project was subject to Arizona’s competitive bidding laws. Achen-Gardner,
Chandler and Jeri-Co petitioned this court to review the court of appeals’ opinion. We granted review to resolve the following issues:
1. Whether the off-site improvements in question are “structures” for the purpose of Arizona’s competitive bidding laws, A.R.S. § 34-101 et seq.;
2. Whether the off-site improvements are part of the private development or are a public street improvement undertaken by Chandler and thereby subject to the competitive bidding requirements of A.R.S. § 34-201;
3. Whether the court of appeals, in holding that the requirements of Title 34 apply to development agreements entered into pursuant to A.R.S. § 9-500.05, misinterpreted and improperly applied the public policy underlying competitive bidding statutes.
DISCUSSION
A. The Off-Site Improvements Are “Structures” Subject to the Competitive Bidding Laws
Competitive bidding is required only when mandated by statute. Hertz Drive-Ur-Self Sys. v. Tucson Airport Auth., 81
Arizona’s competitive bidding statutes provide, with certain exceptions, that “[e]very agent
We believe that A.R.S. §§ 34-201 and 34-102 must be construed together “in order to derive [their] true meaning.” Secrist v. Diedrich,
In its petition for review, Chandler appears to agree that the competitive bidding laws apply to buildings and structures, but argues—along with amicus Arizona League of Cities and Towns (the League)—that the court of appeals erred in concluding that the street improvements in question are structures. We disagree.
Chandler criticizes the court of appeals’ reliance on Secrist for the proposition that landscaping was covered by the competitive bidding law. See Achen-Gardner,
We believe, however, that the court of appeals correctly concluded that the term “structure” includes the road construction involved in the off-site improvements. The legislature used the term “building” as well as the term “structure” in the competitive bidding laws. Obviously, therefore, a structure must mean something different than merely a “building.” As the court of appeals identified, courts in other states have interpreted structure in various contexts to include improved streets and highways. See, e.g., Village of Niles Center v. Industrial Comm’n,
Finally, the purposes of competitive bidding are “to promote competition, to guard against favoritism, fraud and corruption, and to secure the best work or supplies at the lowest price practicable.” Rollo v. City of Tempe,
B. The Development Agreement Statute and Competitive Bidding
In 1988, the legislature enacted A.R.S. § 9-500.05, which authorizes municipalities to enter into development agreements. Section 9-500.05 provides in relevant part as follows:
A. A municipality, by resolution or ordinance, may enter into development agreements relating to property in the municipality and to property located outside the incorporated area of the municipality.
******
F. In this section, unless the context otherwise requires:
1. “Development Agreement” means an agreement between a municipality and a community facilities district pursuant to § 48-709, subsection C, a landowner or any other person having an interest in real property that may specify or otherwise relate to any of the following: ******
(g) Conditions, terms, restrictions and requirements for public infrastructure and the financing of public infrastructure and subsequent reimbursements over time.
Chandler, Jeri-Co, and the League posit two arguments for the proposition that the development agreement renders the competitive bidding laws inapplicable. First, they argue that the off-site construction was part of the private development and not a public project requiring competitive bidding. Second, they argue that the development agreement law supersedes and provides an exception to the competitive bidding law.
1. The Construction of the Off-Site Improvements Is Not a “Private” Project Exempt from Competitive Bidding
Two factors persuade us that the off-site improvements are public projects and not merely part of the private development. First, the improvements are on public property. Compare Twin State CCS Corp. v. Roberts,
Second, under the development agreement, the city is to reimburse Jeri-Co for most or all of the cost of the improvements from public funds. Cf. Erie County Indus. Dev. Agency v. Roberts,
Jeri-Co additionally argues that the competitive bidding laws do not apply to the transaction before us because Jeri-Co is not an “agent” under the pertinent statutory definition. Section 34-201 requires that every “agent” seek bids for public projects, and § 34-101 defines “agent” as “any county, city or town, or officer, board or, commission thereof, and irrigation, power, electrical, drainage and flood control districts, tax levying public improvement districts, and county or city improvement districts.” Although Jeri-Co is correct that it is not an “agent” as defined by the statute, we are unwilling to accept Jeri-Co’s conclusion that the competitive bidding laws do not therefore apply.
The gist of Jeri-Co’s argument is that a municipality can avoid the competitive bidding requirements by entering into an agreement with a private party whereby the municipality gives the private party control over the letting of the contract for public improvements; because the private party is not an “agent,” the bidding laws do not apply at all. We do not believe the legislature intended the bidding laws to be so easily avoided.
Since they are based upon public economy and are of great importance to the taxpayers, laws requiring competitive bidding as a condition precedent to the letting of public contracts ought not to be frittered away by exceptions, but, on the contrary, should receive a construction always which will fully, fairly, and reasonably effectuate and advance their true intent and purpose, and which willavoid the likelihood of their being circumvented, evaded, or defeated. Stern insistence upon positive obedience to such provisions is necessary to maintain the policy which they uphold.
Secrist,
In short, a municipality cannot alter the public nature of a project for the improvement of public property, to be paid in whole or in large part by public funds, by entering into a development agreement assigning a private party control over the bidding and letting of the construction contract.
2. The Development Agreement Statute Does Not Create an Exception to the Competitive Bidding Laws
In determining whether the development agreement statute supersedes the competitive bidding laws, we are mindful that whenever possible we adopt a construction of a statute that reconciles it with other statutes and gives force to all statutes involved. Pima County v. Maya Constr. Co.,
If the legislature meant for agents to dispense with public bidding on work performed under an A.R.S. § 9-500.05 development agreement, it could and should have made this explicit, given the importance of public bidding. It did not. Unless a statute’s language or effect clearly requires the conclusion that the legislature must have intended it to supersede or impliedly repeal an earlier statute, we will not presume such an intent. Maya Constr. Co., 158 Ariz. at 155,
Despite the absence of conflict between the development agreement law and the competitive bidding law on their face, Jeri-Co and Chandler argue that the public policy behind the development agreement law will be thwarted if compliance with the competitive bidding law is required. They argue that the purpose of the development agreement statute is not merely to expedite the construction of public improvements to facilitate private development—as the court of appeals explained—or to secure the construction of public improvements, but also is to allow municipalities to enhance their economies by attracting private development. They conclude that requiring competitive bidding will jeopardize the willingness of municipalities and developers to enter into development agreements.
We are not convinced that competitive bidding significantly diminishes the legislative incentives to private development embodied in A.R.S. § 9-500.05. Our holding does not prevent municipalities from agree
Finally, Jeri-Co argues that the purpose of competitive bidding, as applied to development agreements, has been served because Chandler’s reimbursement obligation is limited to the amount of the low bid. In focusing exclusively on one purpose of competitive bidding—saving public funds—Jeri-Co ignores the other purposes of bidding: “to promote competition, to guard against favoritism, fraud and corruption, and to secure the best work or supplies at the lowest price practicable.” Rollo,
DISPOSITION
The off-site, street-related improvements are “structures” within the scope of the competitive bidding laws, and the fact that the improvements were provided for in a development agreement does not exempt them from bidding requirements. The court of appeals’ opinion is vacated except for its conclusion granting the injunctive relief requested by Achen-Gardner and awarding Achen-Gardner its costs and attorneys’ fees in the superior court and court of appeals. See Achen-Gardner,
Notes
. The off-site improvements at issue are described in the Agreement as follows:
(a) Construction of an additional thru-lane on Alma School Road with deceleration lanes at the driveways from Warner Road to Mariposa Road. The construction shall include all demolition, grading, paving, curbs and gutters, sidewalks, street lights, street signage, traffic control devices, drainage facilities, utility undergrounding, and landscaping within the right-of-way, in accordance with the City’s design standards. City will be responsible for maintaining all such improvements upon acceptance except for the landscaping which shall be maintained by Developer. Developer agrees to dedicate the necessary right-of-way across the Property at no cost to the City to accommodate the improvements.
(b) Installation of traffic signals at the intersection of Alma School and the Property’s southern most driveway which is north of Warner and at Warner Road and Evergreen Street. City will be responsible for maintenance of the traffic signals.
(c) Right-of-way landscaping along Mariposa, Evergreen, El Monte, and Alma School Road and that portion of Warner east of Evergreen.
(d) Reconfiguration and reconstruction of a new cul-de-sac bubble at the intersection of Mariposa Street and El Monte Drive at the point of abandonment of Mariposa east.
(e) Construction of a deceleration lane on Warner Road at Evergreen Street.
(f) Construction of street lights on Warner Road in accordance with City street light standards.
(g) Construction of a raised median in Warner Road from its current eastern termination point to a point approximately 300 feet east of Evergreen Street.
(h) Reasonable architectural, engineering and landscape architect services necessary to perform items (a) through (g) of this Section 2.1.
. The City of Chandler and its purchasing office are "agents" as defined in A.R.S. § 34-101.
. In addition, courts have construed various improvements other than buildings to be structures. See, e.g., Clark v. Town of Estes Park,
. Cf. Judd Supply Co. v. Merchants and Mfrs. Ins. Co.,
. The court of appeals ordered the superior court to "enjoin Chandler from reimbursing Jeri-Co for the public street improvements unless the competitive bidding laws under Title 34 are followed.” Achen-Gardner,
Dissenting Opinion
dissenting.
I regret that I must dissent.
I agree with the majority that the outside improvements are structures subject to the competitive bidding law. I agree that the construction of the outside improvement is not a private project exempt from competitive bidding.
I dissent, however, because I believe that the requirements in the development agreement statute and the competitive bidding law have been complied with by the procedure followed here. There was notice, there was an open bid, and there was a decision to reject that bid, which the law allows.
Jeri-Co and Chandler complied with the spirit if not the letter of the competitive bidding law. The procedure followed protects the rights of the public. I would affirm the trial court.
This matter was considered by the Court, Chief Justice Feldman, Vice Chief Justice Moeller, and Justices Corcoran and Gordon (retired) participating.
IT IS ORDERED that the Motion for Reconsideration is granted with regard to the Court of Appeals’ injunction order and award of costs and attorneys’ fees in the Superior Court and Court of Appeals to Achen-Gardner, Inc., and denied as to all other issues.
IT IS FURTHER ORDERED that the last sentence in the Opinion in this matter is amended, on page 18, as set forth on the attached page.
IT IS FURTHER ORDERED that Achen-Gardner’s request for attorneys’ fees in this Court is denied.
IT IS FURTHER ORDERED that Achen-Gardner is allowed its costs in this Court in the sum of $84.75.
