659 F. Supp. 2d 1225 | S.D. Ala. | 2009
ORDER
This matter comes before the Court on defendants’ Motion for Partial Summary Judgment as to All Damages Predicated upon Events or Actions Occurring Prior to February 6, 1988 (doc. 224). This Motion has been briefed and is ripe for disposition.
I. Background.
This action involves claims that certain real property located in and around McIntosh, Alabama has been damaged by DDT contamination. The 277 plaintiffs
Upon initiating this lawsuit by filing their Complaint in February 2008, plaintiffs parlayed these basic factual allegations into 11 causes of action asserted by each plaintiff against each defendant, to-wit: negligence, conspiracy, strict liability, trespass, nuisance, intentional misrepresentation, negligent misrepresentation, fraud/fraudulent concealment, constructive fraud, punitive/exemplary damages, and violation of the federal Racketeer Influenced and Corrupt Organizations Act.
In the interests of justice, efficiency and judicial economy, Magistrate Judge Bivins developed and implemented a trial plan pursuant to which the claims of 27 representative “test plaintiffs” would proceed through the discovery and trial processes first, after which a case management plan would be tailored for the remaining plaintiffs. {See docs. 66, 239.) Of the original 27 test plaintiffs, only 17 remain in the case in a test plaintiff capacity at this time, for various reasons. The jury’s verdict as to any test plaintiff will not be binding on any non-test plaintiff. The test plaintiff discovery period has concluded, and the test plaintiff trial is set for jury selection on November 3, 2009, with trial to follow during the November 2009 civil term. In preparation for trial, the parties have collectively filed some 14 motions for summary judgment or partial summary judgment, presenting various legal issues for judicial resolution before trial in an effort to streamline and focus the case.
This Order is confined to defendants’ Motion for Partial Summary Judgment to dismiss all of plaintiffs’ claims predicated on events occurring more than 20 years
II. Analysis.
A. Overview of Alabama’s Rule of Repose.
“Since 1858, causes of action asserted in Alabama courts more than 20 years after they could have been asserted have been considered to have been extinguished by the rule of repose.” Collins v. Scenic Homes, Inc., — So.3d-,(Ala.2009) (citation omitted); see also Moore v. Liberty Nat. Life Ins. Co., 267 F.3d 1209, 1213-14 (11th Cir.2001) (stating that “it is clear that any claim in Alabama courts, brought more than twenty years after the time when it first could have been, is barred if the rule of repose applies”). In Alabama, this rule of repose is a creature of common law, not one of legislative enactment. See Moore, 267 F.3d at 1213 (discussing “Alabama’s judicially created rule of repose”). Its only element is time. See Ex parte Liberty Nat. Life Ins. Co., 825 So.2d 758, 764 (Ala.2002) (noting that “the rule is based solely upon the passage of time”). Application of the rule “is not affected by the circumstances of the situation, by personal
Alabama courts frequently remark on the conceptual similarities between the rule of repose and statutes of limitations. See, e.g., Harrison v. Alabama Forever Wild Land Trust, 4 So.3d 1114, 1117 (Ala. 2008) (“This principle of repose or prescription is similar to a statute of limitations, but not dependent upon one, and broader in scope.”) (citations omitted); Liberty, 825 So.2d at 764 (recognizing that Alabama’s rule of repose “is similar to a statute of limitations”). That said, the differences between Alabama’s rule of repose and a traditional statute of limitations are pronounced and well-defined. The Alabama Supreme Court catalogued the most significant of these differences as follows: “First, the rule is based solely upon the passage of time, ... and is not based upon concepts of accrual, notice, or discovery— concepts that are applicable to statutes of limitation.... Second, the rule is broader than a statute of limitation in that while a statute of limitations generally is procedural and extinguishes the remedy rather than the right, ... repose is substantive and extinguishes both the remedy and the actual action.” Liberty, 825 So.2d at 764-65 (internal quotation marks and citations omitted); see also German ex rel. Grace v. CSX Transp., Inc., 510 F.Supp.2d 630, 632-33 (S.D.Ala.2007) (reciting differences between Alabama’s rule of repose and traditional statutes of limitations).
B. This Court’s Commencement Date Rulings in Related Litigation.
As the parties acknowledge, there is a certain deja vu quality to their briefing concerning the application of Alabama’s rule of repose in this case. That is because this Court previously ruled on this very issue after considering arguments from the same attorneys about the same (or substantially similar) underlying conduct and events, and relating to the same (or substantially similar) theories of liability, in the predecessor Ciba McIntosh litigation styled Jessie Fisher, et al. v. Ciba Specialty Chemicals Corporation, et al., Civil Action No. 03-0566-WS-B. In fact, the Court wrote to the rule of repose issue on two occasions in Fisher. (See docs. 56 and 557 in Civil No. 03-566.) Furthermore, the Court decided an identical rule of repose issue in another McIntosh contamination case brought by the same plaintiffs’ attorneys and styled (at that time) Dorothy Jean Reed, et al. v. Olin Corporation, et al., Civil Action No. 03-0567-WS-B.
In each of these cases, the Court considered the effect, if any, of the federal Com
“In the case of any action brought under State law for personal injury, or property damages, which are caused or contributed to by exposure to any hazardous substance, or pollutant or contaminant, released into the environment from a facility, if the applicable limitations period for such action (as specified in the State statute of limitations or under common law) provides a commencement date which is earlier than the federally required commencement date, such period shall commence at the federally required commencement date in lieu of the date specified in such State statute.”
42 U.S.C. § 9658(a)(1) (emphasis added). The federally required commencement date (“FRCD”) is defined in CERCLA as “the date the plaintiff knew (or reasonably should have known) that the personal injury or property damages referred to in subsection (a)(1) of this section were caused or contributed to by the hazardous substance or pollutant or contaminant concerned.” 42 U.S.C. § 9658(b)(4)(A). If § 9658 applies, its preemptive effect causes the time period for Alabama’s rule of repose to begin running not when the harmful action occurred (ie., when Ciba released DDT into the McIntosh community), but rather when plaintiffs first knew or reasonably should have known that their property was contaminated by DDT (which appears to have occurred long after much or all of the emissions in question). As such, the question of whether CERCLA preempts the commencement date for plaintiffs’ claims against Ciba has profound implications for the temporal scope of the events on which plaintiffs’ causes of actions can rest.
In both Fisher and Reed, the undersigned concluded that the commencement date of Alabama’s rule of repose is preempted by CERCLA. Thus, the Court held that the FRCD marked the commencement date for purposes of assessing whether the plaintiffs’ claims for environmental contamination of their property by chemical manufacturers in McIntosh, Alabama satisfied the 20-year rule of repose. Although Ciba and Olin opposed application of the FRCD to these cases on various bases,
Ciba unveiled this argument at the summary judgment stage in Fisher by maintaining that the undersigned’s prior § 9658 preemption rulings in McIntosh litigation were undermined by the Fifth Circuit’s intervening opinion in Burlington Northern & Santa Fe Ry. Co. v. Poole Chemical Co., 419 F.3d 355 (5th Cir.2005). The Burlington panel reasoned that “[t]he plain language of § 9658 ... refers to state statutes of limitations — not state statutes of repose. This court is bound by that plain language____” 419 F.3d at 364. In Fisher, however, the Court agreed with plaintiffs’ counsel’s unchallenged argument that Burlington is distinguishable and therefore not persuasive to a case involving Alabama’s rule of repose:
“Unlike the case at bar, Burlington concerned application of a state statute of repose, rather than a state rule of repose. Section [ ] 9658 provides that the FRCD preempts limitations periods set by ‘the State statute of limitations or under common law.’ Burlington seized on this statutory language to note that Congress spoke of statutes of limitations but omitted reference to statutes of repose. Here, however, there is no statute of repose, but there is instead a rule of repose created by Alabama common law. Under the plain language of § 9658, Congress intended the FRCD to be afforded primacy over limitations periods set by state common law. What is Alabama’s rule of repose if not a limitations period prescribed by state common law? ... In light of plaintiffs’ unrebutted, persuasive contention that Burlington has no application in the context of a common-law rule of repose, and given the clear language of § 9658 applying the FRCD to limitations periods set by common law, the Court declines defendants’ invitation to overturn its prior determination that the FRCD provides the commencement date for Alabama’s rule of repose in this case.”
Fisher v. Ciba Specialty Chemicals Corp., 2007 WL 2995525, *15 (S.D.Ala. Oct. 11, 2007) (footnote omitted).
C. Defendants’ Contention that CERCLA Preemption is Inapplicable.
Apparently hoping that the fourth time is the charm, defendants endeavor once again to avoid the preemptive effects of CERCLA on the commencement date of Alabama’s rule of repose. This time, Ciba
1. McDonald v. Sun Oil Co.
As a threshold matter, it bears noting that in asserting that “further decisional authority” warrants taking another look at the FRCD/rule of repose interplay, Ciba neglects to mention that post-Fisher authorities include cases decided adversely to Ciba’s position and supporting this Court’s prior rulings on the subject. Most notably, the Ninth Circuit held last year that “the term ‘statute of limitations’ in CERCLA § 309 [42 U.S.C. § 9658] is ambiguous and the legislative history of the section indicates that its meaning includes statutes of repose.” McDonald v. Sun Oil Co., 548 F.3d 774, 779 (9th Cir.2008), cert denied sub nom. Sunoco, Inc. v. McDonald, — U.S.-, 129 S.Ct. 2825, 174 L.Ed.2d 552 (2009). McDonald fully appreciated that “[statutes of limitations and repose are distinct legal concepts with distinct effects.” Id. at 779. Unlike authority cited by Ciba, however, the Ninth Circuit deemed that distinction not to be dispositive. Instead, the McDonald panel opined that “[t]he term ‘statute of limitations’ was ambiguous regarding whether it included statutes of repose when § 309 was enacted in 1986,” inasmuch as contemporaneous legal scholarship routinely flip-flopped in use of these phrases, such that the term had “no plain meaning with respect to whether it included statutes of repose.” Id. at 781.
Turning to the legislative history, the McDonald court found that “Congress’s primary concern in enacting § 309 was to adopt the discovery rule in situations where a plaintiff may lose a cause of action before becoming aware of it — precisely the type of circumstance involved in
2. Rules/Statutes of Repose and Limitations Periods.
Setting McDonald aside for the moment, Ciba’s criticism of the Fisher ruling is rooted in defendants’ contention that “[b]y its plain terms, § 9658 preempts only inconsistent state statutes of limitations.” (Doc. 225, at 8.) Because the Alabama Supreme Court and the Eleventh Circuit have distinguished between statutes of limitations and Alabama’s rule of repose, Ciba continues, § 9658 can have no application here. Both Ciba and one of the opinions it cites fault Fisher for blurring or otherwise failing to appreciate the distinction between statutes of limitation and statutes or rules of repose, suggesting that confusion as to the difference between these devices (one procedural, the other substantive) underlies and ultimately invalidates the Fisher holding.
The Court cannot embrace either Ciba’s reading of the Fisher decision or its interpretation of the relevant CERCLA section. Nowhere in Fisher was Alabama’s rule of repose equated to a traditional statute of limitations. Moreover, the critical statutory language is not framed in terms of statutes of limitation. Rather, the actual text of the relevant provision (and the language upon which Fisher focused) is couched in terms of the FRCD preempting a state “limitations period,” not merely a state statute of limitations. See 42 U.S.C. § 9658(a)(1) (the FRCD preempts the state commencement date set forth in “the applicable limitations period for such action (as specified in the State statute of limitations or under common law)”) (emphasis added). Although Ciba and certain authority it cites apparently view them as synonyms, there is an important difference between the terms “limitations period” and “statute of limitations.” In general usage, the term “limitations period” is commonly understood by Alabama and federal courts to encompass traditional statutes of limitations as well as rales and statutes of repose. Indeed, more than 60 years ago, the Alabama Supreme Court expressly recognized that Alabama’s 20-year prescriptive restriction is a “period of limitation, ... created by the chancery court as a rule of repose.” Meeks v. Meeks, 251 Ala. 435, 37 So.2d 914, 917 (1948) (on rehearing). Furthermore, even a cursory review of case law from this and other jurisdictions reveals legion authorities routinely referring to rules and statutes of repose as creating limitations periods. See, e.g., Tello v. Dean Witter Reynolds, Inc., 410 F.3d 1275, 1279 n. 5 (11th Cir.2005) (“Regarding the definiteness of a statute of repose, the Supreme Court recognized that the purpose of the limitations period is clearly to serve as a cutoff and held that tolling principles do not apply.”) (citation and internal quotation marks omitted); Moore, 267 F.3d at 1217 (“Application of an additional, distinct state limitations period, such as a rule of repose, would contradict our mandate to borrow and apply only one specific limitations period.... ”).
3. The Effect of Section 9658(b)(2).
In so concluding, the Court does not overlook the definition of “applicable limitations period” set forth in § 9658(b)(2). The definitional provision states, “The term ‘applicable limitations period’ means the period specified in a statute of limitations during which a civil action referred to in subsection (a)(1) of this section may be brought.” 42 U.S.C. § 9658(b)(2). Ciba maintains that this definition is dispositive of the FRCD issue because it expressly limits the phrase “applicable limitations period” to periods specified in statutes of limitations. But this argument oversimplifies and distorts § 9658 by reading one subsection in a vacuum without taking it in context of the statute as a whole. See, e.g., Wachovia Bank, N.A. v. United States, 455 F.3d 1261, 1266 (11th Cir.2006) (emphasizing that statutory construction is “a holistic endeavor” and that statutory lan
Undoubtedly, there is a tension between the two provisions. In subsection (b)(2), Congress defined the term “applicable limitations period” solely by reference to “a statute of limitations.” By contrast, in subsection (a)(1), Congress stated that “the applicable limitations period” was “as specified in the State statute of limitations or under common law,” which appears broader than the subsection (b)(2) definition. The discrepancy demonstrates that § 9658 is ambiguous as to the meaning of “applicable limitations period.” To resolve this ambiguity, it is appropriate to consult familiar canons of statutory construction. See, e.g., Garcia v. Vanguard Car Rental USA, Inc., 540 F.3d 1242, 1247 (11th Cir. 2008) (“In construing an ambiguous statute, we also employ canons of construction which embody sound generalizations about Congressional intent.”); CBS Inc. v. PrimeTime 24 Joint Venture, 245 F.3d 1217, 1225 (11th Cir.2001) (where statutory language is not transparent, canons of construction are tools at courts’ disposal for elucidating the meaning of a statute). Two of those principles have particular application here.
First, courts are discouraged “from adopting a reading of a statute that renders any part of the statute mere surplus-age.” Tug Allie-B, Inc. v. United States, 273 F.3d 936, 944 (11th Cir.2001); see also United States v. Aldrich, 566 F.3d 976, 978 (11th Cir.2009) (“statutes should be construed so that no clause, sentence, or word shall be superfluous, void, or insignificant”)
Second, it is also a well-settled canon of statutory construction that “in determining the meaning of an ambiguous statute, we look not only to the particular statutory language, but to the design of the statute as a whole and to its object and policy.” Tug Allie-B, 273 F.3d at 945 n. 9.
Those policy justifications underlying § 9658 fit plaintiffs’ claims against Ciba like a glove. Plaintiffs’ evidence is that they (or at least most of them) were unaware that DDT releases emanating from Ciba’s McIntosh factory were contaminating and devaluing their properties until long after many of those releases took place, and indeed decades after Ciba stopped producing DDT at that location. This is exactly the kind of “delayed discovery” case that Congress had in mind when
III. Conclusion.
In enacting 42 U.S.C. § 9658, Congress indicated that in cases involving property damage caused by a facility’s emission of contaminants into the environment, CERCLA’s federally required commencement date preempts the commencement date of the applicable state limitations period. Courts around the country have commonly used the term “limitations period” interchangeably to refer to both statutes of limitations and statutes/rules of repose. While § 9658 does include a definitional subsection that purports to link “applicable limitations period” exclusively to statutes of limitation, the latter term is not defined and has recently been construed by one federal appeals court as encompassing statutes of repose. Moreover, the statute is ambiguous because another subsection of § 9658 provides that the “applicable limitations period” is “as specified in the State statute of limitations or under common law.” Applying well-worn canons of construction to resolve the ambiguity, the Court declines movant’s suggestions to write the phrase “or under common law” out of the statute or to construe it in a manner that renders it wholly redundant surplusage given the words that precede it. To give effect to that clause, the phrase “or under common law” must have independent meaning, and must mean that an “applicable limitations period” to which the FRCD applies also encompasses limitations periods that (a) are not statutes of limitation and (b) are created under common law. Rules of repose would satisfy those criteria. Under this reading, Alabama’s rule of repose falls neatly within the ambit of an “applicable limitations period” whose commencement date is altered by CERCLA’s preemption provision. This conclusion is reinforced by examination of the statute’s objectives, which confirm that Congress enacted § 9658 for the express purpose of preserv
For all of the foregoing reasons, defendants’ Motion for Partial Summary Judgment As to All Damages Predicated Upon Events or Actions Occurring Prior to February 6,1988 (doc. 224) is denied.
. The court file reflects that defendants did not submit a reply brief concerning this Motion. Therefore, the parties’ only submissions before the Court as to this Motion are their respective principal briefs (docs. 225 & 249).
. By the Court’s tally, 17 plaintiffs have dropped out of this action pursuant to Orders entered on August 25, 2008 (doc. 55), April 27, 2009 (doc. 165), June 24, 2009 (doc. 203), and September 16, 2009 (doc. 277) for various reasons, including settlement, failure to prosecute, acknowledgment that the plaintiff has no viable claims, or simply a stated desire not to proceed further. That leaves 260 remaining plaintiffs.
. Three of those causes of action (intentional misrepresentation, negligent misrepresentation, and fraud / fraudulent concealment) were dismissed as to all plaintiffs at the pleadings stage more than a year ago for failure to comport with the heightened pleading requirements of Rule 9(b), Fed.R.Civ.P. (Doc. 56, at 14-18.)
. The factual allegations and legal theories posited by the parties (including plaintiffs' causes of action and defendants' affirmative defenses) in this action bear striking resemblance to those previously presented in a related federal action before the undersigned styled Jessie Fisher et al. v. Ciba Specialty Chemicals Corporation, et al., Civil Action No. 03-0566-WS-B. After more than four years of extensive litigation (including an unsuccessful bid for class certification), the five Fisher plaintiffs reached a settlement with Ciba on October 19, 2007, shortly before jury selection was to occur. The identities of counsel for both sides in this action are substantially similar to those in the Fisher matter, and the pleadings in this case appear to have their genesis in the corresponding Fisher pleadings, with some being reproduced nearly verbatim.
. Defendants peg the terminus date for Ciba’s production of DDT in McIntosh as being 1965. (Doc. 225, at 3.) Plaintiffs counter that the actual date of cessation was 1966. (Doc. 249, at 10.) This factual dispute is immaterial for purposes of this Order, and has no bearing on the analysis and conclusions set forth herein.
. The parties’ memoranda reveal a factual dispute concerning the extent to which the alleged contamination may have resulted from Ciba’s activities within (rather than outside) that 20-year period. In particular, defendants maintain that plaintiffs’ experts "have attributed much of the contamination at issue in this case to the production years at Ciba” (doc. 225, at 3), while plaintiffs insist that defendants take the testimony out of context and that "releases of DDTr from the Ciba McIntosh facility occurred during the 1950’s, 1960's and continued at least into 2005 and likely to this day” (doc. 249, at 11). The Court need not definitively resolve this disagreement at this time. After all, the Rule 56 Motion is specifically couched as one for partial summary judgment. Defendants do not suggest that application of the Alabama rule of repose would extinguish plaintiffs’ claims in their entirety, but only that portion concerning events, conduct, or activities predating the filing of the Complaint by more than 20 years. Thus, plaintiffs' claims concerning DDT emissions by defendants post-dating 1988 (albeit through non-production means, since Ciba was no longer manufacturing that substance in McIntosh) are not implicated in any way by defendants' Motion. Given the parties’ apparent unanimity that plaintiffs' causes of action would survive, at least in part, even if this Motion were granted, it is unnecessary at this time to quantify precisely the relative fractions of plaintiffs' claims directed at pre-1988 activity and post-1988 activity.
. The Reed litigation is commonly known and referred to by the parties herein as the LaBauve action. Several months after adjudication of the rule of repose issue in that case, the plaintiffs filed an amended complaint deleting Dorothy Jean Reed as a named plaintiff and putative class representative, and naming Carrie Jean LaBauve to replace her in those capacities.
. See, e.g., Reisman v. General Motors Corp., 845 F.2d 289, 291 (11th Cir.1988) ("Except in matters governed by the federal Constitution or by acts of Congress, federal courts in diversity cases must apply the law of the forum state, including its statute of limitations.”); Nett ex rel. Nett v. Bellucci, 269 F.3d 1, 7 (1st Cir.2001) (in diversity context, federal court’s "reliance on state law to resolve action commencement issues raised by state statutes of limitations also applies to state statutes of repose.”).
. When the issue first arose in Reed in late 2003, Olin objected to use of the FRCD on the grounds that § 9658(a) applies only where there are underlying federal causes of action under CERCLA, and not to actions confined to state-law claims of negligence, nuisance and the like. Based on the plain language of the statute and review of applicable case authorities, the Court found that Olin was improperly attempting to engraft additional prerequisites onto § 9658(a), in excess of those established by the terms of the statute. Reed v. Olin Corporation, Civil Action No. 03-0567-WS-M, doc. 36 (slip op.), at 9-12 (S.D.Ala. Dec. 31, 2003). Similarly, when the rule of repose issue was litigated for the first time in Fisher, Ciba’s principal FRCD argument was that § 9658(a)(1) could not retroactively re
. One month after the Fisher ruling concerning the FRCD and Ciba’s rule of repose defense, the Court reaffirmed it in remanding an environmental contamination lawsuit brought against Olin and others by more than 75 plaintiffs (including overlapping plaintiffs in this case) in the McIntosh area. See Abrams v. Olin Corp., 248 F.R.D. 283 (S.D.Ala.2007). In rejecting Olin's post-removal argument that the plaintiffs had fraudulently joined non-diverse individual defendants against whom their claims were barred by Alabama's rule of repose under a Burlington analysis, the Court pointed out that its "reasoning in Fisher applies with equal force here; therefore, the commencement date of plaintiffs’ claims for Alabama rule of repose purposes is not the date of the harmful action, but rather the date on which plaintiffs knew or reasonably should have known that defendants’ actions had damaged their property.” Id. at 290.
. German actually predates this Court’s ruling in Fisher by more than five months; however, Ciba did not bring that decision to the fore prior to the Fisher ruling, and the undersigned was unaware of it at that time.
. For whatever reason, Ciba did not advance this definitional argument in Fisher, but instead does so here for the first time. Ciba's evolving, incremental attacks on the application of the FRCD are not improper, inasmuch as they have been made in different cases and therefore are not subject to the typical strictures governing motions to reconsider rulings made in the same case. See, e.g., Mays v. U.S. Postal Service, 122 F.3d 43, 46 (11th Cir.1997) ("a motion to reconsider should not be used by the parties to set forth new theories of law”); American Home Assur. Co. v. Glenn Estess & Associates, Inc., 763 F.2d 1237, 1239 (11th Cir.1985) (cautioning against use of motion to reconsider to afford a litigant "two bites at the apple”); Gipson v. Mattox, 511 F.Supp.2d 1182, 1185 (S.D.Ala.2007) ("Amotion to reconsider is only available when a party presents the court with evidence of an intervening change in controlling law, the availability of new evidence, or the need to correct clear error or manifest injustice.”) (citation omitted). Nonetheless, the chameleonic nature of Ciba’s arguments in addressing the FRCD issue over the lifespan of multiple related lawsuits is tantamount to taking multiple bites at the apple. The result, unfortunately, is marked inefficiency and needless expenditure of litigant and judicial resources to return on multiple occasions, a la Bill Murray’s hapless character in Groundhog Day, to variants, extensions and permutations of the same arguments on the same issues in one case after another, rehashing the same rulings based on theories that Ciba could have advanced earlier, but did not.
. See also Tomczyk v. Jocks & Jills Restaurants, LLC, 198 Fed.Appx. 804, 813-14 (11th
. See, e.g., In re Davis, 565 F.3d 810, 823 (11th Cir.2009) (explaining that courts assume that Congress used words "as they are commonly and ordinarily understood”); Assa’ad v. United States Attorney General, 332 F.3d 1321, 1329 (11th Cir.2003) ("When construing the meaning of a statute, we begin with the language Congress has chosen and assume that the words used are intended to carry their ordinary meaning.”).
. By its terms, § 9658 applies only to actions "brought under State law for personal injury, or property damages, which are caused or contributed to by exposure to any hazardous substance, or pollutant or contaminant, released into the environment from a facility.” 42 U.S.C. § 9658(a)(1). Ciba does not contend that any of these statutory prerequisites are not satisfied here, nor could it reasonably do so given that the crux of plaintiffs’ claims herein is that they sustained property damage as a result of DDT released from Ciba's McIntosh manufacturing facility into the surrounding community. Thus, the sole disputed question concerning § 9658’s application to this case is whether Alabama's rule of repose constitutes an "applicable limitations period” for purposes of the statute.
. Additionally, it is well established that courts must attempt to read a statute in a manner that harmonizes their provisions and avoids ambiguity, if possible, such that “we read the statute to give full effect to each of its provisions.” Davis, 565 F.3d at 823 (citation omitted); see also Shotz v. City of Plantation, Fla., 344 F.3d 1161, 1173 (11th Cir.2003) (“our task is to read the statute harmoniously, as a whole”). Although not integral to its reasoning or conclusions herein, the Court observes that there is a way to heed this guidance and read the two provisions to alleviate the conflict. The Ninth Circuit approach in McDonald v. Sun Oil Co., discussed supra, would effectuate a harmonious result by interpreting the term "statute of limitations” to include both statutes of limitations and statutes of repose. See McDonald, 548 F.3d at 783 ("it is evident that the term statute of limitations’ in [§ 9658] was intended by Congress to include statutes of repose”). If McDonald is correct and the term "statute of limitations” is construed in § 9658 as including both limitations and repose provisions, that term could also be read as embracing rules of repose, thereby alleviating any inconsistency between the usage of the term "applicable limitations period” in subsections (a)(1) and (b)(2), since both include within their reach "statutes of limitations.” Stated differently, by following the Ninth Circuit’s lead and affording a broad and inclusive meaning to the undefined term "statute of limitations” in § 9658, the apparent inconsistency in the language of the two subsections concerning the scope of "applicable limitations period” could potentially be resolved without voiding either of those provisions. That route would lead to the very same result that the Court reaches here by prompting a conclusion that Alabama's rule of repose does indeed specify an applicable limitations period, the commencement of which is preempted by CERCLA’s FRCD.
. One of the cases cited by Ciba attempted to assign meaning to the "or under common law” language of subsection (a)(1) by indicating that "the common law preempted by the section should likewise be a statute of limitations period specified by common law.” Evans v. Walter Industries, Inc., 579 F.Supp.2d 1349, 1362 (N.D.Ala.2008). Of course, it is true that, at least in certain jurisdictions, there do exist common law statutes of limitations. See, e.g., Gristede’s Foods, Inc. v. Unkechauge Nation, 532 F.Supp.2d 439, 452 (E.D.N.Y.2007) ("the common law statute of limitations for fraud is six years”). But this reading of subsection (a)(1) is unsatisfying because, if "under common law” simply means "common law statutes of limitations,” then that language is wholly redundant because that subsection already refers to statutes of limitations, without differentiating between those enacted by legislatures and those fashioned by judges. Again, the key text of subsection (a)(1) discusses applicable limitations periods "as specified in the State statute of limitations or under common law.” Congress would not need to add the phrase "under common law” to capture common law statutes of limitations because the all-inclusive term "State statute of limitations” was already listed in that same clause. Thus, this approach would read "or under common law” in a manner that is wholly redundant of, and adds nothing to, the previous words in the same clause. Doing so would contravene another applicable canon of construction. See Vance v. Southern Bell Tel. & Tel. Co., 983 F.2d 1573, 1577 n. 9 (11th Cir.1993) (statutes should be interpreted so that "no provision ... be construed to be entirely redundant”) (citation omitted).
. See also APA Excelsior III L.P. v. Premiere Technologies, Inc., 476 F.3d 1261, 1268 (11th Cir.2007) (opining that "statutory language must be read in the context of the purpose it was intended to serve” and "should not be considered in a vacuum and divorced from its underlying purpose”) (citations omitted); London v. Fieldale Farms Corp., 410 F.3d 1295, 1302 (11th Cir.2005) ("in all cases of statutory construction, our task is to interpret the words of the statute in light of the purposes Congress sought to serve”).
. See also Pakootas v. Teck Cominco Metals, Ltd., 452 F.3d 1066 (9th Cir.2006) (ambiguous provision in CERCLA "must be given a liberal judicial interpretation ... consistent with CERCLA's overwhelmingly remedial statutory scheme”) (citation and internal quotation marks omitted); United States v. E.I. Dupont De Nemours and Co., 432 F.3d 161, 185 (3rd Cir.2005) (en banc) ("We note that because CERCLA is remedial legislation, it should be construed liberally to carry out its purpose.”) (citation omitted); Axel Johnson, Inc. v. Carroll Carolina Oil Co., 191 F.3d 409 (4th Cir. 1999) ("Because CERCLA is a comprehensive remedial statutory scheme, ... courts must construe its provisions liberally to avoid frustrating the legislature’s purpose.”) (citation and internal quotation marks omitted); Prisco v. A & D Carting Corp., 168 F.3d 593 (2nd Cir. 1999) ("As a remedial statute, CERCLA should be construed liberally to give effect to its purposes.”) (citations omitted); Atlantic Richfield Co. v. American Airlines, Inc., 98 F.3d 564, 570 (10th Cir.1996) (“because CERCLA is remedial legislation, it should be construed liberally to carry out its purpose”).
. A vital part of the Burlington court’s reasoning was its determination that the plaintiff in that case did not fall within the class of persons that Congress sought to help via the passage of § 9658. The plaintiff in Burlington purchased above-ground storage tanks from the defendant in October 1988. In January 2003, one of the tanks ruptured, spilling hundreds of thousands of gallons of chemicals onto the plaintiff’s property. As the Fifth Circuit put it, "Poole knew about its injury as soon as the tank ruptured,” yet it waited until after the 15-year statute of repose expired before bringing suit. 419 F.3d at 365. These circumstances, the Burlington court found, rendered that case distinguishable from the long-latency disease scenario or the situation in which the time for filing a claim expired before the plaintiff ever learned that a hazardous substance had caused his injury. Thus, Burlington simply did “not involve the delayed discovery ... which § 9658 was intended to address.” Id. at 364-65. By contrast, plaintiffs’ claims against Ciba in the case at bar fall squarely within the delayed discovery fact pattern which Congress enacted § 9658 to address.
. To dispel any potential misunderstanding on this point, the Court is well aware of the admonition that courts must not use their interpretation of Congressional intent as a license to rewrite an unambiguous statute in conformity with that perception. See, e.g., In re Hedrick, 524 F.3d 1175, 1187-88 (11th Cir. 2008) (professing sharp disagreement with the premise "that a court is authorized to interpret a statute contrary to the plain meaning of its words if doing so would, in the court’s view, better further the purpose it thinks Congress had in mind”); Garcia, 540 F.3d at 1247 ("We may consult legislative history to elucidate a statute's ambiguous or vague terms, but legislative history cannot be used to contradict unambiguous statutory text er to read an ambiguity into a statute which is otherwise clear on its face.”); APA Excelsior, 476 F.3d at 1268 (clarifying that legislative history materials are not referenced to contravene Congress’s clear and unambiguous will, but instead to determine Congressional intent). The Court has engaged in no such exercise here. Rather, the undersigned made a specific finding that the subsections of § 9658 create ambiguity as to whether limitations periods created by common law and not embodied in state statutes of limitations are or are not subject to FRCD preemption. It is only for the purpose of resolving that ambiguity that the Court looks to legislative history and the Congressional objectives undergirding the passage of § 9658.