ABLE DEMOLITION, INC v CITY OF PONTIAC
Docket No. 273295
Court of Appeals of Michigan
Submitted March 14, 2007. Decided May 17, 2007.
275 Mich. App. 577
The Court of Appeals held:
- The contractual provision that required Able to obtain letters to proceed is a condition precedent, and Able‘s failure to comply with this clear and unambiguous provision means that it was not entitled to performance by the city in the form of payment for the demolitions at issue.
- Because the provision requiring a letter to proceed before demolition occurred was a condition precedent intended to minimize the city‘s legal liability and protect citizens’ property rights, Able‘s failure to obtain the letters constituted a substantial breach of the contract; therefore, despite the fact that Able substantially performed the central purpose of the contract by demolishing the buildings at issue, it may not maintain an action for damages against the city as a matter of law.
Affirmed.
WILDER, J., concurring, agreed with and joined the majority‘s opinion, except for the part relating to substantial breach.
CONTRACTS — ACTIONS — BREACH OF CONTRACT.
A party who substantially breaches a contract cannot maintain an action for a subsequent breach or failure to perform by the other contracting party.
Penzien & Associates, PLLC (by Charles M. Penzien), for the plaintiff.
Before: SMOLENSKI, P.J., and SAAD and WILDER, JJ.
SAAD, J. Able Demolition, Inc., appeals the trial court‘s grant of summary disposition to the city of Pontiac. For the reasons set forth below, we affirm the trial court‘s ruling.
I. FACTS AND PROCEDURAL HISTORY
On July 1, 2004, Able Demolition contracted with Pontiac to tear down certain abandoned homes. As the below-quoted provisions of the contract make clear, Able was required to obtain specific written permission to proceed before demolishing any building:
IV. SCOPE OF SERVICES
4.01 The Contractor shall diligently perform certain Demolition Services for the City of Pontiac, primarily for the Department of Community Development, as outlined in the attached “Contract Documents.” The term “Contract Documents” means and includes the following: 1) Performance Bond; 2) Bid Tally Sheet; 3) Specifications (including any supplemental specifications and special provisions.)
4.02 The demolition services shall be performed over the course of the one (1) year contract, and shall include, but not be limited to, work as specified on the Purchase Order attached hereto, incorporated hereto marked as Exhibit “A” regarding ________, (address of building)
4.03 The Contractor is an independent contractor and shall not be subject to the specific direction or supervisions of any representative of the City, except in regard to the
determination of the acceptability of the Contractor‘s work product by the Director of the Community Development Department and the Mayor of the City of Pontiac, and in regard to the mandatory requirements that the Contractor get pre-demolition authorization (“Letter to Proceed” described below) from the Director of Law or their designees prior to performance and/or demolition.
* * *
V. PRE-DEMOLITION APPROVAL
5.01 Prior to any performance of services by the Contractor under the terms of this contract and pursuant to a successful bid, the Contractor must, on the date that the anticipated services will be performed (mandatory), contact the Director of Law or their designee to secure written approval to proceed with said services. Upon request for approval by the Contractor, the Director of Law or their designee will provide said Contractor with a “Letter to Proceed” which will specifically grant the Contractor written approval to proceed with said specified services. Prior to any payment under the terms of this contract (Section VI. Compensation), the Contractor must present the “Letter to Proceed” (Director of Law‘s---City Attorney‘s approval documentation) to the Director of Finance of the City verifying that approval to proceed was granted. If the Contractor proceeds without the approval specifically granted in the “Letter to Proceed“, the Contractor shall forfeit any payment for unauthorized services performed as a result of his failure to get said pre-approval “Letter to Proceed“.
* * *
VII. COMPENSATION
7.01 The City agrees to pay the Contractor for the Demolition Services performed pursuant to Paragraph 4.02 in the amount of ____ Thousand ____ Hundred and ____/100 Dollars ($____), itemization required), not to exceed a maximum of One Hundred Thousand and
00/100 Dollars ($100,000.00) for the entire one (1) year contract. If the “Letter to Proceed” for each demolished property is not provided, the Contractor forfeits any payment under the terms of this contract.
* * *
VIII. METHOD OF PAYMENT
8.01 Contractor shall submit monthly “Itemization Statements” for services along with the “Letters to Proceed” in accordance with the provisions of this Contract. The original of said “Itemization Statement and “letters [sic] to Proceed” must be sent to the Director of the Community Development Department. Copies must also be provided to the Finance Director and to the Director of Law and the City of Pontiac.
Able maintains that it demolished numerous buildings under the contract, but that Pontiac refused to pay $42,299 for 11 of the demolitions that Able completed. Able filed a complaint against Pontiac on May 10, 2006, and alleged claims of breach of contract, promissory estoppel, unjust enrichment, and quantum meruit.
In lieu of an answer, Pontiac filed a motion for summary disposition under
II. ANALYSIS
A. STANDARD OF REVIEW
This Court explained in Hamade v Sunoco Inc (R&M), 271 Mich App 145, 165-166; 721 NW2d 233 (2006):
This Court... reviews de novo the proper interpretation of a contract. Clark v DaimlerChrysler Corp, 268 Mich App 138, 141; 706 NW2d 471 (2005). Likewise, whether a contract‘s terms are ambiguous is a question of law this Court reviews de novo. Wilkie v Auto-Owners Ins Co, 469 Mich 41, 47; 664 NW2d 776 (2003). When a contract is unambiguous, it must be enforced according to its terms. DaimlerChrysler Corp v G-Tech Professional Staffing, Inc, 260 Mich App 183, 185; 678 NW2d 647 (2003).1
B. CONTRACT INTERPRETATION
Section 5.01 of Able‘s contract with Pontiac unambiguously requires that, on the day of each demolition,
As our Supreme Court explained in Quality Products & Concepts Co v Nagel Precision, Inc, 469 Mich 362, 375; 666 NW2d 251 (2003):
In interpreting a contract, our obligation is to determine the intent of the contracting parties. Sobczak v Kotwicki, 347 Mich 242, 249; 79 NW2d 471 (1956). If the language of the contract is unambiguous, we construe and enforce the contract as written. Farm Bureau Mut Ins Co of Michigan v Nikkel, 460 Mich 558, 570; 596 NW2d 915 (1999). Thus, an unambiguous contractual provision is reflective of the parties’ intent as a matter of law. Once discerned, the intent of the parties will be enforced unless it is contrary to public policy. Id.
Here, the language of the contract is clear: the contractor, Able Demolition, must obtain a letter to proceed from the city‘s legal department before it can proceed.2
The question here is what is the legal consequence of the contractor‘s failure to comply with this unambiguous contractual obligation.
C. CONDITION PRECEDENT3
Because the contractual language is clear, we need not interpret this contract. Instead, we address the question of the legal consequences of plaintiff‘s failure to comply with its straightforward obligation. We hold that the contract provision that required Able to obtain letters to proceed is a condition precedent and that Able‘s failure to comply with this provision means that it was not entitled to performance by Pontiac, i.e., payment for demolition services. A condition precedent ” ‘is a fact or event that the parties intend must take place before there is a right to performance.’ ” Mikonczyk v Detroit Newspapers, Inc, 238 Mich App 347, 350; 605 NW2d 360 (1999), quoting Reed v Citizens Ins Co of America, 198 Mich App 443, 447; 499 NW2d 22 (1993). “Failure to satisfy a condition precedent prevents a cause of action for failure of performance.” Berkel & Co Contractors v Christman Co, 210 Mich App 416, 420; 533 NW2d 838 (1995).
D. SUBSTANTIAL BREACH
Were we to conclude that the “letter to proceed” provision constitutes a duty or a promise rather than a condition precedent, Able would not be entitled to
We disagree with Able‘s assertion for several reasons. Though the contract contemplated that Able would perform demolition services for the city, the contract here is more than a mere services contract. Rather, the contract is a “legal protocol,” and, as such, the critical aspect of the agreement is that any demolition be accomplished in strict compliance with the procedures designated by Pontiac‘s legal department to minimize the risk of legal liability and the serious violation of citizens’ property rights. A demolition company must ask the city for a letter on the day of each demolition because, in some cases, a property owner may obtain a last-minute temporary restraining order to prevent destruction of a building. Clearly, the city insists on the clause to avoid liability for demolitions that should not,
Affirmed.
SMOLENSKI, J., concurred.
WILDER, J. (concurring). I agree with and join in parts I and II(A), (B), and (C) of the majority opinion.
Notes
A motion under
