194 Mass. 208 | Mass. | 1907
The plaintiff’s bill prays for injunctive relief, and the assessment of damages against the defendants who are alleged to have formed a conspiracy to compel it under penalty of a general strike of its employees to hire only union workmen in the erection of a large building then in process of construction under its contract with the Christian Science Board of Directors, one of the defendants. Upon the principal question, the master to whom the case was referred found in favor of the plaintiff, and his report was confirmed except as to the time when this
In the general scheme of the conspiracy the breaking of the contract
The remaining question relates to the form and scope of the decree. An interlocutory injunction having issued under the first prayer of the bill, the plaintiff fully performed its contract,
Ordered accordingly.
The vote of the defendant corporation was communicated to the plaintiff in a letter from the architect of the corporation, found by the master to have been its agent for the purpose. This letter contained the following sentence : “ I am instructed by the Directors of the First Church of Christ, Scientist, to inform you that it is their wish that you retire immediately from the work at the First Church of Christ, Scientist. It has been decided by them to do the remainder of the work included in your contract in a different manner, commencing at one o’clock today.”
About twelve o’clock on the same day the agent of the defendant corporation ordered the plaintiff to leave the job, and, upon its refusal to do so, this agent called the watchman employed by the directors to police the building, who forcibly, but without actual physical violence, ejected the foreman of the plaintiff from the job and escorted him to the street, and the men employed by the plaintiff followed.