233 S.W.2d 793 | Mo. Ct. App. | 1950
(Sitting by Order of the Supreme Court.)—
These four suits are for commissions for selling and supervising the installation of refrigeration equipment. They were filed in the magis
THE BRYANT CONTRACT
Two of the cases arose out of what has been called the Bryant Contract. In the trial, plaintiffs’ evidence showed that in January, 1946, .the defendant was engaged in selling refrigerating equipment in Independence, Missouri, at 222 No. Liberty. Plaintiff Myers was a salesman and plaintiff Abbott was an electrical engineer, of seven years experience. Defendant employed them to procure business for him by getting customers, who would buy refrigeration equipment. Defendant agreed that if the plaintiffs would get such customers who bought refrigerating equipment and locker boxes, that he would pay each of them 30% of the profit, defendant to retain the other 40%. While working under this arrangement, plaintiff and defendant, in January, 1946, traveling together, went to Latour, Missouri,' where they contacted one William E. Bryant, a groeerman, told him their business, gave him some of defendant’s literature and the cards of plaintiffs, showing one to be a salesman, the other an electrical engineer working for the defendant, who was doing business under the trade name of Record Refrigeration Service. Bryant told them he was interested in installing a refrigerated locker box system if he could lease a building next door to his grocery store. They told him they would come back again later and discuss the matter further. Sometime about the 1st of March, they did go back, drew up some plans and specifications, figured how many locker boxes Bryant could use, their size and how much it would cost to install the system, which amount was $5850.00. They then gave a carbon copy of the “bid” to Bryant, brought the other copy back and delivered it to the defendant, Record, at all times keeping him informed of their progress. Sometime later, defendant Record phoned to a carpenter, who was working for him at DeSoto, Kansas, instructing him to come to Independence and accompany plaintiffs to Latour to figure the cost of the carpenter work necessary in installing the system. This action on defendant’s part was because of a telephoned request by Bryant. The carpenter (Orland Wesley Stodgell, commonly called Budd) testified that he came from DeSoto to Independence at defendant’s orders, accompanied the two plaintiffs to Latour, made some measurements of the building in which the locker box system was to be installed, estimated the cost and returned with plaintiffs to Independence. Those figures were turned over to the defendant. Defendant paid Stodgell for this service.
All this time, while not regularly employed, plaintiffs were intermittently working for defendant, and were available to finish the installation of the locker system at Latour. In June, defendant told them that locker box equipment was difficult to obtain and he was so busy on other jobs in Kansas, that their selling efforts Were terminated and they made no further efforts to obtain purchasers. Plaintiffs went to Latour to see Bryant and his explanation about what had happened was “very vague.” They then discussed it with defendant who told them they were entitled to no commission as they had no connection with the Bryant contract, that Bryant just “happened” to come into his office to see about getting the locker system installed. Plaintiffs offered to go ahead with the supervision of the installation, but this offer was rejected. The total amount of the Bryant deal was $6970.00 and they estimated the profit at $2400.00. The defendant had been fully paid but although payments of the commissions had been demanded from him, he had refused to pay.
On this case, the defendant’s testimony was that the plaintiffs had nothing whatever to do with the procuring of the purchaser of this refrigerating equipment. Defendant admitted sending carpenter Stodgell with plaintiffs but testified he didn’t know where they were going. He also admitted that each of the plaintiffs was around his place of business and did work for him after July, 1946. His evidence further was that Mr. Bryant had seen the advertisement of the defendant in the Kansas City Star and in the telephone classified directory, had voluntarily come to that place of business in Independence, and without any inducement or assistance from the two plain
Where a 'cause at law is tried to the court without a jury, the appellate court on review must, under the statutes, review the case upon both the law and the evidence, as in suits of an equitable nature, and cannot set aside the judgment unless clearly erroneous. While it is a trial de novo in this court, great deference must be paid to the decision of the trial court, who by reason of seeing and hearing the witnesses, was better able to judge their credibility than we, who read only the cold- record.- Union National Bank of Wichita, Kansas v. Lamb (Mo. Sup.) 227 S. W. (2d) 60. Krueger v. Fitzpatrick et al., (Mo. App.) 229 S. W. (2) 255. Consentino v. Heffelfinger (Mo. Sup.), 229 S. W. (2) 546. In re Priest’s Estate and McMurry v. Pickett (Mo. App.) 227 S. W. (2) 474. Key et al. v. Kilburn (Mo. Sup.), 228 S. W. (2) 731. Beery v. Linstorm (Mo. App.), 228 S. W. (2) 814.
We have carefully reviewed the evidence in this case as to the Bryant matter and have arrived at the conclusion that the trial court was correct in rendering judgment for the plaintiffs. We have read and considered the cases cited by appellant and we take no issue with the law. declared therein. Each case, however, was decided on its own particular' set of facts. The facts in none of them were the same as in the case before us; If the court believed the evidence of plaintiffs, he was fully justified in rendering judgment for them. He was not required-to believe defendant’s evidence, nor are we. We believe that plaintiffs were the procuring cause of this sale and are entitled.to their compensation. (See LeCompte v. Sanders (Mo. App.) 229 S. W. (2) 298.) The evidence preponderated in favor of
THE DARNELL CONTRACT
There is only a slight difference in the testimony of 'plaintiffs and defendant in the two claims growing from the Darnell contract, but it is vital. These two plaintiffs procured a contract with one Darnell for the installation of a refrigerated locker box system. The system was installed and Darnell agreed to pay approximately $15,000.00 for its installation. There remained unpaid on that job, the sum of $1485.00. The plaintiffs contended that their commission should be paid as soon as the amount thereof was ascertainable and the defendant contended that it was to be paid only when and if the contract price had been fully paid by the locker box system purchaser. An additional but significant fact was that the defendant, without the knowledge and consent of the two plaintiffs, in writing, released all lien rights he might have to secure the payment of the unpaid balance in the Darnell Locker Box Plant. This release, after listing the refrigerating equipment, states:
“Independence Mo.
October 10, 1946
For value received all of the equipment furnished for the Darnell
Locker Plant together with all labor and services is hereby released from all lein rights.
(Signed) Truman Record.”
The court. rendered judgment for each of the plaintiffs in the Darnell matter for the sum of $428.00 with interest at 6% per annum since August 14th, 1947 or $49.28. The sum of $428.00 was the amount sued for but less than actually proven to be - 30% of the amount admittedly due. . ’ ’
There is no dispute as to the amount still due ¡from the Darnell job upon which the commissions had not been paid. It is merely a question of when those commissions became due. If the testimony of plaintiffs was true, then they were due from defendant when the job was completed and the commissions ascertainable. If defendant’s contention was true, then they were not due until the final payment from the party contracted with had been paid to defendant. The court decided in favor of the plaintiffs.
But there are other factors that should be taken into consideration. The evidence showed that it was the duty of defendant to collect for the equipment. The defendant, by releasing the lien he had upon the Darnell Locker Box Plant, thereby made it more difficult, if not impossible to collect, and this was done without the consent of plaintiffs. This act on the part of defendant showed that he considered the balance due as an asset of his own and over which plaintiffs had no control. Defendants should not be permitted to
In Westinghouse Company v. Tilden, (Nebr.) 96 N. W. 74, a case where the facts were very similar to the one here, the court held that the agent was entitled to his commissions, although the defendant had not collected the price of the property sold. This for the reason that it had been negligent in attempting to collect and had extended the time of payment. The court said:
“If it desired to extend time of its patrons, it had no legal right to ask the plaintiff to await their convenience in the collection of the amount due him as • commission on these notes. We think that the facts amply justify the court in finding that the plaintiff was entitled to recover for the amount of his commission, although not collected .by the defendant because of the negligence of the defendant in making collections.”
In the case at bar, the defendant had released all materialmen and mechanics’ liens. AVe can see no distinction in principle in that action and in extending time for payment. If anything, the relinquishment of a lien would be more apt to make collection difficult than an extension of time for payment.
We have read the case cited by appellant, Rogers-Ruger Co. v. McCord, 115 Wis. 261, 91 N. W. 685, and we think it supports our conclusions herein.
While the evidence showed a suit was pending between defendant and Darnell for the remainder due, this does not alter the situation. All these matters raised a question of fact, were considered by the court, which, from its advantageous position, we think, arrived at the right conclusion and we will defer to its judgment.
The judgment in each of the four cases should be affirmed. It is so ordered.