AAA RESTORATION COMPANY, INC. v. PEEK
A15A0555
Court of Appeals of Georgia
JULY 14, 2015
775 SE2d 627
AAA Restoration Company, Inc. (“AAA“), appeals from an order of the Henry County Superior Court denying AAA‘s motion to stay the lawsuit brought against it by Florence Dianne Peek and to compel arbitration of Peek‘s claims against AAA. AAA contends that the trial court erred in finding that a corporate misnomer as to the arbitral forum designated in the arbitration clause of the parties’ agreement meant that the arbitral forum was unavailable. AAA further argues that even if the parties’ designated arbitral forum is unavailable, the trial court misapplied our decision in Miller v. GGNSC Atlanta, 323 Ga. App. 114 (746 SE2d 680) (2013), to find that this unavailability rendered
Because “[t]he question of whether a valid and enforceable arbitration agreement exists . . . represents a question of law,” we review de novo a trial court‘s order granting or denying a motion to compel arbitration. Yates v. CACV of Colorado, 303 Ga. App. 425 (693 SE2d 629) (2010) (citation and footnote omitted).
The facts relevant to this appeal are undisputed. On July 16, 2013, a fire occurred at Peek‘s residence in Newnan, resulting in the destruction of a significant portion of the home. Approximately three weeks later, Peek signed a written agreement (“the Agreement“) with AAA for the demolition of her fire-damaged residence and for the construction of a new home on the same lot. The Agreement contained an arbitration clause, initialed by both Peek and a representative of AAA, which provides:
All disputes arising from or related to this Agreement shall be resolved by binding arbitration in accordance with the Construction Arbitration Association (of Atlanta) according to their Commercial rules. The locale of any such arbitration shall be Atlanta, Fulton County, Georgia. The dispute shall be heard and decided by a single arbitrator selected pursuant to the applicable arbitration rules.
A dispute eventually arose between the parties and in March 2014, Peek filed suit against AAA asserting claims for rescission, fraud, negligent misrepresentation, violations of the Deceptive Trade Practices Toward the Elderly Act (
Following a hearing on the motion to compel arbitration, the trial court denied the same. At the request of AAA, and over the objection of Peek, the trial court certified its order for immediate review. This Court then granted AAA‘s application for an interlocutory appeal.
1. AAA first argues that, as evidenced by the affidavit of AAA‘s vice president, the arbitration clause simply misidentifies Construction Arbitration Associates, Ltd., as Construction Arbitration Association (of Atlanta). AAA further contends that this Court is free to correct the misnomer in the Agreement‘s arbitration clause and require the parties to arbitrate before Construction Arbitration Associates, Ltd. We disagree.
In support of its argument, AAA relies on the rule that “a mere misnomer of a corporation in a written instrument, or in a law, or in a judicial proceeding is not material or vital in its consequences, if the identity of the corporation intended is clear or can be
Notably, in each of these cases, the corporate entity that had been misidentified was a party to the transaction which gave rise to the litigation, as well as being a party to the lawsuit itself. Thus, in each case the evidence was clear as to which corporate entity the parties to the transaction had intended to name in the contract or deed. And the evidence also showed that the misnomer had resulted from a mutual mistake of the parties to the underlying transaction — i.e., that despite the intent of both parties, the contract or deed had misnamed a corporate entity. Such evidence of the parties’ intent is not present in this case.
The corporate entity that was allegedly misidentified (Construction Arbitration Associates, Ltd.) was not a party to the underlying Agreement and is not a party to this dispute. Additionally, there is no evidence that Peek knew of Construction Arbitration Associates, Ltd., or intended to designate that entity, rather than Construction Arbitration Association (of Atlanta), as the parties’ arbitral forum. Thus, we cannot conclude that all parties to the transaction intended the arbitration clause to name Construction Arbitration Associates, Ltd., as the arbitral forum.
Put another way, the relief sought by AAA is not the correction of a corporate misnomer known to all parties to the Agreement. Instead, AAA is seeking reformation of the agreement to have the name “Construction Arbitration Associates, Ltd.” substituted for the name “Construction Arbitration Association (of Atlanta).” To be entitled to reformation of a contract based upon a
2. Given that the arbitral forum designated in the Agreement (Construction Arbitration Association (of Atlanta)) does not exist, the question is whether the failure of this forum means that the arbitration clause is impossible to perform and therefore unenforceable. AAA argues that the arbitration clause remains enforceable because the contract is governed by the Georgia Arbitration Code,
The Georgia Arbitration Code (“GAC“) provides that the trial court “shall appoint one or more arbitrators” where the arbitration agreement “does not provide for a method of appointment” or where the method for appointing arbitrators set forth in the parties’ agreement either “fails” or “is not followed for any reason.”
Under this test, “where the language of the agreement reflects that the choice of arbitral forum ‘is an integral part of the agreement to arbitrate,’ then the agreement will be considered void if the forum is unavailable.” Miller, 323 Ga. App. at 119 (2), quoting Brown v. ITT Consumer Financial Corp., 211 F.3d 1217, 1222 (II) (A) (3) (11th Cir. 2000). “If, on the other hand, the agreement shows that the selection of a particular forum was merely an ‘ancillary logistical concern,’ [
Both Peek and the trial court rely on our application of the integral term vs. ancillary logistical concern test in Miller to conclude that the designation of the arbitral forum was an integral part of the arbitration clause at issue in this case. Specifically, citing Miller, the trial court found that because the arbitration clause at issue provides that the parties “shall” arbitrate their disputes “in accordance with the Construction Arbitration Association (of Atlanta) according to their Commercial rules,” the parties “contracted to arbitrate only before Construction Arbitration Association (of Atlanta) — an entity that does not exist.” Thus, the trial court concluded that the appointment of a substitute arbitrator “‘would constitute a wholesale revision of the arbitration clause.‘” (quoting Miller, 323 Ga. App. at 124 (2)).3 This reasoning gives far too broad a reading to Miller and fails to acknowledge the unique circumstances of that case — circumstances which do not exist here.
In Miller, we found that the selection of the arbitral forum (the National Arbitration Forum or “NAF“), was an integral term of the arbitration agreement for several reasons. First, the arbitration agreement provided “that any disputes between the parties ‘shall be resolved exclusively through binding arbitration’ conducted ‘in accor- dance with the National Arbitration Forum Code of Procedure, which is hereby incorporated into this Agreement.‘” 323 Ga. App. at 120 (2) (emphasis in original). The NAF Code of Procedure, in turn, provided that “only the NAF” could administer its Code, id., and that if the parties were unable to arbitrate before the NAF or pursuant to the NAF Code (which could be administered only by the NAF), “the parties [were] free to seek legal remedies — i.e., to file a traditional lawsuit.” Id. at 122 (2). We concluded that “[t]he Arbitration Agreement‘s use of the mandatory ‘shall’ and the word ‘exclusively,’ together with its express incorporation” of rules releasing the parties from their obligation to arbitrate if the NAF was not available demonstrated “that the parties did not have a general agreement to arbitrate; rather, they contracted to arbitrate only before the NAF.” Id. at 120-121 (2) (emphasis supplied).
The circumstances in this case are markedly different from those in Miller. As an initial matter, the forum designated by the parties in Miller did, in fact, exist; it was unavailable because the NAF had “entered into a consent judgment under which [it] agreed that it would not administer, process, or in any manner participate in any consumer arbitration” after a certain date. Id. at 116 (punctuation and footnote omitted). In this case, however, the designated forum did not exist. This fact, together
Moreover, although the arbitration clause at issue does employ the mandatory term “shall,” unlike Miller, the parties here did not use the word “exclusively.” Thus, the parties gave no indication that they intended Construction Arbitration Association (of Atlanta) to be the only forum in which they would arbitrate their disputes. This lack of “exclusive intent,” taken together with the fact that Georgia law provides for the appointment of a substitute arbitrator where a designated forum is unavailable, further supports the conclusion that the selection of an arbitral forum was not integral to the parties’ agreement to arbitrate. See Brown, 211 F.3d at 1222 (3) (selection of arbitral forum not an integral part of an arbitration clause which provided that any dispute between the parties “shall be resolved by binding arbitration under the Code of Procedure” of a forum that had become defunct by the time the dispute arose; thus, Section 5 of the FAA empowered the trial court to appoint a substitute arbitrator).
Finally, and most importantly, the arbitration clause at issue did not incorporate, by reference or otherwise, any language indicating that if the designated arbitral forum was unavailable, the parties were not obligated to arbitrate their disputes but were instead free to seek traditional legal remedies. Given the circumstances of this case, including the nonexclusive language of the arbitration clause and the fact that it named a nonexistent forum, we find that the designation of the arbitral forum was merely an ancillary concern of the parties; it was not an integral part of the parties’ agreement to arbitrate any dispute that arose out of their Agreement. See Inetianbor, 768 F.3d at 1350 (III) (A) (the designation of an arbitral forum is an integral part of an agreement to arbitrate only where it appears that the selection “of this forum was ‘as important a consideration as the agreement to arbitrate itself‘“), quoting In re Salomon Inc. Shareholders Derivative Litigation, 68 F.3d 554, 561 (III) (2d Cir. 1995). Accordingly, the trial court erred in finding that the arbitration clause at issue in this case was unenforceable.
For the reasons explained herein, we find that the parties have a binding agreement to arbitrate their disputes. Because the designated arbitral forum is unavailable, the trial court shall on remand exercise its authority under
Judgment reversed and case remanded with direction. Andrews, P. J., and Miller, J., concur.
DECIDED JULY 14, 2015.
Giacoma, Schleicher, Roberts & Daughdrill, Brian E. Daughdrill, Matthew Momtahan, for appellant.
Glover & Davis, Peter A. Durham, for appellee.
Notes
If in the agreement provision be made for a method of naming or appointing an arbitrator or arbitrators or an umpire, such method shall be followed; but if no method be provided therein, or if a method be provided and any party thereto shall fail to avail himself of such method, or if for any other reason there shall be a lapse in the naming of an arbitrator or arbitrators or umpire, or in filling a vacancy, then upon the application of either party to the controversy the court shall designate and appoint an arbitrator or arbitrators or umpire, as the case may require, who shall act under the said agreement with the same force and effect as if he or they had been specifically named therein; and unless otherwise provided in the agreement the arbitration shall be by a single arbitrator.